Availability-based tariff
Availability Based Tariff (ABT) is a frequency based pricing mechanism applicable in India for unscheduled electric power transactions. The ABT falls under electricity market mechanisms to charge and regulate power to achieve short term and long term network stability as well as incentives and dis-incentives to grid participants against deviations in committed supplies as the case may be.[1]
Introduction
ABT Mechanism in Electricity sector in India is adopted since the year 2000 and in a few other countries for pricing bulk power across various stakeholders. ABT concerns itself with the tariff structure for bulk power and is aimed at bringing about more responsibility and accountability in power generation and consumption through a scheme of incentives and disincentives. As per the notification, ABT was initially made applicable to only central generating stations having more than one SEB/State/Union Territory as its beneficiary. Through this scheme, the Central Electricity Regulatory Commission (CERC) looks forward to improve the quality of power and curtail the following disruptive trends in power sector:
- Unacceptably rapid and high frequency deviations (from 50 Hz) causing damage and disruption to large scale industrial consumers
- Frequent grid disturbances resulting in generators tripping, power outages and power grid disintegration.
The ABT scheme has now been expanded to cover the Intrastate systems as well.[2] The power generation or grid capacity has increased substantially in last fifteen years particularly after the Electricity Act 2003 by introduction of competition and unbundling of vertically integrated utilities (SEBs) into separate entities in charge of electricity generation, electricity transmission, and electricity distribution. Deregulation and competition has facilitated participation of private sector on large scale in electricity generation, transmission and distribution. Of late, Indian electricity sector is transforming from perennial deficit to surplus electricity availability.[3] The volume of purchased electricity that could not be transmitted to the buyers due to transmission lines congestion is only 0.3% of the total electricity consumed in the financial year 2013–14.[4] It means that the actual power deficit in India is less than 1% excluding under priced electricity demand. ABT/DSM mechanism needs improvements to address the requirements of all stake holders (including final electricity consumers) for encouraging least cost electricity generation / tariff based on demand verses availability in the grid.[5][6] There is a need of well represented Electric Reliability Organization to involve all the grid participants for framing guidelines for power system operation and accreditation which is presently looked after by the CEA
Bulk power purchasers can buy electricity on daily basis for short, medium and long term duration from reverse e-auction facility.[7] In reverse e-auction, availability based tariff /Deviation Settlement Mechanism (DSM) is applied to settle the failed commitments by the electricity sellers or buyers[8][9] The electricity prices transacted under reverse e-auction facility are far less than the prices agreed under bilateral agreements.[10][11]
For those power generators who have made power purchase agreements (PPA) with Discoms and need not participate in day ahead market (DAM) trading on daily basis, the pecking order among the power generators in a state is called merit order power generation where the lesser variable generation cost electricity producer is selected out of the available generators to maintain the normal grid frequency.[12] IEX is also implementing real-time round the clock trading or one hour ahead trading which will take care of intra day market dynamics.[13] GoI also permitted electricity trading on exchanges with forward and derivatives contracts.[14]
A reverse auction is not a perfect price discovery mechanism or balanced market coupling where single price is applicable to all traders when there is no transmission constraints.[15] However, when the demand is slightly more than the supply, the market discovered price (Rs/KWh) would go steeply high and vice versa. When there is a transmission constraint to export power to a region, the difference between the market-discovered prices of different regions are unreasonably high. In reverse auction trading, the buyers pay a very high price/KWh (many times more than the cost of power from the diesel generator sets) for the incremental purchases.
In 2021, CERC proposed a grid management system where ancillary service providers are fully responsible for maintaining grid frequency within the safe range similar to prevalent practice in developed countries.[16][17] Generators and Discoms are not required to keep the grid frequency in the permitted range under this proposal and the applicable power tariff is delinked from the grid frequency. Observing its detrimental effects on grid safety, it was discontinued after implementing for a few weeks.
ABT details
- What is availability?
Availability, for the purpose of the ABT order means the readiness of the generating station to deliver ex-bus output expressed as a percentage of its ex-bus rated capacity (MCR). Electricity is a commodity whose cost of storing is more than its production cost. The most economical method for electricity generation, transmission and distribution is just in time production where the availability and reliability of the entire system shall be very high to meet the unpredictable electricity demand on minute to minute basis.
- How is availability calculated?
Availability of thermal generating station for any period shall be the percentage ratio of average Sent Out Capability (SOC) for all the time blocks during that period and the rated MCR / SOC of generating station. The SAIDI (System Average Interruption Duration Index) is commonly used as a reliability indicator by electric power utilities.
- Is unified electric grid of India, a smart grid?
During the fiscal year 2014–15, 1,043 billion KWh of electricity (three times that of National Grid) was supplied and met 138,215 MW maximum peak load.[18] The total installed generation capacity is 267,637 MW at the end of fiscal year 2014–15. Its size is of global scale comparable only with EU grid, NERC grid, China electricity grid and Russian electricity grid.[19] However, Indian grid lacks the basic features of smart grid for optimum use of its deployed resources.[20]
- What is the effectiveness criteria of a smart grid?
Generally the top 10% of the unrestricted daily peak load (MW) persists only for 1% (15 minutes) of the total duration and its energy share (MWHr) is of the order of 0.2% of the daily energy supplied. Instead of generating this substantial extra power for a short duration, automatic selective load shedding can be implemented on bulk consumers possessing with standby power facility to eliminate the load spikes without inconvenience to most of the consumers.[21][22] Alternatively, working captive power plants start feeding to the grid by giving break to the captive power supply up to a maximum of 30 minutes duration. The standby generator / captive power owner would be paid for providing grid reserve ancillary services.
With an installed capacity of proper mix of base load and variable load generation capability (excluding low capacity utilisation or secondary power or negative load type on daily basis such as solar, wind, etc. without storage) equivalent to the unrestricted annual maximum peak load, the most effective and economical smart grid shall be able to cater more than 99 percentile duration unrestricted load/demand on daily basis with 100% stable operation of the grid.[23][24] The purpose of smart grid is to supply required electricity at optimum cost with reliability to the final consumers.[25][26]
Scheduling
- Each day of 24 hrs starting from 00.00 hours be divided into 96 time blocks of 15 minutes each.
- Each generating station is to make advance declaration of its capacity for generation in terms of MWh delivery ex-bus for each time block of the next day. In addition, the total ex-bus MWh which can actually be delivered during the day will also be declared in case of hydro stations. These shall constitute the basis of generation scheduling.
- While declaring the capability, the generator should ensure that the capability during peak hours is not less than that during other hours.
- The Scheduling as referred to above should be in accordance with the operating procedures in force.
- Based on the above declaration, the Regional Load Dispatch Centre (RLDC) shall communicate to the various beneficiaries their respective shares of the available capability.
- After the beneficiaries give their requisition for power based on the generation schedules, the RLDC shall prepare the generation schedules and drawal schedules for each time block after taking into account technical limitations and transmission constraints.
- The schedule of actual generation shall be quantified on ex-bus basis, whereas for beneficiaries, scheduled drawals shall be quantified at their respective receiving points.
- For calculating the drawal schedule for beneficiaries, the transmission losses shall be apportioned in proportion to their drawals.
- In case of any forced outage of a unit, or in case of any transmission bottleneck, RLDC will revise the schedules. The revised schedules will become effective from the 4th time block, counting the time block in which the revision is advised by the generator, to be the 1st one.
- It is also permissible for the generators and the beneficiaries to revise their schedules during a day, but any such revisions shall be effective only from the 6th time block reckoned in the manner as already stated.
ABT features
- ABT brings about enhanced grid discipline
- Economically viable power with right pricing
- Promote competition and efficiency
- Encourage use of Merit Order Dispatch / Economic Dispatch in India.
- Addressing grid disturbance issues
- Gaming and avoiding the same
- Requires special meters, remote metering with open protocols and communication mechanisms to read meters timely
- Software that is comprehensive to do calculations, address regulatory issues and modifications as per different Regulatory Commission requirements.
- Interface options to various stakeholders in the ABT mechanism on line to enable effective implementation and benefits to all* Capability of power producers to be able to control their cost of production as well as flexibility in operations
ABT drawbacks
- As per DSM / UI procedure, the incentives and penalty to the grid participants are charged based on the average grid frequency in a time block of 15 minutes duration.[28][29] During a time block, it is normal that frequency goes above rated 50 Hz frequency and comes down below rated frequency as the number of frequency excursions above 50 Hz are more than 100 in a day.[30] Thus the average frequency in a time block remains close to the 50 Hz without giving much benefit in the applicable UI tariff for a Discom who is consuming the surplus power available in the grid or generators with valid scheduling who is reducing the generation when frequency is above 50 Hz. Similarly, the generators and Discoms who are not adhering to grid discipline are not penalised with UI tariff in excess of normal tariff when average grid frequency in a time block is used for fixing UI/DSM charges. Each time block is further needs to be separated into two parts for application of UI charges. One for the duration the frequency is more than 50 Hz whose average frequency is considered for fixing UI/ DSM charges to consume the excess power in the grid or reduce excess power generation. Another for the duration the frequency is less than 50 Hz whose average frequency is considered for fixing UI/DSM charges to reduce over drawl and encourage additional power generation.
- Whenever distribution feeders from a substation are switched on after a break down or scheduled power cut, it should be done only when grid frequency is above 50 Hz such that it does not lead to steep drop in the frequency . The total numbers of feeders switching on, in a day are substantial at national level to cause load (≥ 500 MW) increase on the grid to cause wide fluctuations.
- The incentives and disincentives are prefixed (annually/periodically) by the electricity regulator (CERC) for the variation in the grid frequency which may not reflect the actual situation temporally and spatially on day-to-day basis. There is a need to decide the electricity tariff by the grid participants (generators, discoms, transcos & final consumers) on day-to-day basis for achieving further fine tuning.[5] To correct these anomalies, CERC has proposed 100% sale and purchase of power produced in day ahead market.[31][32]
- The ABT mechanism aims to maintain grid frequency at 50 Hz but does not permit the grid participants to decide the optimum frequency within the permitted frequency band (say 49.20 to 50.80 Hz) on day-to-day basis.[5][33] This is required not to impose additional load shedding/power cuts when frequency is within the safe variation limits.[29]
- Transmission system operator (TSO) is obliged to provide non-discriminatory transmission access to electricity generators and consumers in order to promote competition. ABT mechanism does not bring at par all the grid participants whether in private or central sector or state sector ownership.[34] ABT mechanism does not encourage to install the generating units at advantageous locations to offer least cost electricity to the final electricity consumers.[5] ABT mechanism is suitable in an electricity grid suffering from perennial power shortages to prevent overdrwals but it is not suitable for the grid with surplus electricity generation with non-discriminatory responsibility.[35] CERC regulation on ancillary services operations, are permitting only inter state power generating stations to provide these services which are discriminatory by not allowing rest of electricity generators.[36]
- Every state is conducting independently load management to avoid overdrawal from other states by using mix of generation sources (ex: hydro power or peaking power plants) to adhere to their power drawal commitments on 15 minutes period basis in ABT mechanism. Thus hydro power stations are ending up to cater base load instead of peak load in non-monsoon months also (ex: Kerala, Karnataka, Telangana, HP, J&K, Uttarakhand, etc.).[37] TSO is responsible to ensure the provision of reserves (including spinning reserve for base load power plants by operating in frequency follow mode with upper & lower generation caps) that will allow for sudden contingencies by determining the optimal combination of generating stations and reserve providers for each grid trade bloc.[38][39] The available hydro power stations in a region/grid should be used to cater peaking load only at regional/national level. Using hydro power stations to cater peak load, would improve the peaking load capability of a regional/national grid and maintain safe grid frequency and network stability. The 24 hours duration of a day should be divided into four parts only (i.e. daytime peak load period, daytime off peak load period, nighttime peak load period and nighttime off peak load period) instead of 96 number 15 minutes periods for commercially settling the power transactions to cater better to the peak load requirements within the safe frequency range.
- Many gas turbine power stations are not operating due to perennial natural gas shortage.[40] Recently, many DG sets (large & medium sizes) are also idling throughout the year due to better availability of grid power.[41] Alternatively, these power generation units can be put to use for grid reserve service either with liquid / gas fuels when there is unexpected tripping of operating power plants (five nos of 660 MW stations in a short duration) or tripping of a high voltage transmission line to prevent the grid operation below safe limit.[42][43] This would also allow all the available transmission lines at their full capacity in service without the need to maintain n+1 reserve capacity for meeting any break down and thus accruing savings in high voltage transmission losses.[25][44] The unified national grid stability can also be enhanced further by converting the existing back to back HVDC links into HVAC links bypassing the existing converter stations. These are Chandrapur back to back HVDC converter station, Vizag back to back HVDC converter station, Sasaram back to back HVDC converter station, Vindhyachal back to back HVDC converter station and HVDC Sileru–Barsoor link. The yearly cost of ensuring grid safety would be less than 2 paisa per Kwh for the total electricity generation in India.[45][46][47]
Natural gas transmission
The Petroleum and Natural Gas Regulatory Board (PNGRB) was created in the year 2005 to regulate downstream activities in the petroleum and natural gas sector.[48] There is requirement of natural gas TSO also for imparting optimum use of the gas on hourly basis for meeting peak load in the electricity grid and minimize gas transport distances.[49] The available gas should be stored up to rated pressure in the pipe grid for generating power during peak demand hours on a daily (or more) basis.[50] The natural gas carrying capacity utilization of GAIL pipelines is not exceeding 33%.[51] Thus available limited gas quantity is used to meet the peak electricity loads by all gas based power stations.[52] Gas turbine power plants are operated at 32.6% capacity factor as peaking power plants only in the US though being a surplus natural gas producer with lower price and the natural gas contributes largest portion (35.06%) of the total electricity produced. Also gas should not be transported from a power deficit region to a power surplus region by the gas grid and generated power from gas there shall not be transmitted back to the power deficit region to avoid misuse of the gas and power grid infrastructure. Natural gas TSO would also serve other sectors such as petro-chemical plants, CNG, fertilizer plants, PNG, LNG, etc. as per their hourly requirement in addition to receive gas from various types of natural gas producers and importers.[53][54]
Indian Gas Exchange (IGX) started online gas trading platform for physical delivery of natural gas.[55] Initially, the company has identified Dahej, Hazira and Kakinada as delivery points and will subsequently include Dhabol, Kochi, Ennore and Mundra terminals.[56]
See also
- Transmission system operator
- Regional transmission organization
- National Grid Reserve Service
- EU power grid operator
- EU gas grid operator
- Electricity sector in India
- Energy policy of India
- Load following power plant
- Engine power plant
- Virtual power plant
- Battery storage power station
- Ancillary services (electric power)
- Grid energy storage
- Spark spread
- Power outage
- Fault (power engineering)
- Droop speed control
- Power-flow study
- Dynamic demand
- ISO RTO
- NERC Tag
- OASIS
References
- "ABC of ABT" (PDF). Archived from the original (PDF) on 12 March 2014. Retrieved 14 August 2014.
- "MERC Order on ABT in State of Maharashtra". Retrieved 14 August 2014.
- "Open Access in Indian power sector" (PDF). Retrieved 15 May 2013.
- "Tables 1 & 25; Report on Short-term Power Market in India, 2014-15" (PDF). Retrieved 4 October 2015.
- Electricity online trading in India
- "Integrating European Electricity Markets" (PDF). Retrieved 15 May 2013.
- "Government asks states to purchase short term power through reverse e-auction". Retrieved 5 April 2016.
- "Vidyut Pravah". Archived from the original on 13 October 2016. Retrieved 3 July 2016.
- "IEX Power Trading Process Flow". Retrieved 3 July 2016.
- "Reverse e-auction lowering power prices. Ind-Ra". Retrieved 26 May 2016.
- "Area prices in reverse e-auction trading". Retrieved 26 September 2016.
- "Merit Order Despatch of Electricity for Rejuvenation of Income and Transparency". Archived from the original on 15 June 2021. Retrieved 26 September 2017.
- "Real Time IEX Market Snapshot". Retrieved 3 June 2020.
- "Govt allows electricity derivatives, forward contracts". Retrieved 15 July 2020.
- "Market coupling is beneficial for the market not 1-2 players: PXIL MD". Retrieved 11 May 2021.
- "Explanatory Memorandum to Deviation Settlement Mechanism Regulations, 2021" (PDF). Retrieved 7 January 2022.
- "Central Electricity Regulatory Commission (Deviation Settlement Mechanism and Related Matters) Regulations, 2021" (PDF). Retrieved 7 January 2022.
- "April, 2015 Monthly report, National Load despatch Centre (NLDC)" (PDF). Archived from the original (PDF) on 27 May 2015. Retrieved 25 May 2015.
- Electricity sector in India#Electricity transmission and distribution
- "India can achieve 1,650 billion units of electricity next year, Piyush Goyal". Retrieved 9 July 2016.
- Control of the National Grid (Great Britain)#Frequency Service
- "How Smart Is The Smart Grid?". NPR. Retrieved 17 August 2014.
- Talk:Availability-based tariff
- "National Study by NREL-Pathways to Integrate 175 Gigawatts of Renewable Energy into India's Electric Grid, Vol I" (PDF). Retrieved 7 July 2017.
- "Govt accepts expert panel report on smart electricity transmission system in India". Retrieved 11 March 2023.
- "Status of Power System Transformation 2019" (PDF). Retrieved 3 June 2019.
- B. J. Kirby, Spinning Reserve from Responsive Loads, Oak Ridge National Laboratory, March 2003.
- "Real Time Power Grid Frequency". Archived from the original on 21 January 2020. Retrieved 6 August 2015.
- "Deviation Settlement Mechanism and related matters, CERC, GoI" (PDF). Retrieved 6 August 2015.
- "Typical daily frequency graph of Indian grid" (PDF). Archived from the original (PDF) on 4 March 2016. Retrieved 6 August 2015.
- "CERC pushes for 100% power sale in spot market". Retrieved 5 February 2019.
- "Market Based Economic Dispatch of Electricity: Re-designing of Day-ahead Market (DAM) in India" (PDF). Retrieved 5 February 2019.
- "ENTSO-E Operation Handbook Policy 1 (2009), Load frequency control & performance,(refer last page)" (PDF). Retrieved 6 January 2015.
- "Ease trading of power". Archived from the original on 27 April 2015. Retrieved 27 April 2015.
- "Power Minister Piyush Goyal says power available for free". Retrieved 1 May 2015.
- "CERC regulation on Ancillary Services Operations, 2015". Retrieved 26 August 2015.
- "Daily reports; Power supply position; SRLDC". Archived from the original on 17 July 2014. Retrieved 17 August 2014.
- "Siemens technology is helping achieve smooth grid integration of renewables". Retrieved 27 September 2017.
- "World's First Technology To Measure Electricity Grid Stability Announced". Retrieved 7 October 2017.
- "Monthly generation report of power stations; October, 2015; CEA". Retrieved 13 November 2015.
- "Gensets add up to under half of installed power capacity; August, 2014". Retrieved 13 May 2015.
- Commercial Opportunities for Back-Up Generation and Load Reduction via National Grid, the National Electricity Transmission System Operator (NETSO) for England, Scotland, Wales and Offshore.
- "How to Turn Standby Generation Into Profit-Making Assets". Retrieved 13 March 2015.
- "Modification to existing transmission lines to double the capacity". Retrieved 9 June 2015.
- "Inertia and the Power Grid: A Guide Without the Spin" (PDF). NREL. Retrieved 25 March 2023.
- "Reserve Regulation Ancillary Services (RRAS) Implementation in Indian Grid". Retrieved 9 January 2017.
- "Ancillary Services – Monthly Reports -2016-17". Retrieved 9 January 2017.
- "The Petroleum and Natural Gas Regulatory Board Bill, 2005" (PDF). Retrieved 17 August 2014.
- "Exchange in the works to discover local gas price". Retrieved 27 October 2018.
- "India to test gas-fired plants as 'peakers' to smooth power grid". Retrieved 17 August 2018.
- "Map of GAIL's Natural Gas Pipelines". Retrieved 22 November 2018.
- "Report on Indian electricity grid management requirements". Archived from the original on 22 December 2017. Retrieved 17 December 2017.
- "GAIL to launch portal allowing outsiders to hire its gas pipelines". Retrieved 27 August 2018.
- "Priority allocation of gas to power plants may end". Retrieved 2 November 2018.
- "IGX-Broucher" (PDF). Retrieved 30 August 2020.
- "In a first, India to launch natural gas trading on electronic platform next month". Retrieved 27 April 2020.
External links
- The Perspective Transmission Plan (2016-36) Archived 20 December 2016 at the Wayback Machine
- Summary record of discussions at the first meeting of the grid study committee held on 22 May 2015 in CEA
- Grid maps of southern region Archived 31 July 2021 at the Wayback Machine
- CERC INDIA Website
- Significance of UI Mechanism for Power Pricing
- Introduction to ABT - A White Paper
- ABT Software Archived 6 July 2010 at the Wayback Machine
- COMPASS an Availability Based Tariff software from Engineering Consultants Group Inc