Ganga Water Lift Project
Ganga Water Lift Project (गंगाजल उद्वह परियोजना (Hindi)) is a multi-phase drinking water project in Bihar, India.[1] It is the ambitious project of Chief Minister of Bihar, Nitish Kumar to supply safe drinking water to the water-alarmed towns like Gaya, Rajgir and Nawada, located in southern part of the state through pipeline by lifting water from Ganga river near Hathidah Ghat in Mokama in Patna district.[2] The cost of first phase of this project was initially approved with ₹2,836 crore (US$360 million), the cost was later revised to ₹4,174 crore (US$520 million).[3] Government of Bihar approved the first phase of the coveted Ganga Water Lift Scheme (GWLS) of Water Resource Department (WRD) in December 2019.[4] Ganga Water Lift Project is part of Nitish Kumar's ‘Jal-Jivan-Hariyali Abhiyan' which is aimed to minimize the bad effects of climate change.[5]
Ganga Water Lift Project | |
---|---|
Location | |
Country | India |
State | Bihar |
Coordinates | 25°21′57″N 85°59′14″E |
Technical information | |
Length | 151 km (94 mi) |
Project details
The total length of pipeline that supply Ganga waters to three towns is 190.90 km. The Ganga water is lifted near Hathidah Ghat in Mokama and the pipeline crosses alongside the national highways and state highways. The main pipeline runs from Hathidah to Giriyak via Sarmera and Barbigha. From Giriyak, one pipeline goes to Rajgir, while another to Nawada. The water from Ganga is brought to Motnaje water treatment plant in Nawada district through a pipeline.[6] In Gaya, urban development & housing department (UDHD) will ensure supply of water to the households through pipeline. The Public health & engineering department (PHED) will be responsible for Ganga water supply in Nawada. The length of the pipeline on Hathidah-Motnaje-Tetar-Abgilla pipe route is 150 km.[7]
Third pipeline goes to Manpur (near Gaya) via Vanganga, Tapovan and Jethia. A major water storage point is constructed near Manpur. Similar storage point is to be constructed for other towns too. The project is completed in three phases. Ganga water will be supplied to Gaya, Bodhgaya and Rajgir in the first phase of the project. Nawada town would be covered in the second phase.
Hyderabad-based infrastructure firm Megha Engineering & Infrastructures Ltd (MEIL) completed phase 1 of Ganga Water Lift Project in 2022.[8][9]
References
- "Complete Ganga Water Lift Project within time frame Nitish Kumar".
- "Bihar plans mega water lift project to supply Ganga water for drinking purpose to Gaya, Rajgir, Nawada towns".
- "Ganga water lifting project cost revised".
- "Bihar cabinet approves a Rs 2,836 crore project to supply Ganga water to Gaya, Bodh Gaya and Rajgir".
- "Bihar: Residents of Gaya, Bodhgaya, Rajgir may get piped Ganga water by June 2022".
- "Ganga water to reach Gaya by July 15, officials tell Bihar CM Nitish Kumar".
- "Bihar: Residents of Gaya, Bodhgaya, Rajgir may get piped Ganga water by June 2022".
- "Phase 1 of 4,000-cr Ganga water lift project over: MEIL".
- "MEIL completes Phase-1 of Rs 4,000 crore Ganga floodwater harvesting project in Bihar".