GlaxoSmithKline Carbon Neutral Laboratory

The GlaxoSmithKline Carbon Neutral Laboratory for Sustainable Chemistry is a chemistry laboratory in Nottingham, England. It is located on the Jubilee Campus of the University of Nottingham, and is part of the university's School of Chemistry.[1] The school carries out research at the carbon neutral laboratory, which is the first of its kind in the UK.[2] The construction was majority funded by GlaxoSmithKline, as part of their commitment to green chemistry first announced in 2010,[3] and saw a grant of £12 million provided to the project.[2]

GlaxoSmithKline Carbon Neutral Laboratory for Sustainable Chemistry
Profile view of the GSK Carbon Neutral Laboratory
Alternative namesThe Carbon Neutral Laboratory
General information
StatusCompleted
LocationJubilee Campus
Town or cityNottingham
CountryEngland
Coordinates52°57′01″N 1°10′58″W
Opened27 February 2017
Cost£15.8 million
OwnerUniversity of Nottingham
Technical details
MaterialGerman spruce, Austrian spruce, American red cedar
Floor count2
Floor area4,199 m2 (45,200 sq ft)
Design and construction
Architect(s)Fairhursts Design Group
Structural engineerEngenuiti, Aecom
Main contractorMorgan Sindall

There are five teaching and research laboratories on the first floor,[4] with write-up space for about 100 researchers. The laboratories have been designed to encourage sharing of equipment, in order to be more collaborative than traditional ones.[4] There are also dedicated instrument rooms, including nuclear magnetic resonance, and space to work with schools on outreach activities.[5] The laboratory contains a number of innovations to reduce its environmental impact including a wooden construction, a green roof, solar panels, and extensive use of passive ventilation.[6]

Design and construction

Design

The Logo Of GlaxoSmithKline.

The Carbon Neutral Laboratory was designed to minimise the impact on the environment of its construction and operation. The design of the building is made up of modules manufactured off-site. The building support pillars and trusses are made from a combination of German spruce, Austrian Spruce, and American red cedar.[7] The land used for the construction was previously home to the Raleigh Bicycle Company factory.[8]

The designers used computational fluid dynamics to design the curved roof. This enables ventilation of the building by taking advantage of the prevailing wind. One of the laboratories is also ventilated in this way, to determine the viability of doing so elsewhere. The building also features a green roof, and solar panels that cover 45 per cent of the roof area and provide up to 230.9 kW.[2] The four towers on the roof hide the building's plant equipment. Additionally, a 125-kilowatt biofuel combined heat and power system was built on-site, providing the majority of heat needed for the buildings.[1]

The design of the building did not add any additional parking spaces, and staff are encouraged to walk, cycle or use public transport when visiting the building.[2]

The design delivers power savings of more than 60 per cent over a traditional building design, and will use 15 per cent of the energy that a traditional building would have used for heating. This enables the carbon emitted during the construction phase to be "paid back" over a 25-year period.[1] These savings earned the design multiple awards, including BREEAM Outstanding in 2017.[2]

Construction

Construction of the laboratory began in the spring of 2013 and it was expected to be completed during 2014. Morgan Sindall was the main contractor for the construction of the laboratory.[1] The wooden beams were connected using the "Resix System", by the Simonin Company. This system is completely invisible once construction is completed, and is achieved by the lamination of wood with epoxy and threaded steel bar.[9]

Fire and reconstruction

The 2014 fire broke out as construction was nearing completion.

On 12 September 2014, a fire broke out on the construction site at approximately 8:30 pm. The construction of the building was about 70-per-cent complete at the time.[10][11] Sixty firefighters from five crews attended the scene and gained control, with no injuries or damage to neighbouring buildings reported.[12] An investigation in December 2014 found no associated wrongdoing or arson.[5] It was later announced that the cause was likely an electrical fault with the temporary site power. The report also determined that the rapid spread had been due to the partially completed state of the building, which lacked fire doors or windows and had open voids within the floor. This allowed the fire to self-ventilate very easily.[13] The building also had not at that point installed fire suppression systems.[14]

The original plan was to open the laboratory in late 2014 but this was delayed due to the damage. The main contractor Morgan Sindall cleared the site after the fire and restarted construction.[15] The opening eventually took place on 27 September 2017, with a conference led by Peter Licence, the head of the Carbon Neutral Laboratory. Around 250 guests visited the lab on its opening day, including Martyn Poliakoff, Paul Anastas and Andrew Witty.[16]

Cost

The total cost of the laboratory was £15.8 million. GlaxoSmithKline provided the majority of the funding, with a grant of £12 million. The Wolfson Foundation also donated £750,000.[2]

References

  1. "The Carbon Neutral Laboratory - The University of Nottingham". www.nottingham.ac.uk. Retrieved 16 March 2022.
  2. "GlaxoSmithKline's Carbon Neutral Laboratory for Sustainable Chemistry, Nottingham | BREEAM - Sustainability Assessment Method". 24 November 2017. Retrieved 16 March 2022.
  3. "GSK and University of Nottingham collaborate to create Centre of Excellence for sustainable chemistry | GSK". www.gsk.com. Retrieved 16 March 2022.
  4. "Inspirational timber case studies". www.trada.co.uk. Retrieved 16 March 2022.
  5. "Update on the GSK Carbon Neutral Laboratory for Sustainable Chemistry – Campus News". Retrieved 16 March 2022.
  6. "Case study: The University of Nottingham's Carbon Neutral Chemistry Lab – Social Responsibility and Sustainability". blogs.ed.ac.uk. Retrieved 18 March 2022.
  7. Welch, Adrian (14 August 2017). "GlaxoSmithKline Carbon Neutral Laboratory". e-architect. Retrieved 16 March 2022.
  8. Nanrah, Gurjeet (14 February 2021). "Life at the Nottingham factory making millions of bikes a year". NottinghamshireLive. Retrieved 18 March 2022.
  9. Farah Aida Binti Shahar Sham; Koh Ee Sing; Lin Hui (26 July 2017). "Group Assignment: Prefabricated Timber Framing System". Construction Technology 3 (BLD 90303). Subang Jaya, Selangor, Malaysia: School of Architecture, Building and Design, Taylor's University.
  10. "University of Nottingham labs destroyed in fire". BBC News. 13 September 2014. Retrieved 19 March 2022.
  11. Urquhart2014-09-16T00:00:00+01:00, James. "Blaze destroys Nottingham sustainable chemistry lab". Chemistry World. Retrieved 16 March 2022.
  12. "Nottingham university fire destroys new multimillion-pound chemistry building". The Guardian. 13 September 2014. Retrieved 16 March 2022.
  13. "University of Nottingham laboratory fire caused by electrical fault, says report". BBC News. 9 January 2015. Retrieved 18 March 2022.
  14. Waite, Richard (13 September 2014). "Fire destroys Fairhursts-designed university lab". The Architects’ Journal. Retrieved 19 March 2022.
  15. Ijeh, Ike (16 November 2016). "Carbon Neutral Laboratory: Out of the ashes". Building. Retrieved 18 March 2022.
  16. "The GSK Carbon Neutral Laboratories for Sustainable Chemistry are officially opened". The News Room. 1 March 2017. Retrieved 18 March 2022.
  • Periodic Videos on YouTube (The laboratory features in several videos, as the channel itself is closely tied to the University of Nottingham)
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.