HVDC Gezhouba–Shanghai
The HVDC Gezhouba–Shanghai is a high voltage direct current electric power transmission system between Gezhouba and Nanqiao near Shanghai, China put in service in 1989. The bipolar 1,046-kilometre (650 mi) line is rated at 500 kV and a maximum power of 1,200 MW.
HVDC Gezhouba–Shanghai | |
---|---|
Location | |
Country | China |
Province | Hubei, Anhui |
Coordinates | 30°43′44″N 111°14′39″E 30°57′22″N 121°24′48″E |
General direction | west–east |
From | Gezhouba |
To | Nanqiao |
Ownership information | |
Operator | China Southern Power Grid |
Construction information | |
Manufacturer of substations | ABB |
Contractors | ABB, Siemens |
Construction started | 1985 |
Commissioned | 1989 |
Technical information | |
Type | overhead transmission line |
Type of current | HVDC |
Total length | 1,046 km (650 mi) |
Power rating | 1,200 MW |
AC voltage | 500 kV (both ends) |
DC voltage | ±500 kV |
No. of poles | 2 |
Between 2008 and 2011 the towers of the most part of the line, which were almost guyed towers capable of carrying two conductors, were replaced by new free-standing line towers for 4 conductors in order to install the conductors for the HVDC Hubei-Shanghai on them. This 970 km long line, which is also a bipolar HVDC with an operating voltage of 500 kV runs from Jingmen to Fenjing and has a transmission capacity of 3000 MW.
HVDC Hubei-Shanghai shares also the grounding electrode of HVDC Gezhouba–Shanghai for the Nanqiao terminal. For most of its length, the electrode line of HVDC Gezhouba–Shanghai carries also the electrode line of HVDC Hubei-Shanghei. HVDC Gezhouba–Shanghai carries between Fenjing and Nanqiao also the electrode line of HVDC Hubei-Shanghei in most part of its length on its towers.
The grounding electrode of HVDC Hubei-Shanghai at Chujiahu is also used by HVDC Three Gorges-Changzhou.
Sites
Site | Coordinates |
---|---|
China - Gezhouba Static Inverter Plant ( GeSha) | 30°43′44″N 111°14′39″E |
China - Jingmen Static Inverter Plant ( HVDC Hubei - Shanghai) | 30°49′21″N 112°07′15″E |
China - Chujiahu Grounding Electrode ( HVDC Hubei - Shanghai) | 30°36′26″N 111°54′51″E |
China - Liufangtei HVDC Gezhouba–Shanghai HVDC Hubei - Shanghai Split | 30°43′2″N 112°41′57″E |
China - HVDC Gezhouba - Shanghai (old) - Maiyuan PLC-Repeating Station | 30°18′41″N 116°28′10″E |
China - Fenjing HVDC Gezhouba–Shanghai HVDC Hubei - Shanghai Split | 30°51′53″N 121°00′50″E |
China - Fenjing Static Inverter Plant ( HVDC Hubei - Shanghai) | 30°52′00″N 121°00′58″E |
China - Caijiacun HVDC Gezhouba–Shanghai HVDC Hubei - Shanghai electrode line split | 30°52′04″N 121°01′13″E |
China - Wangjiatiantou HVDC Gezhouba–Shanghai HVDC Hubei - Shanghai - electrode line split | 30°56′54″N 121°24′32″E |
China - Malucun HVDC Gezhouba–Shanghai HVDC Hubei - Shanghai - electrode line split | 30°57′00″N 121°24′01″E |
China - Nan Qiao Static Inverter Plant ( GeSha) | 30°57′22″N 121°24′48″E |
China - Liaoxiangcun HVDC Gezhouba–Shanghai HVDC Hubei - Shanghai - ground electrode | 30°50′52″N 121°38′33″E |
References
- "The Gezhouba–Shanghai HVDC project". ABB. Retrieved 2010-10-01.
- "Gezhouba–Shanghai HVDC transmission project". Siemens. Archived from the original on 2010-06-07. Retrieved 2010-02-21.
External links