Kuril Flyover

The Kuril Flyover is the third largest flyover in Bangladesh. Its foundation stone was laid on 2 May 2010.[1][2][3] Finally the work started in March 2011.[4]

Kuril Flyover
LocaleDhaka
Official nameKuril Flyover
Characteristics
Total length3.1 km
History
Constructed byProject Builders Limited, China Major Bridge Engineering Corporation
Construction start2 May 2010
Construction end4 August 2013
Construction cost3.06 billion taka[1]

The flyover was opened on 4 August 2013.[1]

References

  1. "PM opens Kuril Flyover". bdnews24.com. Retrieved 10 December 2020.
  2. "PM inaugurates Kuril flyover". The Daily Star. Retrieved 10 December 2020.
  3. "PM to open Kuril Flyover on Sunday". Dhaka Tribune. Retrieved 10 December 2020.
  4. "Kuril flyover open for public". Risingbd.com. Retrieved 10 December 2020.


This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.