Münster freight bypass railway

The Münster freight bypass railway (German: Güterumgehungsbahn Münster) is an electrified and mostly single track bypass railway in Münster in the German state of North Rhine-Westphalia. It is only regularly used by freight to avoid Münster Hauptbahnhof.

Münster freight bypass railway
Güterumgehungsbahn Münster
Overview
Line number
  • 2010 (Sudmühle–Mecklenbeck)
  • 2011 (Kanal–Lechtenberg)
LocaleNorth Rhine-Westphalia, Germany
Technical
Line length13 km (8.1 mi)
Track gauge1,435 mm (4 ft 8+12 in) standard gauge
Electrification15 kV/16.7 Hz AC overhead catenary
Operating speed80 km/h (50 mph)
Route map

12.3
Bbf Sudmühle
9.2
Pleister crossover
Münster–Neubeckum line (WLE)
(5.4)
Former local bypass[1]
4.9
Bbf Kanal
Connecting line to Lechtenberg junction
3.2
Münster substation siding
0.0
Bbf Mecklenbeck
Source: German railway atlas[2]

History

The bypass was opened on 5 October 1930[3][4] and is the most recent major railway construction project in Münster. The reason for its construction was that after the First World War there was a great increase freight traffic on the line while Münster Hauptbahnhof had no through tracks dedicated to freight and such tracks could not be built due to lack of space.

Originally, the plan was also to build a two-sided marshalling yard (approximately in the area between the Dortmund–Ems Canal and Kaldenhofer Weg), which would be connected via the bypass to all major routes to Münster. However, this was not implemented for cost reasons.

Electrification of the line was completed on 25 May 1968.

The bypass is proposed to be closed under the Netz (network) 21 project, which would relocate freight traffic on the routes between the North Sea ports and the Ruhr to other lines via Minden, but, because some of the required upgrades have still not been completed, it is still open.

Route

The bypass begins at Bbf (Betriebsbahnhof, “operations” station, which mainly consists of passing loops) Mecklenbeck on the Wanne-Eickel–Münster line. It runs east around the city and ends at Bbf Sudmühle on the Münster–Osnabrück line. In addition, there is also possible to connect to Lechtenberg junction on the Münster–Hamm railway to run over the bypass towards Sudmühle (or vice versa).

Most of the line is built as single track. Only the connection curve to the Hamm line and the section from Pleister crossover to Bbf Sudmühle are duplicated. It has three tracks at Bbf Kanal. The track is built mainly on an embankment and has no level crossings. The Bbf MecklenbeckBbf Kanal section it partially built in a cutting. Along the way there are many bridges, the largest of which crosses the Dortmund–Ems Canal.

Notes

  1. Gussek-Revermann, Anja; Kilian, Heinz (2003). Münster und die Eisenbahn (in German). Ardey-Verlag. p. 121. ISBN 3-87023-183-1.
  2. Eisenbahnatlas Deutschland (German railway atlas). Schweers + Wall. 2017. pp. 40, 134. ISBN 978-3-89494-146-8.
  3. "Line 2010: Mecklenbeck - Sudmühle". NRW Rail Archive (in German). André Joost. Retrieved 19 January 2014.
  4. "Line 2011: Abzw Lechtenberg - Kanal". NRW Rail Archive (in German). André Joost. Retrieved 19 January 2014.

References

  • Anja Gussek-Revermann, Heinz Kilian (2003). Münster und die Eisenbahn (in German). Ardey-Verlag. p. 121. ISBN 3-87023-183-1.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.