List of National Projects of the Ministry of Water Resources of India

Government of India has approved a scheme of National Projects to be implemented during XI Plan(2007-2012) with a view to expedite completion of identified National Projects for the benefit of the people. Such projects will be provided financial assistance by the Government of India in the form of Central grant which will be 90% of the estimated cost of such projects for their completion in a time bound manner.[1]
I. Criteria for selection of National Projects
II. Procedure for inclusion as National project
III.Funding of the National Project
IV. Work plan and time schedule for completion of National Projects
V. Monitoring for National Projects
VI. Review by steering committee
VI. Evaluation and impact assessment

List of Projects so far declared by the Government as National Projects[2]
Sl. No. Name of the Project State Status
1Gosi Khurd Irrigation ProjectMaharashtraProject is under Execution
2Shahpurkandi dam projectPunjabProject is under Execution
3Teesta Barrage ProjectWest BengalProject is under Execution
4Saryu Nahar PariyojnaUttar PradeshProject is under Execution
5Polavaram ProjectAndhra PradeshProject is under Execution
6Lakhwar Vyasi Multipurpose ProjectUttrakhandLakhwar as standalone project (300MW) accepted by TAC. The project was considered by Investment Clearance Committee of MoWR, RD & GR in its meeting held on 24.2.2016.
7Renuka Dam ProjectHPTechnical clearances from CWC is to be obtained by HPPCL. Environment Clearance granted by MoEF & CC was under challenge in

NGT. NGT has cited discrepancies in the requirement of land figures (forest and non-forest, Government and Non-Government)

8Ujh Multipurpose ProjectJ & KDPR under appraisal in CWC/CEA
9Kishau Multipurpose ProjectHP/UttrakhandDPR prepared. MOU for Joint Venture between Govt. Of UK and Govt. Of HP signed. JV SPV yet to be formed.
10Ken Betwa Link ProjectMadhya PradeshUpdated cost estimate of the project(2015-16 PL) was submitted in CWC by NWDA in February 2016 which is

under examination. DPR of Phase- II is yet to be submitted to CWC by NWDA.

11Kulsi Dam ProjectAssamProject is Under appraisal in CWC/CEA. Compliance to the observations of CWC/CEA on the DPR of the project are pending.
12Noa-Dihing Dam ProjectArunachal PradeshProject is Under appraisal in CWC/CEA. Compliance to the observations of CWC/CEA on the DPR of the project are pending.
13Bursar HE ProjectJ & KDPR under preparation by NHPC
14Gyspa HE ProjectHPDPR under preparation by Govt. Of Himachal Pradesh
152nd Ravi Vyas Link ProjectPunjabUnder PFR stage.
16Upper Siang ProjectArunachal PradeshUnder PFR stage

See also

References

  1. "Guidelines For Implementation of National Projects" (PDF). mowr.gov.in.
  2. "National Project Loksabha Question" (PDF). indiaenvironmentportal.org.in.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.