Gordie Howe International Bridge
The Gordie Howe International Bridge (French: Pont International Gordie-Howe), known during development as the Detroit River International Crossing and the New International Trade Crossing, is a cable-stayed international bridge across the Detroit River, currently under construction. The crossing will connect Detroit and Windsor by linking Interstate 75 in Michigan with Highway 401 in Ontario (through the Rt. Hon. Herb Gray Parkway extension of Highway 401). The bridge will provide uninterrupted freeway traffic flow, as opposed to the current configuration with the nearby Ambassador Bridge that connects to city streets on the Ontario side. The bridge is named after Canadian ice hockey player Gordie Howe, whose celebrated career included 25 years with the Detroit Red Wings, and who died two years before construction began.
Gordie Howe International Bridge | |
---|---|
Coordinates | 42°17′15″N 83°05′52″W |
Carries | Road, bike and pedestrian traffic |
Crosses | Detroit River, Canada–United States border |
Locale | Detroit, Michigan and Windsor, Ontario |
Website | www |
Characteristics | |
Design | Cable-stayed bridge |
Total length | 2.5 km (1.6 mi)[1] |
Width | 37.5 m (123 ft)[1] |
Height | 220 m (722 ft)[1] |
Longest span | 853 m (0.53 mi)[1] |
Piers in water | 0 |
Clearance below | 42 m (138 ft)[1] |
History | |
Construction start | June 2018[2] |
Construction cost | CA$5.7 billion (estimated)[1] |
Opening | 2025 (expected)[3] |
Location | |
First proposed in the early 2000s, the project was met with prominent opposition by Ambassador Bridge owner Manuel "Matty" Moroun, who believed competition from a publicly owned bridge would reduce his revenue. A Canadian federal Crown corporation, the Windsor–Detroit Bridge Authority, was established in 2012 to coordinate the bridge's construction and management. Environmental approvals and other permits were approved in the United States and Canada in the early 2010s. Lawsuits by Moroun alleged that the crossing agreement was illegal and the Ambassador Bridge had "exclusivity rights". These lawsuits were denied, along with various attempts to stop property expropriations, allowing the project to continue.
The "Bridging North America" consortium was selected in July 2018 to design, build, operate and maintain the bridge, and construction began that month. The CA$3.8 billion cost of construction will be funded by the Canadian federal government, paid for by bridge tolls. Construction is expected to be completed in 2025.
History
Background
The passage across the Detroit River between the United States and Canada has been an important traffic route since the American Civil War, with ferries transporting goods and people across the river.[4] A railway tunnel (Michigan Central Railway Tunnel) was opened in July 1910, a suspension bridge for road traffic (Ambassador Bridge) opened in November 1929, and a road tunnel (Detroit–Windsor tunnel) opened in 1930.[5]
The Ambassador Bridge is the busiest crossing on the Canada–United States border,[6][7] with nearly 25% of U.S.–Canada border crossings by trucks using the bridge.[8][7]
The Ambassador Bridge has been criticised for its monopoly status (as no trucks are permitted to use the tunnel), private ownership by billionaire Manuel Moroun and poor maintenance record.[9][10] Both the bridge and the road tunnel lack direct highway connections on the Canadian side, with city streets and traffic lights between them and Ontario Highway 401.[11]
Detroit River International Crossing
In the early 2000s, work was begun to investigate the need for a future crossing of the Detroit River by a bi-national partnership of the U.S. Federal Highway Administration, Transport Canada, Ontario Ministry of Transportation and the Michigan Department of Transportation.[12] During development, the project was known as the Detroit River International Crossing and the New International Trade Crossing.[12]
In 2004, a joint announcement by the federal government of the United States and Government of Canada confirmed a new border crossing would be constructed between Detroit and Windsor. A bi-national committee was formed to manage the project.[13][12] An extension of Ontario Highway 401 to the future bridge was also proposed - construction on this extension began in 2011, with the Rt. Hon. Herb Gray Parkway opening in 2015.[14]
The various environmental approvals for the project were approved in both the United States and Canada in 2009.[12][15]
In 2009, the Ohio State Senate passed a non-binding resolution expressing support for the crossing, and urged the Michigan government to pass it, due to Canada being Ohio's largest foreign trade partner, with US$35.8 billion per year in goods traded between Ohio and Canada.[16]
Michigan legislation
In 2010, the Michigan Senate had not approved any authorizing legislation related to the bridge. The Senate Majority Leader Mike Bishop had stated that the Senate would not vote until revenue forecasts were released, reports that were being withheld by the director of the Michigan Department of Transportation. The Michigan House of Representatives had already passed the measure while the bill was called "doomed" in the Senate.[17]
Michigan Governor Rick Snyder supported construction of the new crossing in his first State of the State address on January 19, 2011. His plan would leverage Canadian money to receive a 160 percent match—totaling $2.2 billion—on funding from the Federal Highway Administration in a deal reached the week previous to the speech.[18] In August 2011, Michigan State Senator Mike Kowall, when asked by the Windsor Star if enabling legislation for the bridge would currently pass, replied "absolutely not."[19]
In October 2011, "the Michigan Senate rejected a bill [that] would have allowed the state to accept $550 million from the Canadian government to fund the country's share of the New International Trade Crossing."[20] One commentator, Bill Mann, noted the rejection, saying "Canada calls the new bridge its biggest infrastructure priority and has even offered to pay for the span. But pesky U.S. special-interest politics intrude once again," as he reviewed a number of "U.S. government actions (and inactions) that show little concern about Canadian concerns". Mann drew from a Maclean's article sub-titled "We used to be friends"[21] about U.S.–Canada relations after the Keystone Pipeline, the bridge, and other "insulting" decisions.[22][23]
In 2011, the bridge was tentatively scheduled for completion in 2016, according to the Michigan Department of Transportation. It was estimated the bridge would generate $70.4 million in toll revenues in its first year of operation.[24] The Michigan Senate's Economic Development Committee dealt the plan a setback by turning down a $550 million Canadian appropriation in October 2011,[25] but an agreement announced June 15, 2012 by Canadian Prime Minister Stephen Harper and Michigan Governor Rick Snyder,[26] ensured the project will proceed with the Canadian federal government funding bridge construction, land acquisition in Michigan and the construction of Interstate 75 on-ramps. The Canadian contribution will be repaid from bridge tolls collected on the Canadian side, and no tolls will be charged on the U.S. side.[27] The crossing agreement also included community benefits for residents on both sides of the Detroit River, including improvements to local neighbourhoods affected by bridge construction.[28]
Approvals and land acquisition
On April 12, 2013, the US Department of State and the Obama administration granted Michigan the permit required to build the bridge, allowing construction to go forward once details were finalized.[29][30][31] In May 2014, the United States Coast Guard issued a bridge permit, the final federal approval required.[12] A Canadian federal Crown corporation, the Windsor–Detroit Bridge Authority (WDBA) began work in July 2014 to coordinate the bridge's construction and management.[12][32]
The Canadian government allocated $25 million to begin land acquisition on the Detroit side on May 22, 2013.[33] In January 2015, Parsons Corporation was named the general engineering consultant for the bridge. On February 18, 2015, Minister of Transport Lisa Raitt announced Canada would fund the construction of a customs plaza on the U.S. side of the bridge in Detroit's Delray neighborhood. The plaza will have a budget of around $250 million, and be recouped through tolls. The U.S. Department of Homeland Security will provide a first-year investment of $150 million, and an "ongoing annual requirement" of $50 million, to cover the plaza's operational and staffing costs.[34][35]
On May 14, 2015, during an event attended by Canadian Prime Minister Stephen Harper, it was officially announced that the bridge would be known as the Gordie Howe International Bridge after Canadian ice hockey player Gordie Howe, whose celebrated career included 25 years with the Detroit Red Wings.[36]
In July 2015, WDBA began work procuring a consortium who would design, build and finance the construction of the bridge, as well as operate and maintain it over a 30 year period.[12] The cost of building the Gordie Howe International Bridge escalated by CA$3.5 billion as the value of the Canadian dollar declined in 2015–2016. In January 2016, it was reported, due to exchange rates and increased inflation, costs could rise to CA$4.8 billion.[37]
In July 2016, it was announced many properties that would be required to build the bridge were still in the hands of private landowners. Some properties on the American side of the river were owned by Manuel Moroun, owner of the Ambassador Bridge.[38] An estimated 30 of the 900 properties needed were considered to be problems if the owners resist selling.[39][40] In July 2016, the CBC reported Dwight Duncan, the former finance minister for Ontario had advised the Government of Canada to consider buying the Ambassador Bridge from Moroun.[41]
In a joint statement released after a meeting between newly elected U.S. president Donald Trump and Canadian prime minister Justin Trudeau on February 13, 2017, the two governments reiterated the support of the "expeditious completion" of the project. Construction started in 2018 after a project contractor was selected in 2017.[42] This is listed as a priority infrastructure project by the Donald Trump administration.[43]
In June 2017, the City of Detroit sold 36 city-owned parcels of land, underground assets and five miles of city-owned streets in the Delray neighborhood, which is the site of the U.S. Customs facility. A $33 million neighborhood improvement fund for the neighborhood was set up. Residents of the area can stay and have their home renovated or move to a renovated home in a different neighborhood.[44]
In May 2018, the Michigan Court of Appeals ruled against Moroun's attempt to stop expropriations on the Michigan side of the river, allowing construction of the U.S. plaza to begin.[45]
Contract award
On July 5, 2018, WDBA was announced the consortium "Bridging North America" had been awarded the bridge contract, using a design, build, finance, operate and maintain structure.[46] The consortium consisted of AECOM for design; Dragados Canada, Fluor Corporation, and Aecon for construction; and ACS Infrastructure, Fluor, and Aecon for operations and maintenance.[47][48] Following construction, Bridging North America will receive monthly payments for operating and maintaining the bridge over a 30 year period.[49]
Construction
Construction began on July 17, 2018 with groundbreaking by Minister of Infrastructure Amarjeet Sohi and Michigan Governor Rick Snyder.[50][51] On September 28, 2018, the WDBA announced the project would cost CA$3.8 billion to construct,[52] part of a CA$5.7 billion contract with Bridging North America.[49] The bridge was to be completed by the end of 2024.[52]
In 2019, preparatory work for major construction continued, with cleaning of contaminated land.[53] $20 million of community benefits for local residents on both sides of the Detroit River was also announced.[54] In 2020, the design of new pedestrian bridges over Interstate 75 were unveiled.[55] In January 2021, foundation work for the bridge towers had been completed, and construction of the 220 m (720 ft) bridge towers was underway.[56] In March 2021, work began to construct the buildings in the Canadian port of entry.[12]
By March 2022, legs of the bridge on both sides of the Detroit River had been completed, with road deck construction underway.[12][57] By November 2022, over 150 m (490 ft) of the bridge towers had been completed. The WDBA noted that the bridge could open in 2025 owing to delays caused by the COVID-19 pandemic, however the builder of the bridge noted they were pushing for a 2024 opening date.[58]
By May 2023, cables used to hold up the future bridge deck were starting to be installed.[59] In August 2023, the US bridge tower reached its final height of 220 m (720 ft), with the Canadian bridge tower to be completed a few weeks later.[60]
Design
The bridge design is by chief bridge architect of AECOM, Erik Behrens.[61][62] It will have two "A"-shaped bridge towers (220 m (720 ft) high) built on the banks of the Detroit River, six lanes for automotive traffic, and a bicycle and walking path. It will be 2.5 km (1.6 mi) long. It will have the longest main span of any cable-stayed bridge in North America at 853 m (2,799 ft).[63]
On the U.S side, the port of entry will encompass 68 hectares (170 acres) with border inspection facilities, directly connecting to Interstate 75 with dedicated highway ramps.[64][65] On the Canadian side, the port of entry will encompass 53 hectares (130 acres) with border inspection facilities, toll collection and bridge maintenance facilities. It will directly connect to Ontario Highway 401.[64] The bicycle and walking path will connect to new and existing trails as well as bike lanes on both sides of the Detroit River.[66]
With traffic crossing the border expected to grow from 18,500 vehicles a day in 2016 to 26,500 by 2025, the Gordie Howe International Bridge will provide an orderly flow of people and goods between the two countries.[24] Transport Canada retained the engineering firms, Morrison Hershfield, Davis Langdon, and Delcan to develop cost estimates for right of way and utility relocation; design and construction; and operation and maintenance on the Canadian side of the crossing.[67]
Artwork
The project will include several pieces of public art. During construction, artworks by local artists were placed on the construction facade that builds the bridge towers.[68][60] The Canadian bridge towers were undertaken by artists from the Walpole Island First Nation and the Caldwell First Nation, with the American bridge towers undertaken by Roberto Villalobos, an artist from Southwest Detroit.[69][60]
A piece by artist Sara Graham involves cast concrete patterns on the outside of a maintenance building.[70] Other artworks are being developed, with artist Michael Belmore creating a 2.7 m (8.9 ft) high sculpture that recognizes and celebrates First Nations[71][72] and another artwork being commissioned to commemorate the Underground Railroad.[73][74] Another artist will be commissioned to design architectural lighting for the bridge.[75]
Connections
Rt. Hon. Herb Gray Parkway
In Canada, the bridge will connect to an extension of Highway 401, locally named the Rt. Hon. Herb Gray Parkway, on its east side.[64] The parkway is below-grade and has six through-lanes. It follows (but does not replace) Talbot Road and Huron Church Road from a new interchange at the former end of Highway 401 to the E. C. Row Expressway, where it runs concurrently westward for 2 km (1.2 mi). From there, it turns northwest and follows a new alignment to the border.[76] The parkway also features 300 acres (1.2 km2) of green space and over 20 kilometres (12 mi) of recreational trails, with seven bridges and two tunnels separating the trails from roads.[77][78] Full construction of the parkway began in 2011,[79] and was completed in November 2015 at a cost of CA$1.4 billion.[80][81]
Construction of the Rt. Hon. Herb Gray Parkway that links to the bridge on the Canadian side was hampered by concerns it could affect Ontario's last known habitat of Butler's garter snakes.[82] During the construction process, biologists relocated the snakes (including eastern fox snakes, and the garters—of which there were a larger number than originally thought), with their new habitats protected by a specially-designed above and below-ground fencing system along affected portions of the E. C. Row Expressway.[83]
Interstate 75
In the United States, the bridge will connect to Interstate 75 with dedicated ramps. 3 km (1.9 mi) of the highway will be rebuilt and widened, local roads will be improved and new pedestrian bridges will be built across the highway.[65][84] Noise walls will also be built to mitigate impacts to the Southwest Detroit neighbourhood.[85]
Opposition
The most vocal opposition to the new crossing came from American billionaire Manuel "Matty" Moroun (1927–2020), owner of the nearby Ambassador Bridge. He sued the governments of Canada and Michigan to stop its construction, and released a proposal to build a second span of the Ambassador Bridge (which he would have owned) instead.[86] Critics suggest that Moroun's opposition was fueled by the prospect of lost profits from duty-free gasoline sales, which are exempt from about 60 cents per gallon in taxes even though the pump price to consumers is only a few cents lower.[87]
In early June 2011, the conservative advocacy group Americans for Prosperity posted bogus eviction notices on homes in Detroit's Delray district. With the words "Eviction Notice" in large type, the notices told homeowners their properties could be taken by the Michigan Department of Transportation to make way for the proposed new bridge. The group's state director said the fake notices were intended to get residents to contact state lawmakers, to ask them to vote against the bridge project.[88] Americans for Prosperity charged that the project would be a waste of taxpayer money if toll revenues did not cover debt service.[89][90]
In July 2011, the Canadian Transit Company, the Canadian side of Moroun ownership of the Ambassador Bridge,[91] began running advertisements against the DRIC proposal, calling it a "$2.2 billion road to nowhere".[92] The phone number listed for Canadian Transit Company forwarded to a phone number in Michigan,[92] and the Canadian Transit Company previously held its 2011 annual meeting at the offices of the Detroit International Bridge Company.[93] MPP Dwight Duncan advised that he was investigating whether or not the ads violated Ontario's election laws, which disallow public spending by foreign lobbyists.[92]
In 2012, Moroun spent more than US$30 million promoting a proposed amendment to the Michigan Constitution that, had it passed, would have required approval of both the voters of Detroit and the voters of Michigan in statewide elections to build the bridge.[94] NPR station Michigan Radio aired a story on November 2, four days before the vote, which indicated the amendment's "seemingly neutral language masks a very specific—and bitter—political battle".[95] The ballot proposal was defeated by a 60 percent to 40 percent margin, paving the way for the project to proceed.[96]
In the 2010s, Moroun undertook several lawsuits alleging that the 2013 crossing agreement was illegal (and should not have been approved by the U.S. State Department),[97] as well as alleging that they had exclusive rights to a span connecting Detroit to Windsor.[98] In 2015, the Supreme Court of the United States declined to hear a challenge by Moroun regarding the choice of location for the bridge.[99] In June 2016, the last of these lawsuits by Moroun was dismissed, allowing the project to continue.[97]
In 2018, the company aired television ads on Fox & Friends asking President Donald Trump to cancel the project.[100] In late 2019, Trump signed the first U.S. funding for customs and border protection for bridge into law.[101] In May 2018, the Michigan Court of Appeals ruled against Moroun's attempt to stop expropriations on the Michigan side of the river, allowing construction of the bridge to begin.[45]
Naming
Snyder stated that he had "not [been] crazy" about naming the bridge the Detroit River International Crossing, noting that "DRIC" was intended only to be the name of the commission sponsoring the bridge, and not the bridge itself. Concerns were also acknowledged that the abbreviated name was too close to that of the Detroit International Bridge Company (DIBC)—that would be too sensitive given its objections to the project.[102] Sometime afterward, the working name for the project became the New International Trade Crossing (NITC), garnering the endorsement of 139 organizations and individuals.[103] It was under the NITC name that the project was approved by the U.S. State Department on April 12, 2013.[31]
In late 2010, David Bradley, president of the Ontario Trucking Association, proposed naming the bridge in honor of Canadian professional ice hockey player Gordie Howe, who played the bulk of his career for the Detroit Red Wings. The naming was supported by a number of Canadian politicians, along with Howe's son Marty—who felt the name would have been symbolic of him having come from Canada to spend his NHL career in Detroit.[102][104]
On May 14, 2015, during an event attended by then-Canadian Prime Minister Stephen Harper, it was officially announced that the bridge would be known as the Gordie Howe International Bridge.[36][105] Howe, 87 and in ailing health, did not attend the ceremony. Later, when asked by his son what he thought about the naming, Howe remarked "That sounds pretty good to me."[106] Howe died one year later on June 10, 2016.[107][108]
See also
- Detroit–Windsor Tunnel, a car-van-bus link between the two cities
- Blue Water Bridge, connecting Port Huron, Michigan, to Sarnia, Ontario
- Infrastructure policy of Donald Trump
- List of bridges in Canada
References
- "Gordie Howe Bridge By the Numbers". Archived from the original on January 30, 2022. Retrieved July 10, 2021.
- Battagello, Dave (April 12, 2013). "New Detroit crossing seven years away". Windsor Star. Archived from the original on April 12, 2014. Retrieved August 4, 2013.
- Molnar, Dale (November 30, 2022). "Gordie Howe Bridge completion date likely in 2025, later than initial estimates: officials". Canadian Broadcasting Corporation. Archived from the original on March 30, 2023. Retrieved March 30, 2023.
- Mason, Philip P. (1987). The Ambassador Bridge: A Monument to Progress. Detroit: Wayne State University Press. pp. 31+. ISBN 978-0-814-31840-9.
- Hanson, Adriane & Dow, Kathleen (2005–2007). "Finding aid for Ambassador Bridge Records, 1927–1930". Special Collections Library. University of Michigan. Archived from the original on October 6, 2014. Retrieved June 3, 2014.
- "Chapter 4: The Watery Boundary". United Divide: A Linear Portrait of the USA/Canada Border. The Center for Land Use Interpretation. Winter 2015. Archived from the original on June 20, 2018. Retrieved July 24, 2023.
- "Michigan voters could nix new bridge to Canada". CBC News. November 6, 2012. Archived from the original on July 24, 2023. Retrieved July 24, 2023.
In 2010, it was reported that 28,814 trucks crossed the privately owned Ambassador Bridge on a daily basis. It is the busiest border crossing in North America. According to the Ambassador Bridge, more than 25 per cent of all merchandise trade between the U.S. and Canada crosses that span. Almost $500 million US in trade and an average of 10,000 commercial vehicles pass daily over the Ambassador Bridge.
- "Road Transportation". Transport Canada. March 5, 2021. Archived from the original on July 24, 2023. Retrieved April 11, 2022.
- Staff (July 12, 2012). "The Proposed New US-Canada Bridge: Guide to the Controversy". Detroit Free Press. Archived from the original on October 17, 2015. Retrieved July 24, 2023.
- Lawrence, Eric (October 15, 2015). "Ambassador Bridge rains concrete chunks down on Windsor". Detroit Free Press. Archived from the original on February 9, 2022. Retrieved November 28, 2021.
- Jarvis, Anne (November 2, 2017). "Jarvis: Ambassador Bridge wants to be connected to the parkway". Windsor Star. Archived from the original on May 15, 2021. Retrieved July 24, 2023.
- "Chronology". Gordie Howe International Bridge. Archived from the original on July 24, 2023. Retrieved July 24, 2023.
- Detroit River International Crossing Study team. "DRIC Reports (Canada)". Detroit River International Crossing Project. Archived from the original on May 4, 2010. Retrieved February 26, 2010.
- Chen, Dalson (January 3, 2013). "What To Nickname the Herb Gray Parkway?". Windsor Star. Retrieved January 15, 2013.
- Detroit River International Crossing Study Team (May 1, 2008). "Parkway Map" (PDF). URS Corporation. Archived from the original (PDF) on July 6, 2011. Retrieved February 25, 2010.
- "A Resolution to Support the construction of the new Detroit River International Crossing between the United States and Canada". Laws, Acts, and Legislation-Ohio General Assembly. Archived from the original on March 3, 2016. Retrieved February 27, 2016.
- Samuel, Peter (June 10, 2010). "Michigan Senate Leader Says: No $#s on DRIC Bridge, No Vote". TollRoadNews. Archived from the original on November 29, 2010. Retrieved July 1, 2010.
- Christoff, Chris (January 19, 2011). "Snyder Backs 2nd Bridge for First Time". Detroit Free Press. Retrieved January 19, 2011.
- Schmidt, Doug (August 16, 2011). "Sides Remain Entrenched After Cross-Border Tour: Vote for Public Bridge Would Fail Today, Says Michigan Senator". Windsor Star. Archived from the original on August 17, 2011. Retrieved August 2, 2011.
- Edmonson, R.G. (October 20, 2011). "Plan for Detroit–Windsor, Ont., Bridge Dealt Blow". The Journal of Commerce. Archived from the original on October 22, 2011. Retrieved November 24, 2011.
- Mann, Bill (November 24, 2011). "Americans Should Be Thankful for Canada". MarketWatch. Archived from the original on December 2, 2013. Retrieved November 24, 2011.
- Savage, Luiza Ch. (November 21, 2011). "The U.S. and Canada: We Used To Be Friends". Maclean's. Archived from the original on November 24, 2011. Retrieved November 24, 2011.
- Mann, Bill (December 6, 2011). "A Bridge Too Difficult by Far". MarketWatch. Retrieved November 2, 2012.
- Oosting, Jonathan (June 17, 2010). "MDOT Report: Detroit River International Crossing". MLive. Detroit: Booth Newspapers. Archived from the original on March 4, 2016. Retrieved October 12, 2010.
- Tencer, Daniel (November 21, 2011). "Canada–U.S. Trade: Michigan Senate Committee Kills New Border Crossing". Huffington Post. Archived from the original on March 13, 2021. Retrieved June 15, 2012.
- "Canada, Michigan announce new Detroit-Windsor bridge". Reuters. June 15, 2012. Archived from the original on July 24, 2023. Retrieved July 24, 2023.
- "$1B Windsor–Detroit Bridge Deal Struck". CBC News. June 15, 2012. Archived from the original on August 23, 2013. Retrieved June 15, 2012.
- "Community Benefits". Gordie Howe International Bridge. Archived from the original on August 17, 2023. Retrieved August 17, 2023.
- Battagello, Dave (April 12, 2013). "Michigan Governor Snyder Confirms Permit for DRIC Approved". Windsor Star. Archived from the original on November 14, 2013. Retrieved April 12, 2013.
- "New Windsor–Detroit bridge gets Obama's OK". CBC News. April 12, 2013. Archived from the original on August 28, 2013. Retrieved April 12, 2013.
- "Issuance of Presidential Permit for New International Trade Crossing" (Press release). United States Department of State. April 12, 2013. 2013/0402. Retrieved April 12, 2013.
- "DRIC bridge executive teams loaded with financial expertise, but nobody local". Windsor Star. Archived from the original on July 2, 2015.
- Battagello, Dave (May 22, 2013). "Canada to start buying property in Delray for DRIC bridge". Windsor Star. Archived from the original on April 12, 2014. Retrieved August 4, 2013.
- "$250M U.S. customs plaza to be paid for by Canada". CBC News. Archived from the original on February 24, 2015. Retrieved May 14, 2015.
- "Deal for new customs plaza in Detroit announced". Detroit Free Press. February 18, 2015. Archived from the original on December 1, 2020. Retrieved May 14, 2015.
- "Gordie Howe International Bridge to connect Windsor and Detroit". CBC News. May 14, 2015. Archived from the original on February 13, 2021. Retrieved May 14, 2015.
- "Gordie Howe bridge costs skyrocketing thanks to tumbling loonie". Windsor Star. The Canadian Press. January 4, 2016. Archived from the original on July 16, 2018. Retrieved October 4, 2018.
- "Gordie Howe Bridge Authority ready to take on Moroun over land needed for crossing". CBC News. April 28, 2017. Archived from the original on July 24, 2023. Retrieved July 24, 2023.
- "Gordie Howe bridge faces delays on both sides of border". CBC News. July 10, 2016. Archived from the original on August 24, 2016. Retrieved August 24, 2016.
- Kurth, Joel (May 3, 2018). "A new bridge is dawning in Detroit. Matty Moroun isn't the only one unhappy". Michigan Radio. Archived from the original on November 17, 2019. Retrieved December 13, 2019.
- "Canada should consider buying Ambassador Bridge, Ottawa told". CBC News. July 28, 2016. Archived from the original on August 20, 2016. Retrieved August 24, 2016.
- Battagello, Dave (February 13, 2017). "Howe bridge highlighted during Trudeau-Trump meeting". Windsor Star. Archived from the original on September 21, 2021. Retrieved November 19, 2021.
- "Trump makes $137bn list of "emergency" infrastructure schemes, all needing private finance". Global Construction Review. January 30, 2018. Archived from the original on May 13, 2019. Retrieved February 10, 2019.
- Runyan, Robin (June 23, 2017). "City sells land in Delray for Gordie Howe International Bridge". Curbed Detroit. Archived from the original on June 27, 2018. Retrieved June 27, 2018.
- "Appeal to stop Gordie Howe Bridge project fails in Michigan court". CBC News. May 10, 2018. Archived from the original on June 28, 2018. Retrieved June 27, 2018.
- Chen, Dalsen (July 5, 2018). "Bridging North America will build Gordie Howe International Bridge". Windsor Star. Archived from the original on October 22, 2021. Retrieved November 19, 2021.
- "Bridging North America". Gordie Howe International Bridge. Archived from the original on August 7, 2020. Retrieved March 4, 2020.
- "Gordie Howe bridge will be the longest cable-stayed bridge in North America". CBC News. July 5, 2018. Archived from the original on October 1, 2020. Retrieved July 5, 2018.
- "Gordie Howe International Bridge to cost $5.7B, create 2,500 jobs". CTV News Windsor. September 27, 2018. Archived from the original on March 6, 2022. Retrieved July 24, 2023.
- Fraser, Kaitie (July 17, 2018). "Canada's infrastructure minister, Mich. governor break ground on Gordie Howe International Bridge". CBC News. Archived from the original on July 24, 2023. Retrieved July 24, 2023.
- Gallagher, John (July 17, 2018). "Gov. Snyder on Gordie Howe bridge start today: 'We need this bridge'". Detroit Free Press. Archived from the original on June 1, 2021. Retrieved July 28, 2018.
- "$3.8B to build Gordie Howe bridge, complete by end of 2024". CBC News. September 28, 2018. Archived from the original on October 10, 2021. Retrieved September 29, 2018.
- "WDBA says land on Michigan side of Gordie Howe bridge is contaminated". CTV News Windsor. April 15, 2019. Archived from the original on July 24, 2023. Retrieved July 24, 2023.
- "$20M in community benefits for Windsor, Detroit announced as part of Gordie Howe Bridge Project". CTV News Windsor. June 14, 2019. Archived from the original on July 24, 2023. Retrieved July 24, 2023.
- Jr, Dave Bartkowiak (January 9, 2020). "Gordie Howe International Bridge project includes 5 new pedestrian bridges". WDIV. Archived from the original on July 24, 2023. Retrieved July 24, 2023.
- Garton, Rich (January 4, 2021). "Banner year expected as tower construction begins on Gordie Howe Bridge". CTV News Windsor. Archived from the original on July 24, 2023. Retrieved July 24, 2023.
- "Gordie Howe Bridge reaches construction milestone, as officials announce details for Sandwich Street improvements". CTV News Windsor. March 9, 2022. Archived from the original on July 24, 2023. Retrieved July 24, 2023.
- "Gordie Howe Bridge completion date likely in 2025, later than initial estimates: officials". CBC News. November 30, 2022. Archived from the original on March 30, 2023. Retrieved July 24, 2023.
- Battagello, Dave (May 10, 2023). "Support cables going up as Gordie Howe bridge work progresses". Windsor Star. Archived from the original on May 10, 2023. Retrieved July 24, 2023.
- Battagello, Dave (August 30, 2023). "Completion of Gordie Howe bridge reaches another milestone". Windsor Star. Retrieved August 31, 2023.
- Welch, Adrian (January 15, 2019). "Gordie Howe International Bridge". e-architect. Archived from the original on August 7, 2020. Retrieved March 4, 2020.
- "AECOM to build the longest cable-stayed bridge in North America". Designboom. January 14, 2019. Archived from the original on July 29, 2020. Retrieved March 4, 2020.
- "Backgrounder" (PDF). Windsor-Detroit Bridge Authority. July 5, 2018. Archived (PDF) from the original on July 5, 2018. Retrieved July 5, 2018.
- "Project Overview". Gordie Howe International Bridge. Archived from the original on July 11, 2021. Retrieved July 24, 2023.
- "Michigan Interchange". Gordie Howe International Bridge. Archived from the original on May 2, 2023. Retrieved May 8, 2023.
- Waddell, Dave (September 9, 2022). "Binational trail system planned to be linked by Gordie Howe bridge". Windsor Star. Archived from the original on September 9, 2022. Retrieved August 11, 2023.
- Report to the Legislature of the State of Michigan Responding to Public Act 116 of 2009, Section 384 (PDF) (Report). Michigan Department of Transportation. May 1, 2010. Archived (PDF) from the original on July 15, 2011. Retrieved October 12, 2010.
- Fraser, Kaitie (November 28, 2020). "Indigenous art set to soar on Gordie Howe International Bridge project". CBC News. Archived from the original on July 24, 2023. Retrieved July 24, 2023.
- "Bridge Tower Artwork". Gordie Howe International Bridge. Archived from the original on July 24, 2023. Retrieved July 24, 2023.
- "Artist shares vision with the world on Gordie Howe International Bridge". CBC News. February 15, 2023. Archived from the original on July 24, 2023. Retrieved July 24, 2023.
- Battagello, Dave (June 18, 2023). "Indigenous artist commissioned for Gordie Howe bridge project". Windsor Star. Archived from the original on June 19, 2023. Retrieved July 24, 2023.
- "Public Art Commission: Indigenous sculpture". Gordie Howe International Bridge. March 2023. Archived from the original on August 17, 2023. Retrieved August 17, 2023.
- "Gordie Howe Bridge to feature art that commemorates the Underground Railroad". CBC News. March 9, 2023. Retrieved July 24, 2023.
- "Commemorating The Underground Railroad At The Canadian Port Of Entry". Gordie Howe International Bridge. March 2023. Archived from the original on August 17, 2023. Retrieved August 17, 2023.
- "Visual Art Program". Gordie Howe International Bridge. Archived from the original on July 24, 2023. Retrieved July 24, 2023.
- Detroit River International Crossing Study Team (May 1, 2008). "Parkway Map" (PDF). URS Corporation. Archived from the original (PDF) on July 6, 2011. Retrieved February 26, 2010.
- Battagello, Dave (December 27, 2015). "New parkway trails to open amid much fanfare". Windsor Star. Retrieved August 27, 2023.
- Pomerleau, Jason. "Herb Gray Parkway Trail". Tourism Windsor Essex Pelee Island. Retrieved August 27, 2023.
- Puzic, Sonja (May 7, 2011). "Parkway Work To Start in August, MPP Says". Windsor Star. Archived from the original on August 11, 2011. Retrieved May 10, 2011.
- "Herb Gray Parkway construction work is all done, Transportation Minister says". CBC News. November 20, 2015. Archived from the original on December 13, 2015. Retrieved August 24, 2016.
- "The Windsor-Essex Parkway" (PDF). Infrastructureontario.ca. Archived from the original (PDF) on March 4, 2016. Retrieved February 27, 2016.
- "Snake in path of parkway". Windsor Star. January 7, 2010. Archived from the original on August 8, 2015.
- Vander Doelen, Chris (August 31, 2012). "Windsor-Essex Parkway One Year Later". Windsor Star. Archived from the original on November 20, 2021. Retrieved November 19, 2021.
- "US Port of Entry and Michigan Interchange Ramp Construction". Gordie Howe International Bridge. Archived from the original on August 17, 2023. Retrieved August 17, 2023.
- "I-75 Noise Walls". Gordie Howe International Bridge. 2022. Archived from the original on August 17, 2023. Retrieved August 17, 2023.
- "Ambassador Bridge Boss Sues Canada, U.S". CBC News. March 26, 2010. Archived from the original on December 16, 2010. Retrieved April 20, 2011.
- Bell, Dawson (April 25, 2011). "Tax-Free Fuel Sales Are Bonanza for Ambassador Bridge Owners". Detroit Free Press. Archived from the original on January 28, 2016. Retrieved April 25, 2011.
- Gallagher, John (June 7, 2011). "Conservative Group: Fake Eviction Notices Were 'Meant To Startle People'". Detroit Free Press. Archived from the original on June 10, 2011. Retrieved June 7, 2011.
- White, Joseph B. (October 10, 2011). "Is Span Plan a Bridge Too Far?". The Wall Street Journal. Archived from the original on April 19, 2015. Retrieved April 19, 2015.
- Christoff, Chris (September 16, 2011). "Detroit Span Owner Keeps Canada Crossing With Koch Aid". Bloomberg Business. Archived from the original on May 25, 2015. Retrieved April 19, 2015.
- Avalon Consulting Professionals of Ontario (April 2011). "Appendix K: Windsor Official Plan". CEAA Environmental Impact Assessment (PDF) (Report). Canadian Transit Company. Archived (PDF) from the original on April 20, 2012. Retrieved December 16, 2011.
- LeBlanc, Daniel (July 20, 2011). "Are U.S. Opponents of Windsor Bridge Trying To Influence Election?". The Globe and Mail. Toronto. Archived from the original on July 21, 2011. Retrieved July 20, 2011.
- Stamper, Dan (May 14, 2011). "Miscellaneous Notices: The Canadian Transit Company". Canada Gazette. 145 (20). Archived from the original on May 21, 2011. Retrieved August 3, 2011.
- Bomey, Nathan; Snavely, Brent (October 12, 2012). "UAW, Moroun Said To Be Allies in Battle To Block New U.S.–Canada Bridge". Detroit Free Press. Archived from the original on October 15, 2012. Retrieved October 16, 2012.
- Cwiek, Sarah (November 2, 2012). "In Michigan, A Contentious Battle Over A Bridge". Michigan Radio. Archived from the original on November 3, 2012. Retrieved November 2, 2012.
- "Transport Minister Says 'Path Clear' for Detroit–Windsor Bridge". CBC News. November 7, 2012. Archived from the original on November 7, 2012. Retrieved November 7, 2012.
- Spangler, Todd (June 21, 2016). "Judge voids last count in Moroun lawsuit against feds". Detroit Free Press. Archived from the original on August 11, 2023. Retrieved August 11, 2023.
- "Billionaire Matty Moroun Largely Loses In International Bridge Dispute With State - CBS Detroit". www.cbsnews.com. September 30, 2015. Retrieved August 11, 2023.
- Spangler, Todd (February 23, 2015). "Supreme Court turns down Moroun challenge to new bridge". Detroit Free Press. Retrieved August 11, 2023.
- Spangler, Todd (June 20, 2018). "Moroun TV ad asks Trump to pick America, reject Gordie Howe bridge". Detroit Free Press. Archived from the original on June 30, 2019. Retrieved September 29, 2018.
- Mauger, Craig (January 2, 2020). "Gordie Howe bridge project scores $15 million in federal funds". The Detroit News. Archived from the original on November 26, 2021. Retrieved November 26, 2021.
- Wattrick, Jeff (February 3, 2011). "Forget the DRIC, How About the Gordie Howe International Bridge?". MLive. Detroit. Archived from the original on June 18, 2018. Retrieved February 5, 2011.
- Supporting the New International Trade Crossing and Public Private Partnership Legislation (PDF). Detroit Free Press (Report). April 21, 2011. Archived (PDF) from the original on October 6, 2012. Retrieved May 9, 2011.
- Noble, Chris (February 8, 2011). "Gordie Howe Bridge Floated as New Span's Name". MarketWatch. Archived from the original on June 10, 2016. Retrieved November 2, 2012.
- Gallagher, John (May 14, 2015). "'Mr. Hockey' gets his own bridge". Detroit Free Press. Archived from the original on July 11, 2021. Retrieved December 13, 2019.
- "Snyder: Naming bridge after Gordie Howe a no-brainer". The Detroit News. Archived from the original on April 24, 2019. Retrieved November 16, 2018.
- "Movement grows to rename arena Gordie Howe Arena". WJBK News. June 10, 2016. Archived from the original on January 20, 2017. Retrieved June 12, 2016.
- "Gordie Howe exposé en chapelle ardente" [Gordie Howe Visitation in Emotional Chapel]. Le Journal de Montréal (in French). June 11, 2016. Archived from the original on June 11, 2016. Retrieved June 12, 2016.
External links
- Windsor-Detroit Bridge Authority (WDBA) official website
- Detroit River International Crossing Project
- New International Trade Crossing from the State of Michigan
- Video of the Highway 401 extension that will connect to the Gordie Howe Bridge
- Mossman, Matt (December 2017). "Crossing Guards". Harper's Magazine. Retrieved November 27, 2017.