Emonika
Emonika, also named the Emonika City Centre or Ljubljana Emonika Passenger Centre (Slovene: Potniški center Ljubljana Emonika), is a construction project including a new bus and railway station at Liberation Front Square (Trg Osvobodilne fronte), near Ljubljana railway station, as well as in the nearby area in the Center District of Ljubljana, the capital of Slovenia. It will also provide a new business and residential complex.
Timeline
TriGranit
The construction was originally planned by the construction company TriGranit. The first old buildings were removed in 2008 in order to prepare space for construction, which was planned to begin in spring 2012 and finish in two years. In September 2012, TriGranit withdrew its construction permit request, filled in June 2012, after failing to acquire some of the necessary land within relevant deadlines. According to Mayor Zoran Janković, the company had invested already 30 million euros in the project.[1] TriGranit later stated it had not withdrawn from the project.[2] After the Government of Slovenia refused to subsidy the investment in July 2014, TriGranit pulled out of the contract with Slovenian Railways.[3] The railway company decided to press charges against it, but the construction of the complex was postponed indefinitely.[4]
Prime Kapital
In early 2017, the project gained a new investor, the Prime Kapital fund from Romania. In March 2017, it was announced that it would, under the management of Csaba Toth who initially worked for TriGranit and in collaboration with Slovenian Railways and the City Municipality of Ljubljana, construct a new bus and railway station, redesign Liberation Front Square, as well as widen Masaryk Street (Masarykova ulica) running along the railway to a four-lane road. The construction works were scheduled to commence at the earliest in the first half of 2018 and no later than the end of 2018. Besides, a shopping mall, a complex of nine cinema halls, and a parking lot for 1,600 cars will be built. The investment has been estimated to be worth of 250 million euros, which is circa 100 million less than the original estimate of 350 million.[5] In 2019, it became known that OTP Bank might join the project, as the schedule was postponed until 2020; in November 2020, the Government of Slovenia signed a memorandum of understanding with OTP Bank for work to begin in 2022. The whole project's cost was set at 350 million euros.[6] In May 2022, minister of Infrastructure Jernej Vrtovec said that engineering permits should be obtained by the end of 2022, and the project completed by 2025.[7] However, as of July 2023, no construction has begun.
References
- "Construction Permit Request for Emonika Withdrawn (adds)". Splošni servis. Slovene Press Agency. 11 September 2012.
- Petkovšek, Janez (11 September 2012). "TriGranit: »Emoniki se nismo odpovedali.«". DELO. Retrieved 25 September 2012.
- "Govt Decides against State Subsidy for New Central Station Project". The Slovenia Times. 14 July 2014.
- "Slovenske železnice si zaradi propadle Emonike obetajo 72 milijonov evrov" [The Slovenian Railways Anticipate 72 Million Euros due to the Failed Emonika] (in Slovenian). Planet Siol.net. 17 November 2014.
- "Nov časovni načrt 250 milijonov evrov težke Emonike" [A New Time Plan of the 250-Million Euros Worth Emonika]. Manager.finance.si (in Slovenian). 2 March 2017.
- Signs Ljubljana passenger terminal back on track, Slovenia Times
- "CONSTRUCTION WORK ON LJUBLJANA PASSENGER CENTRE TO START BY END OF 2022". Slovenske zeleznice. May 5, 2022. Retrieved July 6, 2023.