Gloucestershire EfW

Gloucestershire Energy from Waste Facility, also known as the Javelin Park Incinerator is a residual waste incinerator and energy-from-waste power station which produces 14.5MW of energy for the National Grid by burning up to 190,000 tonnes of residual waste each year.[3] The site is located adjacent to the M5 motorway, near junction 12 and to the south of Gloucester.

Gloucestershire EfW
Entrance to the facility
CountryEngland
Locationnear Stonehouse, Gloucestershire
Coordinates51°47′27.9″N 2°17′28.4″W
StatusOperational
Construction beganAugust 2016
Construction cost£633 million[1]
Owner(s)Urbaser Balfour Beatty
Operator(s)Urbaser Balfour Beatty
Employees~40[2]
Thermal power station
Primary fuelWaste
Site area9,200 square metres[2]
Chimneys1
Power generation
Units operational1 x 17.4 MW
Nameplate capacity14.5 MW[2]
Annual net output116,000 MWh
External links
Websitehttps://www.ubbgloucestershire.co.uk/

History

Gloucestershire County Council bought the land for a waste plant at Javelin Park in 2009 for £7.4m.[4]

In March 2011 contractors Complete Circle and Urbaser with Balfour Beatty were invited to refine their proposals for the incinerator and in December 2011 Gloucestershire County Council awarded a consortium of Urbaser and Balfour Beatty (UBB) the 25-year contract, which is set to end in 2044.[3]

Planning permission was submitted in September 2012[5] however against the recommendation to accept the proposal by the authority's planning committee,[6] it was rejected in March 2013 by the county council over concerns of its impact on the surrounding landscape. Javier Peiro, a director of UBB said the decision was "very disappointing on many levels".[7] UBB appealed the decision and after a public inquiry, the project was approved in January 2015.[8] Former Communities Secretary Eric Pickles delayed announcing his ruling three times on whether the project would be going ahead and Liberal Democrat councillor Jeremy Hilton, described the failures to make a decision as a "disgrace".[9]

In June 2018 the Information Commissioner's Office ruled that Gloucestershire County Council must publish commercially sensitive parts of a previously redacted report on the project due to Freedom of Information Act rules. Campaigners had requested information such as the price per tonne of waste processed and the electrical cost for third parties, to be able to assess whether the project was value for money.[10] The details were released on December 21, revealing a cost of £112.47 per tonne of waste burnt.[11]

In August 2016 construction began on the Javelin Park site, on part of the former RAF Moreton Valence Airfield.[12] Construction was completed in June 2019, with the facility beginning its commissioning process and receiving its first waste as part of testing. This was completed in October and the site became fully operational in January 2020.[3]

Operations

Side view

The Gloucestershire EfW Facility processes all the residual household waste generated in Gloucestershire, making the county self-sufficient for waste treatment capacity. The facility also processes certain deliveries of non-hazardous third party waste from commercial sources. Approximately 104 HGVs deliver 500 tonnes of waste each day.[2][13]

Upon arrival at the facility, waste is deposited into a refuse bunker capable of storing 11 days worth of waste collection. The waste is then loaded into a feed hopper by overhead cranes and dispensed onto a moving grate which transports waste to the burning zone. Oil burners are used to preheat the grate chamber to a minimum of 850 °C to allow waste combustion to begin and continue unaided. The air for this combustion process is drawn in through the waste reception hall and bunker to contain odours within the facility and is preheated by a heat exchanger using hot steam which has already passed through the steam turbine.[14] Heat is released in combustion, creating steam in the boiler which is converted into electrical energy by the turbine.[15]

Electricity is produced at 11kV by the electric generator, which is connected via a gearbox to the steam turbine which spins at 5000 rpm. The voltage is then stepped up to 33kV by an on-site transformer before being exported to the National Grid.[14] In total up to 190,000 tonnes of waste are burnt each year to produce 116,000 MWh annually, enough to power around 25,000 homes.[1] The facility is a CHP Plant so has the capability to supply hot water or lowly pressurised steam for use in heating nearby buildings.[2]

The site has a visitor centre used for educational groups to learn about waste management and resource use. Additionally it also hosts tours and various events.[13][16]

Waste Management

The gaseous products of combustion are managed with a filtration and cleansing system to ensure that flue gas emissions comply with regulations. Emissions firstly undergo a chemical dosing to remove contaminants, and secondly a bag house filter to remove large particulates and dust contained in the flue gases. This process produces waste residues consisting primarily of lime and carbon (which are used to clean the flue gas before its released into the atmosphere). These waste residues are collected and transported off-site to Augean, a waste management operator, who treats them at their landfill site before disposal.[2][15]

The Gloucestershire EfW Facility produces approximately 40,000 tonnes of incinerator bottom ash (IBA) per year, consisting mainly of brick rubble and soils, clinker, glass, ceramics and metals. The IBA produced at the facility is cooled with water before being processed to recover ferrous and non-ferrous metals. Approximately 3,000 tonnes of metal are recycled from the IBA per year. The remaining material is then graded so it can be recycled as an aggregate in construction, such as in the subbase of roads. This process diverts 92% of waste from landfill.[2]

Controversies

The Gloucestershire Energy from Waste Facility faced "fierce opposition" while the project was both being planned and constructed,[17] including from Stroud District Council. Concerns were raised over the cost and carbon dioxide emissions of the project, as well as whether it would discourage residents to recycle.[18]

Local Opposition

More than 5,000 people signed a petition in 2010 opposing the plant.[19]

In October 2012, protesters wearing protective suits and gas masks gathered outside a council office,[20] and then in March 2013 over 100 people protested at the proposed construction site. Objections included the impact on the environment, human health, and the size and location of the plant.[21]

In January 2015, hundreds of protesters gathered in Stroud, concerned over the potential impact on the environment, as well as the size and cost. David Drew, Stroud's labour candidate said he thought the incinerator was the "wrong decision".[22]

In June 2017, protesters stormed and graffitied Gloucester Shire Hall, demanding construction work was halted.[23]

Protesters blocked the entrance to the construction site in August 2017[24] and again in January 2019, when they also held up traffic.[25]

Stroud District Council had consistently opposed the planned facility[18] and in February 2015 launched a legal challenge against the government's decision to approve the plans, describing it as their "only option" left. Balfour Beatty said it would cooperate fully, but was "disappointed" with the legal action.[26] The High Court rejected the legal challenge in July.[27][28]

In April 2017, the environmental group Community R4C filed a complaint with the Competition and Markets Authority, claiming the project did not provide value for money.[29] Community R4C took Gloucestershire County Council to the High Court in March 2020, claiming the contract was awarded to UBB unlawfully. The group said that they "would have bid for the contract" and had been working on an alternative waste processing plant which was "much cheaper". Gloucestershire County Council disagreed, stating its actions were completely lawful.[30] In July, the High Court ruled that Community R4C was not qualified to bid for the contract.[31][32]

References

  1. Boobyer, Leigh (2020-01-14). "Inside Javelin Park incinerator where waste is burned at 850 degrees". GloucestershireLive. Retrieved 2022-06-07.
  2. "Frequently Asked Questions". UBB. Retrieved 2021-09-05.
  3. "Gloucestershire Energy from Waste Facility becomes fully operational". UBB. 2020-01-15. Retrieved 2021-09-05.
  4. "Council buys 'waste plant' land". BBC News. 2009-01-22. Retrieved 2022-06-12.
  5. "Deal signed on £500m incinerator for Gloucester". BBC News. 2012-09-12. Retrieved 2022-06-07.
  6. "Agenda Reports Pack (Public) 21/03/2013, 10.00" (PDF). 21 March 2013. p. 9. Retrieved 2022-06-07.
  7. "Gloucestershire incinerator plan at Javelin Park rejected". BBC News. 2013-03-21. Retrieved 2022-06-07.
  8. "Javelin Park waste incinerator can go ahead, government rules". BBC News. 2015-01-07. Retrieved 2022-06-07.
  9. "Eric Pickles incinerator decision 'needed before election'". BBC News. 2015-01-05. Retrieved 2022-06-07.
  10. "Gloucester incinerator contract 'must be revealed'". BBC News. 2018-06-11. Retrieved 2022-06-07.
  11. "Council publishes Gloucester incinerator costs after ruling". BBC News. 2018-12-21. Retrieved 2022-06-12.
  12. "The Design". UBB. Retrieved 2021-09-05.
  13. Young, James (2020-01-15). "Gloucestershire's incinerator is fully operational and burning 20 tonnes of waste each hour". Punchline. Retrieved 2022-06-07.
  14. "The technology". UBB. Retrieved 2022-10-12.
  15. "The Facility". UBB. Retrieved 2021-09-05.
  16. "Site Tours and Visitor Centre". UBB. Retrieved 2022-06-07.
  17. "Probe into Gloucester incinerator contract blunder". BBC News. 2017-01-30. Retrieved 2022-06-12.
  18. "Stroud District Council leaders oppose waste from our district being burnt at the new Javelin Park incinerator". www.stroud.gov.uk. 2019-07-02. Retrieved 2022-06-12.
  19. "Deal signed on £500m incinerator for Gloucester". BBC News. 2012-09-12. Retrieved 2022-06-09.
  20. "Protest over Gloucester waste incinerator scheme". BBC News. 2012-10-02. Retrieved 2022-06-09.
  21. "Javelin Park incinerator: More than 100 people join protest". BBC News. 2013-03-14. Retrieved 2022-06-09.
  22. "Javelin Park waste incinerator: Hundreds attend protest march". BBC News. 2015-01-17. Retrieved 2022-06-09.
  23. "Incinerator protesters storm Gloucester council offices". BBC News. 2017-06-28. Retrieved 2022-06-12.
  24. "Protesters block Javelin Park incinerator entrance". BBC News. 2017-08-20. Retrieved 2022-06-12.
  25. "Gloucester waste incinerator protesters block road". BBC News. 2019-01-08. Retrieved 2022-06-09.
  26. "Incinerator legal action 'only option left', says council". BBC News. 2015-02-15. Retrieved 2022-06-09.
  27. Perchard, Edward (2015-08-12). "R4C alternative to Gloucestershire incinerator launched". Resource Magazine. Retrieved 2022-06-10.
  28. "Waste incinerator can be built, High Court rules". BBC News. 2015-07-10. Retrieved 2022-06-10.
  29. Cole, Rob (2017-04-03). "Campaigners bid to halt £500m incinerator in Gloucestershire". Resource Magazine. Retrieved 2022-06-10.
  30. "Community group in court over Gloucester incinerator contract". BBC News. 2020-03-02. Retrieved 2022-06-09.
  31. "Community group lose Gloucester incinerator legal bid". BBC News. 2020-07-17. Retrieved 2022-06-09.
  32. "Court of Appeal dismisses Javelin Park challenge". Stroud News and Journal. 2020-11-20. Retrieved 2022-06-10.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.