Hanthawaddy International Airport
Hanthawaddy International Airport (Burmese: ဟံသာဝတီအပြည်ပြည်ဆိုင်ရာလေဆိပ်) is an international airport currently under construction in Bago Region, Myanmar that is located about 48 miles (77 km)[1] away from Yangon. The project was started in 2001 [2] but it was subsequently halted. The proposed site of the airport has a gross area of 36.42 square kilometres (14.06 sq mi).[1]
Myanmar's government have announced their plan to restart the project in 2012 to meet their future developments.[3] A consortium led by Incheon International Airport Corporation (IIAC), including South Korean firms (Halla Engineering & Construction Corporation, Lotte Engineering & Construction Corporation, POSCO ICT and Kumho Industrial Company) was awarded the US$1.1 billion contract, to build the new airport and operate the airport for 50 years.[4] The airport will have the capacity to handle 12 million passengers per year and expected to be start operation by 2018.
Due to financial related issue and disagreement over passenger capacity, however, the deal with the Incheon consortium was terminated and a new tender was reopened in February 2014.
The new tender was awarded to a Singapore-Japan consortium on 29 October 2014. The consortium comprises Singapore's Yongnam Holdings, Changi Airport Planners and Engineers, a subsidiary of Changi Airport Group and Japan's JGC Corporation. The contract is worth $1.45 billion and the consortium will get official development assistance from the Japanese government for up to 49 percent of the total contract. The rest of the funding will come from private lending ($517 million) and investments from the consortium ($222 million).
As the latest tenders and by new operator , the completion date of Phase 1 is now pushed back to 2027. The Phase 1 consists of 3600m concrete runway , as well as the high speed taxiway . After the Phase 3 completion around 2032-2035 , Hanthawaddy will have "2" 3600m runway and a huge satellite terminal which have a capacity of 60million passengers per year ( can be updated ) . [1]
References
- "New Bago airport delayed again, to 2022". Myanmar Times. 31 Aug 2015.
- "Oversea Major Project". SUNJIN Engineering & Architecture. Retrieved 23 June 2012.
- "Myanmar to add two new int'l airports to meet future development". Xinhua. 19 Feb 2012. Archived from the original on April 4, 2013.
- Odedra, Rahul (12 August 2013). "Incheon-led consortium is preferred bidder for new Myanmar airport". Moodie Report. Retrieved 17 August 2013.