Tren Maya

The Tren Maya (sometimes also Mayan Train or Maya Train) is a 1,525-kilometre (948 mi) intercity railway in Mexico that will traverse the Yucatán Peninsula. Construction began in June 2020 and the railway is scheduled to begin operation by December 15, 2023.[2] The railway begins in Palenque in Chiapas and travels northeast towards Cancún in Quintana Roo via two routes that encircle the peninsula. The project aims to connect tourist destinations in the Caribbean with lesser-known sites inland, including historic Mayan sites from which it derives its name.[3][4]

Mayan Train
Overview
Native nameTren Maya (Spanish)
Tsiímin K'aák (Yucatec Maya)
OwnerMexican Armed Forces
LocaleChiapas, Tabasco, Campeche, Yucatán, Quintana Roo; Mexico
Termini
Stations15
Websitehttps://www.gob.mx/trenmaya
Service
Services3
Rolling stock42 X'Trapolis Tsíimin K’áak multiple units
History
Construction beganDecember 16, 2018
Proposed openingDecember 15, 2023[1] (Palenque-Cancún)
End of January 2024[1] (Cancún-Tulum)
February 2024[1] (Tulum-Escárcega)
Technical
Line length1,525 km (948 mi)
Number of tracks1
Track gauge1,435 mm (4 ft 8+12 in) standard gauge
Operating speed160 km/h (99 mph)
Route map

 
Cancún Airport
Puerto Morelos
Playa del Carmen
Tulum
Tulum Airport
Leona Vicario
Nuevo Xcán
Yucatán/Quintana Roo border
Valladolid
Chichén Itzá
Felipe Carrillo Puerto
Limones
Bacalar
Chetumal Airport
Izamal
Tixkokob
Teya Mérida
Umán
Maxcanú
Campeche/Yucatán border
Calkiní
Campeche/Quintana Roo border
Nicolás Bravo
Xpujil
Calakmul
Centenario
Hecelchakán
Tenabo
San Francisco de Campeche
Edzná
Carrillo Puerto
Escárcega
Candelaria
Tabasco/Campeche border
El Triunfo
Tenosique
Usumacinta River
Boca del Cerro
Chiapas/Tabasco border
Palenque
FA Line to Coatzacoalcos
(March 2024)

History

The Tren Maya project was announced in September 2018 by Mexican president-elect Andrés Manuel López Obrador, following earlier proposals to build a shorter 900-kilometre (560 mi) line. Previous presidential administrations had also proposed their own passenger rail projects, but were unsuccessful in attaining funding.[3][5] It would use existing right of way from Ferrosur as well as new tracks constructed through the jungle.[6][7] The project was derided by political opposition groups as a stunt for López Obrador, who had also cancelled a major airport project in Mexico City favored by his predecessor.[8] The Zapatista Army of National Liberation announced that it would oppose the project.[9]

December 2019 consultation

On November 15, 2019, President López Obrador declared that a referendum on the Mayan Train would be held on December 15, 2019, in Chiapas, Tabasco, Campeche, Yucatán, and Quintana Roo.[10]

The weekend of December 15–16, 2019, 92.3% of the people who participated in the consultation voted in favor, while 7.4% voted against the proposal.[11] 100,940 people voted,[12] 2.36% of the 3,536,000 registered voters in the 84 municipalities affected.[13]

The Mexican Office of the United Nations High Commissioner for Human Rights criticized the vote. They pointed out that voters were provided with only the positive effects of the project (improved attention to water supplies, health, education, employment, housing, environmental protection, and culture) but were not informed of the negative effects. The Human Rights Commission also criticized the translations of the material used, the short period of time for the election, and low turnout, particularly among indigenous women. They noted that many potential voters did not have the financial resources to travel to the voting locations, and that the majority of voters were municipal employees.[14] The government rejected the criticisms, stating the consultation met international standards.[15]

Progreso extension

In June 2022 Interior Secretary Adán Augusto López Hernández announced a planned extension to Progreso and Umán in Yucatán.[16]

Funding

Funding for the project will come primarily from a tourism tax levied in the region, as well as funds diverted from other programs, including the Mexican Grand Prix.[5][9]

The project, led by the National Fund for Tourism Development (Fonatur), in December 2018 was estimated to cost 150 billion pesos (US$7.4 billion) and attract 8,000 daily riders.[17] An alternative study by a public policy think tank in 2019 estimated the cost of the project would be 480 billion pesos (US$25.3 billion), supported by the 90 percent cost overrun on the Toluca–Mexico City commuter rail project.[8] In October 2021 Fonatur revised the construction estimate to 200 billion pesos.[18]

In October 2020 the estimated total cost of the project, including 30 years of operating and maintenance but not including electrification, was about 321 billion pesos.[19]

The Secretariat of Tourism will receive a 647.1% increase in its budget for 2021 (MXN $38,613.4 million), of which 94% is destined for the Mayan Train.[20]

In December 2020 president López Obrador announced that the armed forces would operate three sections of the route, and that profits would be used to strengthen finances for pensioners and retirees of the armed forces.[21] In March 2021 Fonatur general director Rogelio Jiménez Pons said that the military would own the entire route, not just the three sections, and would receive all of the profits.[22]

Pons stated in September 2021 that the cost of a single trip for locals, for the section that goes from Cancún to Playa del Carmen, will be around 50 pesos. Tourists will be expected to pay between 800 and 1000 pesos for the same trip. When explaining the difference in price, he stated that the tourist will have additional services such as restaurants.[23]

Construction

On December 16, 2018, president López Obrador conducted a Mayan ritual to commemorate the start of construction on the Mayan Train project.[3] The railway will also accommodate local passenger traffic and freight shipments in addition to tourist functions.[9][24] The first phase of the project is anticipated to open in the late 2020s, but tourism officials in the region have proposed accelerating work for a 2023 opening.[9][25]

The route consists of seven sections. Section I runs from Palenque to Escárcega (228 km (142 mi)); section II from Escárcega to Calkiní (235 km (146 mi)); section III from Calkiní to Izamal (172 km (107 mi)); section IV from Izamal to Cancún (257 km (160 mi)); section V from Cancún to Tulum (121 km (75 mi)); section VI from Tulum to Bacalar (254 km (158 mi)); and section VII from Bacalar to Escárcega (287 km (178 mi)).[26]

Business leaders in Mérida, Yucatán expressed their support on January 31, 2020, for building four kilometers of the railway underground as it passes through the city of Mérida. In this way, the train will not threaten the city's historic center. They are also optimistic that the tourist train, in combination with improvements in energy, airports, and seaports, will make the region economically competitive with the North and the Bajío.[27] Fonatur later announced that the train would initially not stop in Mérida, but near a hacienda 8 km (5.0 mi) away.[28] They said that by 2025 the station will relocate to La Plancha Park in Mérida.[29]

Construction began in June 2020.[30] The construction companies are Mota-Engil México SAPI and China Communications Construction Company LTD for stretch one (Palenque-Escárcega), Operadora CICSA and FCC Construcción for stretch two (Escárcega-Calkiní), Construcciones Urales and GAMI Ingeniería e Instalaciones for stretch three (Calkiní-Izamal), and Grupo ICA for stretch four (Izamal–Cancún).[31] In September 2020 Fonatur rejected a proposal of investment firm BlackRock for the fifth stretch (125 km (78 mi)) of the project, including improvements to the Tulum–Cancún highway.[32][33]

In February 2021 Fonatur awarded a contract to Acciona and Grupo México for 60.3 km (37.5 mi) of electrified double rail tracks for section five between Playa del Carmen and Tulum.[34]

As of January 2021 plans call for diesel-electric trains running at up to 160 km/h (99 mph).[26] In May 2021 Fonatur contracted with a consortium headed by Alstom to supply rolling stock and related equipment. The rolling stock will be manufactured at Alstom's factory in Ciudad Sahagún. The contract also includes European Train Control System signalling and control equipment.[34]

López Obrador has said the project will be completed prior to the end of his term in 2024. A market survey conducted by Fonatur, PricewaterhouseCoopers and other consultants in 2019 found that a majority of 21 construction companies consider this too fast, an unreasonable time to construct so much new rail, and others have expressed fear of a disaster caused by substandard work, such as the May 2021 Mexico City Metro overpass collapse.[35][36] In January 2022, to speed up construction, the route was changed to no longer enter Playa del Carmen.[37] As of June 2021, 10% of the project had been completed.[38] This had increased to 25% by February 2022,[39][40] 67% by June 2023.[41] In February 2023 Tren Maya director general Óscar Lozano said that operations would start on December 1, 2023.[42]

Passenger services

Passenger services

There will be 42 railway cars, which will have a cost of 36,564 million pesos, which the companies of Canadian and French origin, respectively, will be in charge of building at the Ciudad Sahagún plant, in Hidalgo.[43]

Xiinbal

Regular passenger service will be provided by the Xiinbal train, named for a Mayan term meaning “to walk”, is the regular passenger service. They will have business class seats; standard seating and cafeteria car. This service will be offered to frequent local passengers, but also to occasional passengers and tourists.[43]

Janal

The Janal trains (from a Mayan term meaning "to eat") will add to the previous services, a restaurant on board, which will have aquatic landscapes on the outside, and the interior will refer to the work of Luis Barragán. “The restaurant offers two layout options and various seating configurations to allow optimal use of space in a beautiful setting.”[43]

P'atal

The P'atal trains (from a Mayan term meaning "to stay") will have reclining seats and sleeping cabins, especially for long-distance journeys.[43][44]

Rolling stock

The rolling stock of the Mayan train was designed by the French company Alstom, and its cars were built in Ciudad Sahagún.[45][46]

Model Type Consist Capacity Total number of trains
1 2 3 4 5 6 7
X'Trapolis Tsíimin K’áak Xiinbal (standard) 4 to 7 cars 230 to 430 passengers 31
Janal (restaurant) 4 cars 140 passengers 8
P’atal (long-distance) 7 cars 260 passengers 3

Opposition

Environmental and indigenous rights activists objected to construction of new tracks through the jungle.[6][7]

On the 26th anniversary of its armed uprising, January 1, 2020, the Zapatista Army of National Liberation expressed its opposition to the project and declared that the consultation provided only positive information to voters prior to voting.[47]

Groups close to the National Indigenous Congress (CNI) plan to seek injunctions against the train project and other construction in the region. The CNI is looking at three-pronged action: social awareness campaigns, media campaigns, and legal actions.[48] On January 28, 2020, a judge in Campeche issued a temporary injunction against construction of the railway because was approved in a "simulated consultation."[49] In a visit to the city of Campeche, President López Obrador defended the train and pointed out that not only had the train received its greatest support in the state of Campeche, but also that more than half the route would run through the state—worth MXN $60 billion of the $130 billion the government plans to invest in total. He said the section from Escárcega to Cancún should be open for tourist, passenger, and freight traffic in 2023, but that the route will not pass through the Calakmul Biosphere Reserve.[50]

In November 2020 the Regional Indigenous Council of Xpujil delivered a petition with 268,000 signatures to the Campeche Ministry of Environment and Natural Resources asking that the project be suspended because of environmental concerns.[51] Residents of Chocholá, Mérida, and Izamal, in Yucatán obtained a temporary delay in construction in January 2021 until Fonatur and SEMARNAT report on an environmental impact assessment.[52]

On March 3, 2021, an injunction was filed by 80 people from Campeche who fear eviction from their homes. The First District Court in Campeche granted them the provisional suspension. Yucatán's fourth district court also ordered a stop to construction.[53] The brought the total number of injunctions filed in the Yucatan Peninsula to 16 in March 2021,[54] increasing to at least 25 by January 2022. Most of the injunctions have been filed by indigenous collectives who consider the project to be an environmental disaster.[55] The injunctions have had little effect, and construction continues.[53] López Obrador has criticized the saliency in opposition to the train as a partisan attempt to halt his administration's infrastructure projects.[56][57]

A group of celebrities, including comedian Eugenio Derbez, singers Rubén Albarrán and Natalia Lafourcade, and actress Kate del Castillo, as part of the Sélvame del Tren ("Save me from the Train", a play on words between Sálvame meaning Save Me, and Selva meaning jungle) campaign, has expressed opposition to the train.[58]

In July 2022 residents of Chemax barricaded surrounding roads, bringing construction to a halt. They say the government has violated its agreement by clearing the jungle and failing to provide promised infrastructure.[59]

Environmental concerns

As of January 2021 workers and archeologists had uncovered more than 8,000 ancient artifacts and structures during construction.[60]

The National Alliance for Conservation of the Jaguar has identified twelve wildlife corridors that could be constructed to mitigate the situation for the jaguars that live in the area.[61]

The Centro Mexicano de Derecho Ambiental environmental group has accused Fonatur of deforestation along the route, not accounted for in the environmental impact assessment and without acquiring the necessary permits.[62] In November 2021 the Interior Department exempted Tren Maya and other infrastructure projects from environmental review.[63]

Original plans called for electric locomotives on the trains.[9][24] In June 2020 the government announced a switch to diesel to reduce costs,[64] then in August 2020 they announced that half the route, from Mérida to Chetumal via Cancún, would be electrified.[65]

In March 2022 Greenpeace organizers tied themselves to heavy machinery as a protest against construction in Quintana Roo that involves cutting down the jungle without environmental studies having been made.[58]

Cave diver Jose Urbina Bravo conducts expeditions to study the train's impact on wildlife and the environment above ground and in underground caves. Urbina Bravo is also involved in a legal battle to halt construction.[66]

See also

References

  1. "El 15 de diciembre inicia ruta Palenque-Cancún; todos los tramos, para febrero: AMLO". sinembargo.mx (in Spanish). October 6, 2023. Retrieved October 23, 2023.
  2. "El 15 de diciembre inicia ruta Palenque-Cancún; todos los tramos, para febrero: AMLO". sinembargo.mx (in Spanish). October 6, 2023. Retrieved October 23, 2023.
  3. Pskowski, Martha (February 22, 2019). "Mexico's 'Mayan Train' Is Bound for Controversy". CityLab. Retrieved February 23, 2019.
  4. Varillas, Adriana (November 23, 2018). "Everything you need to know about the Mayan Train project". El Universal. Retrieved February 23, 2019.
  5. Fuentes, Yngrid (November 15, 2018). "Tren Maya: así es el ambicioso proyecto que propone AMLO y tiene un costo de miles de millones de dólares para México" (in Spanish). BBC Mundo. Retrieved February 23, 2019.
  6. "Tren Maya unirá Tabasco, Campeche, Chiapas, Yucatán y Quintana Roo". Union Yucatán (in Spanish). August 14, 2018. Retrieved February 23, 2019.
  7. "Mexico launches $7.4bn Tren Maya railway project". BBC News. December 17, 2018. Retrieved February 23, 2019.
  8. Sherman, Christopher (April 17, 2019). "Mayan Train's fast track raising concerns in Mexico". The Washington Post. Associated Press. Archived from the original on April 17, 2019. Retrieved April 19, 2019.
  9. Morgan, Martin (March 5, 2019). "Mexico to 'speed up' Maya train route". BBC News. Retrieved April 17, 2019.
  10. Gobierno inicia proceso de consulta ciudadana e indígena para Tren Maya; se realizará el 15 diciembre Aristegui Noticias, November 15, 2019
  11. "En la consulta sobre el Tren Maya, 92.3% votó por el "Sí"y 7.4% por el "No"" [In the consultation on the Mayan Train, 92.3% voted "Yes" and 7.4% "No"], El Economista (in Spanish), December 16, 2019
  12. Arturo Rodriguez Garcia (December 16, 2019), "A favor del Tren Maya el 92.3% de los consultados el fin de semana" [92.3% of those consulted about the Maya Train over the weekend in favor], Proceso (in Spanish)
  13. Osvaldo Córdova (December 17, 2019). "Solo votó el 2.86% del padrón por Tren Maya" [Only 2.86% of the registered voted for Maya Train]. Diario Contra Replica (in Spanish).
  14. Alexis Ortiz (December 20, 2019). "Rechaza ONU consulta sobre el Tren Maya" [UN rejects consultation on the Maya Train]. El Universal (in Spanish).
  15. Tourliere, Matieu (December 23, 2019). "El gobierno de AMLO reprocha críticas de la ONU-DH sobre consulta por Tren Maya" [The AMLO government reproaches UNHCR critics over consultation for Maya Train]. Proceso (in Spanish). Archived from the original on December 24, 2019.
  16. "Progreso and Umán added to Mayan Train route". Yucatán Magazine. June 20, 2022.
  17. Zavala, Misael (December 9, 2018). "AMLO's Mayan Train will cost 150,000 million pesos". El Universal. Retrieved February 23, 2019.
  18. Veronica Garibay (October 26, 2021). "Mayan Train expected to cost over 60 billion more: sources say two new museums are in the talks". Yucatan Magazine.
  19. "El costo del Tren Maya, para arriba" (in Spanish). Diario de Yucatán. October 5, 2020.
  20. "Turismo domina el PEF con presupuesto para Tren Maya; proyectan aumento de 641.7% en 2021". www.msn.com. Excelsior. Retrieved September 9, 2020.
  21. "AMLO: Una empresa militar administrará y operará el Tren Maya". Diario de Yucatán (in Spanish). December 20, 2020.
  22. "Todo el dinero generado por el Tren Maya irá al Ejército, afirma Jiménez Pons". Diario de Yucatán (in Spanish). March 16, 2021.
  23. "¿Cuánto saldrá viajar en el Tren Maya? Checa los costos". El Financiero (in Spanish). Retrieved September 28, 2021.
  24. "Tren Maya será turístico, de carga y de pasajeros: Arturo Núñez". Forbes (in Spanish). October 15, 2018. Retrieved February 23, 2019.
  25. "Seven tenders ready for the construction of the Maya Train". The Yucatan Times. March 4, 2019. Retrieved April 17, 2019.
  26. "Todo lo que sabemos hasta ahora sobre el Tren Maya". Diario de Yucatán (in Spanish). January 13, 2021.
  27. Juan Manuel Contreras (February 1, 2020). "Positivo que tramo del Tren Maya pase por debajo de Mérida: Concanaco" [Positive that the Mayan Train section passes under Mérida: Concanaco]. La Jornada (in Spanish).
  28. Veronica Garibay (September 23, 2021). "30% of La Plancha to be sold to the private sector". Yucatán Magazine.
  29. Carlos Rosado van der Gracht (November 18, 2021). "Mexico reverses on Mayan Train station, plans new La Plancha stop in 2025". Yucatan Magazine.
  30. "Portuguese company to start building first Tren Maya stretch on April 30th". Yucatan News. April 27, 2020. Retrieved December 10, 2021.
  31. "BlackRock, el gigante financiero acusado por corrupción y daño ambiental, es aliado en Tren Maya". www.msn.com (in Spanish). Sin Embargo. September 4, 2020. Retrieved September 8, 2020.
  32. "Tramo 5 del Tren Maya, declarado desierto; rechazan propuesta de BlackRock". www.msn.com. Forbes Mexico. Retrieved September 9, 2020.
  33. Urrutia, Alonso; Méndez, Enrique (September 8, 2020). "AMLO: participará en el Tren Maya la financiera BlackRock". www.msn.com (in Spanish). La Jornada. Retrieved September 8, 2020.
  34. "Tren Maya Railway Project". Railway Technology.
  35. "Shades of Line 12: Maya Train timelines not realistic, say private firms". Mexico News Daily. June 28, 2021. Retrieved December 10, 2021. A market survey conducted by Fonatur, PricewaterhouseCoopers and other consultants in 2019 found that a majority of 21 construction companies believed that a period of at least 36 months was needed to build a 250-kilometer section of railroad – provided everything went smoothly. However, "companies with more experience in the construction of railroad tracks favor a period between 36 and 48 months", the survey report said.
  36. Kitroeff, Natalie; Abi-Habib, Maria; Glanz, James; Lopez, Oscar; Cai, Weiyi; Grothjan, Evan; Peyton, Miles; Cegarra, Alejandro (June 13, 2021). "Why the Mexico City Metro Collapsed". The New York Times. Retrieved December 10, 2021. bad welds, critical mistakes that likely caused the crash. That is one of the primary explanations being considered by Mexico City officials, according to several people familiar with the official investigations into the disaster, and it underscores a pattern of political expediency and haphazard work as the metro was being built.
  37. Jessica Ruiz (January 19, 2022). "Tren Maya ya no pasará por Playa del Carmen". Diario de Yucatán (in Spanish).
  38. Carlos Rosado van der Gracht (June 23, 2021). "Residents take action to clear La Plancha of garbage". Yucatán Magazine.
  39. Carlos Rosado van der Gracht (March 18, 2022). "Mexican celebrities join indigenous groups against the Mayan Train". Yucatán Magazine.
  40. "El Tren Maya tiene una cuarta parte construida y casi 20% de gasto". Obras (in Spanish). February 15, 2022. Retrieved July 16, 2022.
  41. Alejandro de la Rosa (July 27, 2023). "Construcción del Tren Maya tiene avance de 67% a junio: SHCP". El Economista.
  42. "Maya Train Gets Official Date To Start Operations This Year". Cancun Sun. March 1, 2023.
  43. Carrillo, Emmanuel (May 28, 2021). "Xiinbal, Janal y P'atal: así serán los convoyes del Tren Maya". Forbes México (in Mexican Spanish). Retrieved September 15, 2023.
  44. "Primeras fotos del Tren Maya: así lucirán los vagones por dentro". Noticias de turismo REPORTUR (in Spanish). May 29, 2021. Retrieved September 15, 2023.
  45. "Proyecto del Tren Maya". Alstom (in Spanish). Retrieved September 12, 2023.
  46. "The Mayan train project". Alstom. Retrieved September 14, 2023.
  47. EZLN reitera rechazo a megaproyectos de AMLO El Segundero, January 1, 2020
  48. "El CNI esboza su estrategia contra el Tren Maya" [The CNI lays out it strategy against the Maya Train]. Proceso (in Spanish). January 4, 2020.
  49. Jose Raul Linares (February 1, 2020). "Otorgan suspensión provisional contra el Tren Maya por "consulta simulada"" [Provisional injunction granted against the Mayan Train for "simulated consultation"]. La Jornada (in Spanish).
  50. Rosa Santana (February 1, 2020). "AMLO defiende el Tren Maya tras suspensión provisional ordenada por un tribunal" [AMLO defends the Mayan Train after provisional injunction ordered by a court]. La Jornada (in Spanish).
  51. "Mayan communities of Campeche deliver 268 thousand signatures against the Mayan Train". Yucatan Times. November 26, 2020.
  52. Tourliere, Mathieu (January 21, 2021). "Habitantes de 3 municipios de Yucatán logran suspensión provisional de las obras del Tren Maya". proceso.com.mx (in Spanish). Proceso. Retrieved January 21, 2021.
  53. Carlos Rosado van der Gracht (October 15, 2021). "In Europe, Mexican Indigenous organizations denounce the Mayan Train". Yucatan Magazine.
  54. "Another injunction against the Tren Maya in Campeche". Yucatan Times. March 4, 2021.
  55. Carlos Rosado van der Gracht (January 6, 2022). "New legal challenges to Mayan Train ignored by AMLO's government". Yucatan Magazine.
  56. "Les gusta el chisme: Gobierno federal responde con campaña a artistas y ambientalistas por Tren Maya". Animal Político (in Spanish). March 31, 2022. Retrieved April 23, 2022.
  57. "No tenemos notificación oficial sobre suspensión de construcción de tramo 5 de Tren Maya: AMLO". El Financiero (in Spanish). April 19, 2022. Retrieved April 23, 2022.
  58. "Mayan Train protestors tie themselves to bulldozers, delaying new jungle path". Yucatán Magazine. March 29, 2022.
  59. Carlos Rosado van der Gracht (July 7, 2022). "Chemax protestors barricade Mayan Train construction site". Yucatán Magazine.
  60. Carlos Rosado van der Gracht (January 21, 2021). "Tren Maya leads to amazing discovery of over 8000 archaeological remains in Yucatán". Yucatán Magazine.
  61. "Más de 2 mil jaguares en peligro por el Tren Maya". El Universal (in Spanish). January 7, 2019. Retrieved June 6, 2020.
  62. "Fonatur accused of logging more than 144 hectares of forest land for the Tren Maya". Yucatan Times. October 21, 2021.
  63. "Mexico decrees automatic approval for Mayan Train project". Yucatán Magazine. November 23, 2021.
  64. "Maya Train chooses diesel over electric but source of fuel in doubt". June 9, 2020.
  65. "Maya Train to run on electricity on one-half of its route". August 6, 2020.
  66. "Derailing Tren Maya". 52 Documentary Series. Voice of America News. October 5, 2023. Retrieved October 26, 2023.

Further reading