Fukushima nuclear accident
The Fukushima nuclear accident was a major nuclear accident at the Fukushima Daiichi nuclear power plant in Ōkuma, Fukushima, Japan which began on March 11, 2011. The proximate cause of the accident was the 2011 Tōhoku earthquake and tsunami, which resulted in electrical grid failure and damaged nearly all of the power plant's backup energy sources. The subsequent inability to sufficiently cool reactors after shutdown compromised containment and resulted in the release of radioactive contaminants into the surrounding environment.[9][10] The accident was rated seven (the maximum severity) on the INES by NISA, following a report by the JNES.[11][12]
Part of the 2011 Tōhoku earthquake and tsunami | |
Date | 11 March 2011 |
---|---|
Location | Ōkuma and Futaba, Fukushima, Japan |
Coordinates | 37°25′17″N 141°1′57″E |
Outcome | INES Level 7 (major accident) |
Deaths | 1 confirmed from radiation (lung cancer, 4 years later),[2] and 2,202 from evacuation.[3] |
Non-fatal injuries | 6 with cancer or leukemia,[4] 16 with physical injuries due to hydrogen explosions.[5] 37 people total with physical injuries,[6] 2 workers taken to hospital with radiation burns[7][8] |
Displaced | +164,000 local residents |
No adverse health effects among Fukushima residents or power station workers have been documented that are directly attributable to radiation exposure from the accident.[13]: 106 [14][9] Criticisms have been made about the public perception of radiological hazards resulting from accidents and the implementation of evacuations (similar to the Chernobyl nuclear accident), as they caused much more harm than they prevented.[15] Following the accident, at least 164,000 residents of the surrounding area were permanently or temporarily displaced (either voluntarily or by evacuation order).[16] This response resulted in at least 51 fatalities,[17] with more attributed to subsequent stress or fear of radiological hazards.[18][19][20]
Investigations faulted lapses in safety and oversight, namely failures in risk assessment and evacuation planning.[9] Controversy surrounds the disposal of treated wastewater once used to cool the reactor, resulting in numerous protests in neighboring countries.[21]
Background
The Fukushima Daiichi Nuclear Power Plant consisted of six General Electric (GE) light water boiling water reactors (BWRs). Unit 1 was a GE type 3 BWR. Units 2-5 were type 4. Unit 6 was a type 5. During the 12-year construction of the power station, improvements in technology and design allowed for improvements to be made in the reactors which were constructed sequentially (beginning with unit 1, ending with unit 6).[9]
At the time of the Tōhoku earthquake on 11 March 2011, units 1–3 were operating. However, the spent fuel pools of all units still required cooling.[9][22][10]
Materials
Many of the internal components and fuel assembly cladding are made from a zirconium alloy (Zircaloy) for its low neutron cross-section. At normal operating temperatures (~300 °C (572 °F), it is inert. However, above 1,200 degrees Celsius (2,190 °F), Zircaloy can be oxidized by steam to form hydrogen gas[23] or by uranium dioxide to form uranium metal.[24][25] Both of these reactions are exothermic. In combination with the exothermic reaction of boron carbide with stainless steel, these reactions can contribute to the overheating of a reactor.[26]
Isolated cooling systems
In the event of an emergency situation, reactor pressure vessels (RPV) are automatically isolated from the turbines and main condenser and are instead switched to a secondary condenser system which is designed to cool the reactor without the need for pumps powered by external power or generators. The isolation condenser (IC) system involved a closed coolant loop from the pressure vessel with a heat exchanger in a dedicated condenser tank. Steam would be forced into the heat exchanger by the reactor pressure, and the condensed coolant would be fed back into the vessel by gravity. Each reactor was initially designed to be equipped with two redundant ICs which were each capable of cooling the reactor for at least 8 hours (at which point, the condenser tank would have to be refilled). However, it was possible for the IC system to cool the reactor too rapidly shortly after shutdown which could result in undesirable thermal stress on the containment structures. To avoid this, protocol called for reactor operators to manually open and close the condenser loop using electrically operated control valves.[9]
After the construction of unit 1, the following units were designed with new open-cycle reactor core isolation cooling (RCIC) systems. This new system utilized the steam from the reactor vessel to drive a turbine which would power a pump to inject water into the pressure vessel from an external storage tank to maintain the water level in the reactor vessel and was designed to operate for at least 4 hours (until the depletion of coolant or mechanical failure). Additionally, this system could be converted into a closed-loop system which draws coolant from the suppression chamber (SC) instead of the storage tank, should the storage tank be depleted. Although this system could function autonomously without an external energy source (besides the steam from the reactor), DC power was needed to remotely control it and receive parameters and indications and AC power was required to power the isolation valves.[9]
In an emergency situation where backup on-site power was partially damaged or insufficient or to last until a grid connection to off-site power could be restored, these cooling systems could no longer be relied upon to reliably cool the reactor. In such a case, the expected procedure was to vent both the reactor vessel and primary containment using electrically or pneumatically operated valves using the remaining electricity on site. This would lower the reactor pressure sufficiently to allow for low-pressure injection of water into the reactor using the fire protection system in order to replenish water lost to evaporation.[27]
On-site backup power
In the event of a loss of off-site power, emergency diesel generators (EDG) would automatically start in order to provide AC power.[9][28] Two EDGs were available for each of units 1–5 and three for unit 6.[9][29] Of the 13 EDGs, 10 were water-cooled and placed in the basements about 7–8 m below the ground level. The coolant water for the EDGs was carried by a number of seawater pumps placed on the shoreline which also provide water for the main condenser. These components were unhoused and only protected by the seawall. The other three EDGs were air-cooled and were connected to units 2, 4, and 6. The air-cooled EDGs for units 2 and 4 were placed on the ground floor of the spent fuel building, but the switches and various other components were located below, in the basement. The third air-cooled EDG was in a separate building placed inland and at higher elevation. Although these EDGs are intended to be used with their respective reactors, switchable interconnections between unit pairs (1 and 2, 3 and 4, and 5 and 6) allowed reactors to share EDGs should the need arise.[9]
The power station was also equipped with backup DC batteries kept charged by AC power at all times, designed to be able to power the station for approximately 8 hours without EDGs. In units 1, 2, and 4, the batteries were located in the basements alongside the EDGs. In units 3, 5, and 6, the batteries were located in the turbine building where they were raised above ground level.
In the late 1990s, three additional EDGs were placed in new buildings located inland and at higher elevation to comply with new regulatory requirements, but the switching stations that connected the EDGs to units 1–5 were located in the turbine buildings. Only the switching station for unit 6 was inside of the reactor building.[30]
Fuel inventory
The units and central storage facility contained the following numbers of fuel assemblies:[31]
Location | Unit 1 | Unit 2 | Unit 3 | Unit 4 | Unit 5 | Unit 6 | Central storage |
---|---|---|---|---|---|---|---|
Reactor fuel assemblies | 400 | 548 | 548 | 0 | 548 | 764 | N/A |
Spent fuel assemblies[32] | 292 | 587 | 514 | 1331 | 946 | 876 | 6375[33] |
Fuel type | UO 2 | UO 2 | UO 2/MOX | UO 2 | UO 2 | UO 2 | UO 2 |
New fuel assemblies[34] | 100 | 28 | 52 | 204 | 48 | 64 | N/A |
In September 2010, Reactor 3 was partially fueled by mixed-oxides (MOX).[9][35] There was no MOX (mixed oxide) fuel in any of the cooling ponds at the time of the incident.
Earthquake tolerance
The original design basis was a zero-point ground acceleration of 250 Gal and a static acceleration of 470 Gal,[9] based on the 1952 Kern County earthquake (0.18 g, 1.4 m/s2, 4.6 ft/s2).[36] After the 1978 Miyagi earthquake, when the ground acceleration reached 0.125 g (1.22 m/s2, 4.0 ft/s2) for 30 seconds, no damage to the critical parts of the reactor was found.[36] In 2006, the design of the reactors were reevaluated with new standards (which included vertical acceleration and differentiated E/W and N/S motion) which found the reactors would withstand accelerations ranging from 412 Gal to 489 Gal.[9]
Accident
Earthquake
The 9.0 MW earthquake occurred at 14:46 on Friday, 11 March 2011, with the epicenter off of the east coast of the Tōhoku region.[37] It produced maximum ground g-forces of 0.56, 0.52, 0.56 at units 2, 3, and 5 respectively. This exceeded the seismic reactor design tolerances of 0.45, 0.45, and 0.46 g for continued operation, but the seismic values were within the design tolerances at units 1, 4, and 6.[38]
Upon detecting the earthquake, all three operating reactors (units 1, 2, and 3) automatically shut down. Due to expected grid failure and damage to the switch station as a result of the earthquake, the power station automatically started up the EDGs, isolated the reactor from the primary coolant loops, and activated the emergency shutdown cooling systems.
Tsunami and loss of power
The largest tsunami wave was 13–14 m (43–46 feet) high and hit approximately 50 minutes after the initial earthquake, overtopping the seawall and exceeding the plant's ground level, which was 10 m (33 ft) above the sea level.[39]
The waves first damaged the seawater pumps along the shoreline, disabling the 10 water cooled EDGs. The waves then flooded all turbine and reactor buildings, damaging EDGs and other electrical components and connections located on the ground or basement levels[27][9][29] at approximately 15:41.[40] The switching stations that provided power from the three EDGs located higher on the hillside also failed when the building that housed them flooded.[30] One air cooled EDG, that of unit 6, was unaffected by the flooding and continued to operate. The DC batteries for units 1, 2, and 4 were also inoperable shortly after flooding.
As a result, units 1–5 lost AC power and DC power was lost in units 1, 2, and 4.[9] In response, the operators assumed a loss of coolant in units 1 and 2, developing a plan in which they would vent the primary containment and inject water into the reactor vessels with firefighting equipment.[9] TEPCO notified authorities of a "first-level emergency".[41]
Two workers were killed by the impact of the tsunami.[42]
The dry cask storage building was also flooded, causing some concerns about possible damage.[9]
Unit 1
The isolation condenser (IC) was functioning prior to the tsunami, but the DC-operated control valve outside of the primary containment had been in the closed position at the time to prevent thermal stresses on the reactor components. This status was uncertain at the time due to a loss of indications in the control room, who had correctly assumed loss of coolant (LOC). 3 hours later, the plant operators attempted to manually open the control valve, but the IC failed to function, suggesting that the isolation valves were closed. Although they were kept open during IC operation, the loss of DC power in unit 1 (which occurred shortly prior to the loss of AC power) automatically closed the AC-powered isolation valves in order to prevent uncontrolled cooling or a potential LOC. Although this status was unknown to the plant operators, they correctly interpreted the loss of function in the IC system and manually closed the control valves. The plant operators would continue to periodically attempt to restart the IC in the following hours and days, but it did not function.[9]
The plant operators then attempted to utilize the building's fire protection (FP) equipment, operated by a diesel-driven fire pump (DDFP), in order to inject water into the reactor vessel. A team was dispatched to the reactor building (RB) in order to carry out this task, but the team found that the reactor pressure had already increased significantly to 7 MPa, which was many times greater than the limit of the DDFP which could only operate below 0.8 MPa. Additionally, the team detected high levels of radiation within the RB, indicating damage to the reactor core, and found that the primary containment vessel (PCV) pressure (0.6 MPa) exceeded design specifications (0.528 MPa). In response to this new information, the reactor operators began planning to lower the PCV pressure by venting. The PCV reached its maximum pressure of 0.84 MPa at 02:30, after which it stabilized around 0.8 MPa. Venting of the PCV was completed later that afternoon at 14:00.[9]
At the same time, pressure in the reactor vessel had been decreasing to equalize with the PCV, and the workers prepared to inject water into the reactor vessel using the DDFP once the pressure had decreased below the 0.8 MPa limit. Unfortunately, the DDFP was found to be inoperable and a fire truck had to be hooked up to the FP system. This process took about 4 hours, as the FP injection port was hidden under debris. The next morning (March 12, 04:00), approximately 12 hours after loss of power, freshwater injection into the reactor vessel began, later replaced by a water line at 09:15 leading directly from the water storage tank to the injection port to allow for continuous operation (the fire engine had to be periodically refilled). This continued into the afternoon until the freshwater tank was nearly depleted. In response, injection stopped at 14:53 and the injection of seawater, which had collected in a nearby valve pit (the only other source of water), began.[9]
Power was restored to unit 1 (and 2) using a mobile generator at 15:30 on March 12.[9][43]
At 15:36, a hydrogen explosion damaged the secondary confinement structure (the RB). The cause was unknown to the workers at the time, most of whom evacuated shortly after the explosion. The debris produced by the explosion damaged the mobile emergency power generator and the seawater injection lines. The seawater injection lines were repaired and put back into operation at 19:04 until the valve pit was nearly depleted of seawater at 01:10 on the 14th. The seawater injection was temporarily stopped in order to refill the valve pit with seawater using a variety of emergency service and JSDF vehicles. However, the process to restart seawater injection was interrupted by another explosion in the unit 3 RB at 11:01 which damaged water lines and prompted another evacuation. Injection of seawater into unit 1 would not resume until that evening, after 18 hours without cooling.[9][44][45]
Subsequent analysis in November suggested that this extended period without cooling resulted in the melting of the fuel in unit 1, most of which would have escaped the reactor pressure vessel (RPV) and embedded itself into the concrete at the base of the PCV. Although at the time it was difficult to determine how far the fuel had eroded and diffused into the concrete, it was estimated that the fuel remains within the PCV.[46]
In November 2013, Mari Yamaguchi reported for Associated Press that there are computer simulations that suggest that "the melted fuel in Unit 1, whose core damage was the most extensive, has breached the bottom of the primary containment vessel and even partially eaten into its concrete foundation, coming within about 30 cm (1 ft) of leaking into the ground" – a Kyoto University nuclear engineer said with regard to these estimates: "We just can't be sure until we actually see the inside of the reactors."[47]
TEPCO estimated for Unit 1 that "the decay heat must have decreased enough, the molten fuel can be assumed to remain in PCV (primary containment vessel)".[48]
In February 2015, TEPCO started the muon scanning process for Units 1, 2, and 3.[49][50] With this scanning setup it was possible to determine the approximate amount and location of the remaining nuclear fuel within the RPV, but not the amount and resting place of the corium in the PCV. In March 2015 TEPCO released the result of the muon scan for Unit 1 which showed that no fuel was visible in the RPV, which would suggest that most if not all of the molten fuel had dropped onto the bottom of the PCV – this will change the plan for the removal of the fuel from Unit 1.[51][52]
Unit 2
Unit 2 was the only other operating reactor which experienced total loss of AC and DC power. Prior to blackout, the RCIC was functioning as designed without the need for operator intervention. The safety relief valve (SRV) would intermittently release steam directly into the PCV suppression torus at its design pressure and the RCIC properly replenished lost coolant. However, following the total blackout of unit 2, the plant operators (similar to unit 1) assumed the worst case scenario and prepared for a LOC incident. However, when a team was sent to investigate the status of the RCIC of unit 2 the following morning (02:55), they confirmed that the RCIC was operating with the PCV pressure well below design limits. Based on this information, efforts were focused onto unit 1. However, the condensate storage tank from which the RCIC draws water from was nearly depleted by the early morning, and so the RCIC was manually reconfigured at 05:00 to recirculate water from the suppression chamber instead.[9]
On the 13th, unit 2 was configured to vent the PCV automatically (manually opening all valves, leaving only the rupture disk) and preparations were made to inject seawater from the valve pit via the FP system should the need arise. However, as a result of the explosion in unit 3 the following day, the seawater injection setup was damaged and the isolation valve for the PCV vent was found to be closed and inoperable.[9]
At 13:00 on the 14th, the RCIC pump for unit 2 failed after 68 hours of continuous operation. With no way to vent the PCV, in response, a plan was devised to delay containment failure by venting the reactor vessel into the PCV using the SRV in order to allow for seawater injection into the reactor vessel.[9]
The following morning (March 15, 06:15), another explosion was heard on site coinciding with a rapid drop of suppression chamber pressure to atmospheric pressure, interpreted as a malfunction of suppression chamber pressure measurement. Due to concerns about the growing radiological hazard on site, almost all workers evacuated to the Fukushima Daini Nuclear Power Plant.[9]
In February 2017, six years after the accident, radiation levels inside the Unit 2 containment building were crudely estimated to be about 650 Sv/h.[53] The estimation was revised later to 80 Sv/h.[54] These readings were the highest recorded since the accident occurred in 2011 and the first recorded in that area of the reactor since the meltdowns. Images showed a hole in metal grating beneath the reactor pressure vessel, suggesting that melted nuclear fuel had escaped the vessel in that area.[55]
In February 2017, TEPCO released images taken inside unit 2 by a remote-controlled camera that show a 2 m (6.5 ft) wide hole[56] in the metal grating under the pressure vessel in the reactor's primary containment vessel,[57] which could have been caused by fuel escaping the pressure vessel, indicating a meltdown/melt-through had occurred, through this layer of containment. Ionizing radiation levels of about 210 sieverts (Sv) per hour were subsequently detected inside the Unit 2 containment vessel.[58] Undamaged spent fuel typically has values of 270 Sv/h, after ten years of cold shutdown with no shielding.[59]
In January 2018, a remote-controlled camera confirmed that nuclear fuel debris was at the bottom of the Unit 2 PCV, showing fuel had escaped the RPV. The handle from the top of a nuclear fuel assembly was also observed, confirming that a considerable amount of the nuclear fuel had melted.[60][61]
Unit 3
Although AC power was lost, some DC power was still available in unit 3 and the workers were able to remotely confirm that the RCIC system was continuing to cool the reactor. However, knowing that their DC supply was limited, the workers managed to extend the backup DC supply to about 2 days by disconnecting nonessential equipment, until replacement batteries were brought from a neighboring power station on the morning of the 13th (with 7 hours between loss and restoration of DC power). At 11:36 the next day, after 20.5 hours of operation, the RCIC system failed. In response, the high pressure coolant injection (HPCI) system was activated to alleviate the lack of cooling while workers continued to attempt to restart the RCIC. Additionally, the FP system was utilized to spray the PCV (mainly the SC) with water in order to slow the climbing temperatures and pressures of the PCV.[9]
On the morning of the 13th (02:42), after DC power was restored by new batteries,[9][43] the HPCI system showed signs of malfunction. The HPCI isolation valve failed to activate automatically upon achieving a certain pressure. In response, the workers decided to switch off HPCI and begin injection of water via the lower pressure firefighting equipment. However, the workers found that the SRV did not operate to relieve pressure from the reactor vessel in order to allow water injection by the DDFP. In response, workers attempted to restart the HPCI and RCIC systems, but both failed to restart. Following this loss of cooling, workers established a water line from the valve pit in order to inject seawater into the reactor alongside unit 2. However, water could not be injected due to RPV pressures exceeding the pump capability. Similarly, preparations were also made to vent the unit 3 PCV, but PCV pressure was not sufficient to burst the rupture disk.[9]
Later that morning (9:08), workers were able to depressurize the reactor by operating the safety relief valve using batteries collected from nearby automobiles. This was shortly followed by the bursting of the venting line rupture disk and the depressurization of the PCV. Unfortunately, venting was quickly stopped by a pneumatic isolation valve which closed on the vent path due to a lack of compressed air, and venting was not resumed until over 6 hours later once an external air compressor could be installed. Despite this, the reactor pressure was immediately low enough to allow for water injection (borated freshwater, as ordered by TEPCO) using the FP system until the freshwater FP tanks were depleted, at which point the injected coolant was switched to seawater from the valve pit.[9]
Cooling was lost once the valve pit was depleted, but was quickly resumed two hours later (unit 1 cooling was postponed until the valve pit was filled). However, despite being cooled, PCV pressure continued to rise and the RPV water level continued to drop until the fuel became uncovered on the morning of the 14th (6:20), as indicated by a water level gauge, which was followed by workers evacuating the area out of concerns about a possible second hydrogen explosion similar to unit 1.[9]
Shortly after work resumed to reestablish coolant lines, an explosion occurred in the unit 3 RB at 11:01 on March 14, which further delayed unit 1 cooling and damaged unit 3's coolant lines. Work to reestablish seawater cooling directly from the ocean began two hours later, and cooling of unit 3 resumed in the afternoon (approximately 16:00) and continued until cooling was lost once more as a result of site evacuation on the 15th.[9]
In August 2014, TEPCO released a new revised estimate that reactor 3 had a complete melt through in the initial phase of the accident. According to this new estimate within the first three days of the accident the entire core content of reactor 3 had melted through the RPV and fallen to the bottom of the PCV.[62][63][64] These estimates were based on a simulation, which indicated that reactor 3's melted core penetrated through 1.2 m (3 ft 11 in) of the PCV's concrete base, and came close to 26–68 cm (10–27 in) of the PCV's steel wall.[65]
Unit 4
Unit 4 was not fueled at the time, but the unit 4 spent fuel pool (SFP) contained a number of fuel rods.[9]
On 15 March, an explosion was observed at the unit 4 RB during site evacuation. A team later returned to the power station to inspect unit 4, but were unable to do so due to the present radiological hazard.[9] The explosion damaged the fourth floor rooftop area of Unit 4, creating two large holes in a wall of the RB. The explosion was later found to be caused by hydrogen passing to unit 4 from unit 3 through shared pipes.[66]
The following day, on the 16th, an aerial inspection was performed by helicopter which confirmed there was sufficient water remaining in the SFP. On the 20th, water was sprayed into the uncovered SFP, later replaced by a concrete pump truck with a boom on the 22nd.[9]
Unit 5
Unit 5 was fueled and was undergoing a RPV pressure test at the time of the accident, but the pressure was maintained by an external air compressor and the reactor was not otherwise operating. Removal of decay heat using the RCIC was not possible, as the reactor was not producing sufficient steam. However, the water within the RPV proved sufficient to cool the fuel, with the SRV venting into the PCV, until AC power was restored on March 13 using the unit 6 interconnection, allowing the use of the low-pressure pumps of the residual heat removal (RHR) system.[9]
Cold shutdown was achieved in the afternoon on the 20th.[9]
Unit 6
Unit 6 was not operating, and its decay heat was low because it had been in an outage since August 2010.[9]
All but one EDG was disabled by the tsunami, allowing unit 6 to retain AC-powered safety functions throughout the incident. However, because the RHR was damaged, workers decided to activate the make-up water condensate system to maintain the reactor water level until the RHR was restored on the 20th.[9]
Cold shutdown was achieved on the 20th, less than an hour after unit 5.[9]
Central fuel storage areas
On 21 March, temperatures in the fuel pond had risen slightly, to 61 °C (142 °F), and water was sprayed over the pool.[6] Power was restored to cooling systems on 24 March and by 28 March, temperatures were reported down to 35 °C (95 °F).[67]
Evacuation
In the initial hours of the accident, in response to station blackout and uncertainty regarding the cooling status of units 1 and 2, a 2 km radius evacuation of 1,900 residents was ordered at 20:50.[68][69] However, due to difficulty coordinating with the national government,[70][71] a 3 km evacuation order of ~6,000 residents and a 10 km shelter-in-place order for 45,000 residents was established nearly simultaneously at 21:23. The following morning (05:44), this evacuation radius was expanded to 10 km by local authorities in response to the unit 1 core damage and plans to vent the PCV later that day. The evacuation radius was further revised at 18:25 to 20 km, involving a total of 78,000 residents, in response to the hydrogen explosion at unit 1.[68][69] However, miscommunication of this final evacuation order resulted in those within 20 km to shelter in place.[71][72] Additionally, many municipalities independently ordered evacuations ahead of orders from the national government due to loss of communication with authorities;[71] at the time of the 3 km evacuation order, the majority of residents within the zone had already evacuated.[71]
Due to the multiple overlapping evacuation orders, many residents had evacuated to areas which would shortly be designated as evacuation areas. This resulted in many residents having to move multiple times until they reached an area outside of the final 20 km evacuation zone. 20% of residents who were within the initial 2 km radius had to evacuate more than six times.[69]
Additionally, a 30 km shelter in place order was communicated on the 15th, although some municipalities within this zone had already decided to evacuate their residents. This order was followed by a voluntary evacuation recommendation on the 25th, although the majority of residents had evacuated from the 30 km zone by then.[68][69][71] The shelter in place order was lifted on April 22, but the evacuation recommendation remained.[71]
Fatalities
Within the 20 km evacuation zone, of an estimated 2,220 patients and elderly resided within hospitals and nursing homes,[73] 51 fatalities are attributed to the evacuation.[17]
Radionuclide release
The predominant mechanism by which fission products can leave the core during core melt is through vaporization, thus only relatively volatile nuclides mix with the vaporized coolant and can be transported by the flow of gas. This gas can then exit the RPV and into the PCV through small leak paths in imperfections in the RPV, but in a situation in which the RCIC is used, this gas flows through the RCIC system and into the suppression pool, where some of the vaporized or suspended fission products are condensed or captured (scrubbed) by the SC, although some remainder (notably, radioactive noble gasses) will remain vaporized or suspended inside of the PCV. From the PCV, similar to the RPV, some small quantity inevitably leaks through small imperfections in the structure, but the predominant designed path for the escape of suspended radionuclides is through venting of the PCV where they are dispersed by the vent stack. However, if the PCV is compromised, the gas will be released directly into the secondary containment, and the potential loss of the SC function would also increase the concentration of unwanted fission products in the gas.
The fraction of releases associated to certain events is debated, as some of the detected fluctuations in the environment do not strongly correlate with events at the power station.[9]
Once released into the atmosphere, those which remain in a gaseous phase will simply be diluted by the atmosphere, but some which precipitate will eventually settle on land or in the ocean. Thus, the majority (90~99%) of the radionuclides which are deposited are isotopes of iodine and caesium, with a small portion of tellurium, which are almost fully vaporized out of the core due to their low vapor pressure. The remaining fraction of deposited radionuclides are of less volatile elements such as barium, antimony, and niobium, of which less than a percent is evaporated from the fuel.[74]
Quantities of the released material are expressed in terms of the three predominant products released: caesium-137, iodine-131, and xenon-133. Estimates for atmospheric releases range from 7–20 PBq for Cs-137, 100–400 PBq for I-131, and 6,000–12,000 PBq for Xe-133.[9]
Approximately 40–80% of the atmospheric releases were deposited over the ocean.[75][76]
In addition to atmospheric deposition, there was also a significant quantity of direct releases into groundwater (and eventually the ocean) through leaks of coolant which had been in direct contact with the fuel. Estimates for this release vary from 1 to 5.5 PBq. Although the majority had entered the ocean shortly following the accident, a significant fraction remains in the groundwater and continues to mix with coastal waters.[9]
According to the French Institute for Radiological Protection and Nuclear Safety, the release from the accident represents the most important individual oceanic emissions of artificial radioactivity ever observed. The Fukushima coast has one of the world's strongest currents (Kuroshio Current). It transported the contaminated waters far into the Pacific Ocean, dispersing the radioactivity. As of late 2011 measurements of both the seawater and the coastal sediments suggested that the consequences for marine life would be minor. Significant pollution along the coast near the plant might persist, because of the continuing arrival of radioactive material transported to the sea by surface water crossing contaminated soil. The possible presence of other radioactive substances, such as strontium-90 or plutonium, has not been sufficiently studied. Recent measurements show persistent contamination of some marine species (mostly fish) caught along the Fukushima coast.[77]
Consequences
Evacuation
In January 2015, the number of residents displaced due to the accident was around 119,000, peaking at 164,000 in June 2012.[9] In terms of months of life lost, the loss of life would have been far smaller if all residents had done nothing at all, or were sheltered in place, instead of evacuated.[78][15]
In the former Soviet Union, many patients with negligible radioactive exposure after the Chernobyl accident displayed extreme anxiety about radiation exposure. They developed many psychosomatic problems, including radiophobia along with an increase in fatalistic alcoholism. As Japanese health and radiation specialist Shunichi Yamashita noted:[18]
We know from Chernobyl that the psychological consequences are enormous. Life expectancy of the evacuees dropped from 65 to 58 years – not because of cancer, but because of depression, alcoholism, and suicide. Relocation is not easy, the stress is very big. We must not only track those problems, but also treat them. Otherwise people will feel they are just guinea pigs in our research.[18]
A survey by the Iitate local government obtained responses from approximately 1,743 evacuees within the evacuation zone. The survey showed that many residents are experiencing growing frustration, instability, and an inability to return to their earlier lives. Sixty percent of respondents stated that their health and the health of their families had deteriorated after evacuating, while 39.9% reported feeling more irritated compared to before the accident.[79]
Summarizing all responses to questions related to evacuees' current family status, one-third of all surveyed families live apart from their children, while 50.1% live away from other family members (including elderly parents) with whom they lived before the disaster. The survey also showed that 34.7% of the evacuees have suffered salary cuts of 50% or more since the outbreak of the nuclear disaster. A total of 36.8% reported a lack of sleep, while 17.9% reported smoking or drinking more than before they evacuated.[79]
Stress often manifests in physical ailments, including behavioral changes such as poor dietary choices, lack of exercise, and sleep deprivation. Survivors, including some who lost homes, villages, and family members, were found likely to face mental health and physical challenges. Much of the stress came from lack of information and from relocation.[80][81]
A 2014 metareview of 48 articles indexed by PubMed, PsycINFO, and EMBASE, highlighted several psychophysical consequences among the residents in Miyagi, Iwate, Ibaraki, Tochigi and Tokyo. The resulting outcomes included depressive symptoms, anxiety, sleep disturbance, social functioning, social isolation, admission rates, suicide rates and cerebral structure changes, radiation impacting food safety, maternal anxiety and lowered maternal confidence.[19] The rates of psychological distress among evacuated people rose fivefold compared to the Japanese average due to the experience of the accident and evacuation.[20] An increase in childhood obesity in the area after the accident has also been attributed to recommendations that children stay indoors instead of going outside to play.[82]
Worldwide media coverage of the incident has been described as "ten years of disinformation", with media and environmental organizations routinely conflating the casualties of the earthquake and tsunami, with casualties of the nuclear incident. The incident dominated media coverage while the victims of the natural disasters were "ignored", and a number of media reports incorrectly describing thousands of victims of tsunami as if they were victims of the "nuclear disaster".[83]
Energy policy
Prior to the accident, over 25% of domestic electricity generation in Japan utilized nuclear power[84] and Japan had set a fairly ambitious GHG reduction target of 25% below 1990 levels by 2020, which involved increasing the share of nuclear power in electricity generation from 30% to 50%.[85] However, this plan was abandoned and target was quickly revised to a 3% emissions increase by 2020 following the accident,[86] alongside a focus on reducing dependence on nuclear power in favor of improved thermal efficiency in fossil fuel energy use and increasing the share of "renewables".[87] The contribution of nuclear energy dropped to less than a percent following the accident[84] and all nuclear reactors in the country were shut down by 2013.[88] This resulted in an increase in the share of fossil fuel energy use, which had increased to ~94% by 2015 (the highest of any IEA member state, with the remaining ~6% produced by renewables, an increase from 4% in 2010).[84] The required fossil fuel imports in 2011 resulted in a trade deficit for the first time in decades which would continue in the following decade.[87]
In the immediate aftermath, nine prefectures served by TEPCO experienced power rationing.[89] The government asked major companies to reduce power consumption by 15%, and some shifted their weekends to weekdays to smooth power demand.[90] As of 2013, TEPCO and eight other Japanese power companies were paying approximately 3.6 trillion JPY (37 billion USD) more in combined imported fossil fuel costs compared to 2010 to make up for the missing power.[91]
Elections
On 16 December 2012, Japan held its general election. The Liberal Democratic Party (LDP) had a clear victory, with Shinzō Abe as the new Prime Minister. Abe supported nuclear power, saying that leaving the plants closed was costing the country 4 trillion yen per year in higher costs.[92] The comment came after Junichiro Koizumi, who chose Abe to succeed him as premier, made a statement to urge the government to take a stance against using nuclear power.[93] A survey on local mayors by the Yomiuri Shimbun newspaper in 2013 found that most of them from cities hosting nuclear plants would agree to restarting the reactors, provided the government could guarantee their safety.[94] More than 30,000 people marched on 2 June 2013, in Tokyo against restarting nuclear power plants. Marchers had gathered more than 8 million petition signatures opposing nuclear power.[95]
Previously a proponent of building more reactors, Prime Minister Naoto Kan took an increasingly anti-nuclear stance following the accident. In May 2011, he ordered the aging Hamaoka Nuclear Power Plant closed over earthquake and tsunami concerns, and said he would freeze building plans. In July 2011, Kan said, "Japan should reduce and eventually eliminate its dependence on nuclear energy".[96]
International Impact
In the aftermath, Germany accelerated plans to close its nuclear power reactors and decided to phase the rest out by 2022[97] (see also Nuclear power in Germany). Belgium and Switzerland have also changed their nuclear policies to phase-out all nuclear energy operations.[98] Italy held a national referendum, in which 94 percent voted against the government's plan to build new nuclear power plants.[99] In France, President Hollande announced the intention of the government to reduce nuclear usage by one third. However, the government earmarked only one power station for closure – the aging Fessenheim Nuclear Power Plant on the German border – which prompted some to question the government's commitment to Hollande's promise. Industry Minister Arnaud Montebourg is on record as saying that Fessenheim will be the only nuclear power station to close. On a visit to China in December 2014 he reassured his audience that nuclear energy was a "sector of the future" and would continue to contribute "at least 50%" of France's electricity output.[100] Another member of Hollande's Socialist Party, the MP Christian Bataille, said that Hollande announced the nuclear curb to secure the backing of his Green coalition partners in parliament.[101]
China suspended its nuclear development program briefly, but restarted it shortly afterwards. The initial plan had been to increase the nuclear contribution from 2 to 4 percent of electricity by 2020, with an escalating program after that. Renewable energy supplies 17 percent of China's electricity, 16% of which is hydroelectricity. China plans to triple its nuclear energy output to 2020, and triple it again between 2020 and 2030.[102]
New nuclear projects were proceeding in some countries. KPMG reports 653 new nuclear facilities planned or proposed for completion by 2030.[103] By 2050, China hopes to have 400–500 gigawatts of nuclear capacity – 100 times more than it has now.[104] The Conservative Government of the United Kingdom is planning a major nuclear expansion despite some public objection. So is Russia.[105] India is also pressing ahead with a large nuclear program, as is South Korea.[106] Indian Vice President M Hamid Ansari said in 2012 that "nuclear energy is the only option" for expanding India's energy supplies,[107] and Prime Minister Modi announced in 2014 that India intended to build 10 more nuclear reactors in a collaboration with Russia.[108]
In the wake of the accident, the Senate Appropriations Committee requested the United States Department of Energy “to give priority to developing enhanced fuels and cladding for light water reactors to improve safety in the event of accidents in the reactor or spent fuel pools”.[109] This brief has led to ongoing research and development of Accident Tolerant Fuels, which are specifically designed to withstand the loss of cooling for an extended period, increase time to failure, and increase fuel efficiency.[110] This is accomplished by incorporating specially designed additives to standard fuel pellets and replacing or altering the fuel cladding in order to reduce corrosion, decrease wear, and reduce hydrogen generation during accident conditions.[111] While research is still ongoing, on 4 March 2018, the Edwin I. Hatch Nuclear Power Plant near Baxley, Georgia has implemented “IronClad” and “ARMOR” (Fe-Cr-Al and coated Zr claddings, respectively) for testing.[112]
Radiation effects in humans
Radiation exposure of those living in proximity to the accident site is expected to be below 10 mSv, over the course of a lifetime. In comparison, the dosage of background radiation received over a lifetime is 170 mSv.[113][114] Very few cancers are expected as a result of accumulated radiation exposures[115][116][117][118][119] and residents who were evacuated were exposed to so little radiation that radiation-induced health effects were likely to be below detectable levels.[120][121][83] There is no increase in miscarriages, stillbirths or physical and mental disorders in babies born after the accident.[14][122][123][13]
Outside the geographical areas most affected by radiation, even in locations within Fukushima prefecture, the predicted risks remain low, and no observable increases in cancer above natural variation in baseline rates are anticipated.
— World Health Organization, 2013
Estimated effective doses outside Japan are considered to be below (or far below) the levels regarded as very small by the international radiological protection community.[124][125] The Integrated Fukushima Ocean Radionuclide Monitoring project (InFORM) failed to show any significant amount of radiation[125] and as a result its authors received death threats from supporters of a "wave of cancer deaths across North America" theory.[126]
Thyroid cancer
The overwhelming majority of thyroid growths are benign growths that will never cause symptoms, illness, or death, even if nothing is ever done about the growth. Autopsy studies on people who died from other causes show that more than one third of adults technically have a thyroid growth/cancer.[127] As a precedent, in 1999 in South Korea, the introduction of advanced ultrasound thyroid examinations resulted in an explosion in the rate of benign thyroid cancers being detected and needless surgeries occurring.[128] Despite this, the death rate from thyroid cancer has remained the same.[128]
There is a statistically significant correlation between external radiation dose and thyroid cancer in those under the age of 18.[129] However, this is mostly attributable to the early detection of non-symptomatic disease cases by the screening-effect.[130] Rates of thyroid cancer in children controlled for examination frequency showed no association between the nuclear accident/radiation exposure and thyroid cancer.[131][132][133]
As of 2020, research into the correlation between air-dose and internal-dose and thyroid cancers remains ongoing. Further research is necessary in understanding the dose-response relationship and the prevalence of incident cancers.
Thyroid cancer is one of the most survivable cancers, with an approximate 94% survival rate after first diagnosis. That rate increases to a nearly 100% survival rate if caught early.[134] Cancer may spread to another part of the body, however, and in cases where the thyroid must be removed, the resulting hormonal deficiencies are terminal.[135] In January 2022, six such patients who were children at the time of the accident sued TEPCO for 616 million yen after developing thyroid cancer.[136]
Infant/fetal cancer risk
Evacuated infant girls, the most radiation-sensitive demographic, have an estimated increased lifetime risk of developing thyroid cancer of 1.25% (compared to 0.75% background risk), with the increase being slightly less for males. The risks from a number of additional radiation-induced cancers are also expected to be elevated. There is an estimated 7% higher relative risk of leukemia in males exposed as infants and a 6% higher relative risk of breast cancer in females exposed as infants.[137] In total, an overall 1% higher lifetime risk of developing cancers of all types is predicted for infant females, with the risk slightly lower for males.[137] The fetuses, depending on their sex, would have the same elevations in risk as the infant groups.[138]
Linear no-threshold models (LNT)
LNT models estimate that the accident would most likely cause 130 cancer deaths.[139][140][141] However, LNT models have large uncertainties and are not useful for estimating health effects from radiation,[142][143] especially when the effects of radiation on the human body are not linear, and with obvious thresholds.[144] Producing a statistically useful estimate would require an impractically large number of patients, and LNT models have been described as "junk science".[83] In September 2018, one cancer fatality was the subject of a financial settlement, to the family of a former nuclear station workman.[145]
Radiation effects in non-humans
On 21 March, the first restrictions were placed on the distribution and consumption of contaminated items.[146] However, the results of measurements of both the seawater and the coastal sediments led to the supposition that the consequences of the accident, in terms of radioactivity, would be minor for marine life as of autumn 2011. Despite caesium isotopic concentrations in the waters off of Japan being 10 to 1000 times above the normal concentrations prior to the accident, radiation risks are below what is generally considered harmful to marine animals and human consumers.[147]
As of March 2012, no cases of radiation-related ailments had been reported.[148]
Fisheries
Organisms that filter water and fish at the top of the food chain are, over time, the most sensitive to caesium pollution. It is thus justified to maintain surveillance of marine life that is fished in the coastal waters off Fukushima.[147] Migratory pelagic species are also highly effective and rapid transporters of pollutants throughout the ocean. Elevated levels of Cs-134 appeared in migratory species off the coast of California that were not seen prior to the accident.[149]
In April 2014, studies confirmed the presence of radioactive tuna off the coasts of the Pacific U.S.[150] Researchers carried out tests on 26 albacore tuna caught prior to the 2011 power plant accident and those caught after. However, the amount of radioactivity is less than that found naturally in a single banana.[151] Cs-137 and Cs-134 have been noted in Japanese whiting in Tokyo Bay as of 2016. "Concentration of radiocesium in the Japanese whiting was one or two orders of magnitude higher than that in the sea water, and an order of magnitude lower than that in the sediment." They were still within food safety limits.[152]
In June 2016, the political advocacy group "International Physicians for the Prevention of Nuclear War", asserted that 174,000 people have been unable to return to their homes and ecological diversity has decreased and malformations have been found in trees, birds, and mammals.[153] Although physiological abnormalities have been reported within the vicinity of the accident zone,[154] the scientific community has largely rejected any such findings of genetic or mutagenic damage caused by radiation, instead showing it can be attributed either to experimental error or other toxic effects.[155]
In February 2018, Japan renewed the export of fish caught off Fukushima's nearshore zone. According to prefecture officials, no seafood had been found with radiation levels exceeding Japan safety standards since April 2015. In 2018, Thailand was the first country to receive a shipment of fresh fish from Japan's Fukushima prefecture.[156] A group campaigning to help prevent global warming has demanded the Food and Drug Administration disclose the name of the importer of fish from Fukushima and of the Japanese restaurants in Bangkok serving it. Srisuwan Janya, chairman of the Stop Global Warming Association, said the FDA must protect the rights of consumers by ordering restaurants serving Fukushima fish to make that information available to their customers, so they could decide whether to eat it or not.[157]
On February 2022, Japan suspended the sale of black rockfish from Fukushima after it was discovered that one fish from Soma had 180 times more radioactive Cesium-137 than legally permitted. The high levels of radioactivity led investigators to believe it had escaped from a breakwater at the accident site, despite nets intended to prevent fish from leaving the area. A total of 44 other fish from the accident site show similar levels.[158]
Remediation and recovery
To assuage fears, the government enacted an order to decontaminate over a hundred areas where the level of additional radiation was greater than one millisievert per year. This is a much lower threshold than is necessary for protecting health. The government also sought to address the lack of education on the effects of radiation and the extent to which the average person was exposed.[159]
In 2018, tours to visit the accident area began.[160] In September 2020, The Great East Japan Earthquake and Nuclear Disaster Memorial Museum was opened in the town of Futaba, near the power plant. The museum exhibits items and videos about the earthquake and the nuclear accident. To attract visitors from abroad, the museum offers explanations in English, Chinese and Korean.[161]
Tokyo Electric Power Company (TEPCO) is going to remove the remaining nuclear fuel material from the plants. TEPCO completed the removal of 1535 fuel assemblies from the Unit 4 spent fuel pool in December 2014 and 566 fuel assemblies from the Unit 3 spent fuel pool in February 2021.[162] TEPCO plans to remove all fuel rods from the spent fuel pools of Units 1, 2, 5, and 6 by 2031 and to remove the remaining molten fuel debris from the reactor containments of Units 1, 2, and 3 by 2040 or 2050.[163] An ongoing intensive cleanup program to both decontaminate affected areas and decommission the plant will take 30 to 40 years from the accident, plant management estimated.[164]
Treating contaminated water
As of 2013, about 400 metric tons (390 long tons; 440 short tons) of cooling water per day was being pumped into the reactors. Another 400 metric tons (390 long tons; 440 short tons) of groundwater was seeping into the structure. Some 800 metric tons (790 long tons; 880 short tons) of water per day was removed for treatment, half of which was reused for cooling and half diverted to storage tanks.[165] Ultimately the contaminated water, after treatment to remove radionuclides other than tritium, has to be discharged into the Pacific.[164] TEPCO decided to create an underground ice wall to block the flow of groundwater into the reactor buildings. A $300 million 7.8 MW cooling facility freezes the ground to a depth of 30 meters.[166][167] As of 2019, the contaminated water generation had been reduced to 170 metric tons (170 long tons; 190 short tons) per day.[168]
In February 2014, NHK reported that TEPCO was reviewing its radioactivity data, after finding much higher levels of radioactivity than was reported earlier. TEPCO now says that levels of 5 MBq (0.12 millicuries) of strontium per liter (23 MBq/imp gal; 19 MBq/U.S. gal; 610 μCi/imp gal; 510 μCi/U.S. gal) were detected in groundwater collected in July 2013 and not the 900 kBq (0.02 millicuries) (4.1 MBq/imp gal; 3.4 MBq/U.S. gal; 110 μCi/imp gal; 92 μCi/U.S. gal) that were initially reported.[169][170]
On 10 September 2015, floodwaters driven by Typhoon Etau prompted mass evacuations in Japan and overwhelmed the drainage pumps at the stricken power plant. A TEPCO spokesperson said that hundreds of metric tons of radioactive water entered the ocean as a result.[171] Plastic bags filled with contaminated soil and grass were also swept away by the flood waters.[172]
As of October 2019, 1.17 million cubic meters of contaminated water was stored in the plant area. The water is being treated by a purification system that can remove radionuclides, except tritium, to a level that Japanese regulations allow to be discharged to the sea. As of December 2019, 28% of the water had been purified to the required level, while the remaining 72% needed additional purification. However, tritium cannot be separated from the water. As of October 2019, the total amount of tritium in the water was about 856 terabecquerels, and the average tritium concentration was about 0.73 megabecquerels per liter.[173]
A committee set up by the Japanese Government concluded that the purified water should be released to the sea or evaporated to the atmosphere. The committee calculated that discharging all the water to the sea in one year would cause a radiation dose of 0.81 microsieverts to the local people, whereas evaporation would cause 1.2 microsieverts. For comparison, Japanese people get 2100 microsieverts per year from natural radiation.[173] IAEA considers that the dose calculation method is appropriate. Further, the IAEA recommends that a decision on the water disposal must be made urgently.[174]
Despite the negligible doses, the Japanese committee is concerned that the water disposal may cause reputational damage to the prefecture, especially to the fishing industry and tourism.[173]
Tanks used to store the water are expected to be filled in 2023. In July 2022, Japan's Nuclear Regulation Authority approved discharging the treated water into the sea.[175] A US State Department spokesperson supported the decision. South Korea's foreign minister and activists from Japan and South Korea protested the announcement.[176] In April 2023, fishers and activists held protests in front of the Japanese embassy in the Philippines in opposition to the planned release of 1.3 million tons of treated water into the Pacific Ocean.[177] On 22 August, Japan announced that it would start releasing treated radioactive water from the tsunami-hit Fukushima nuclear plant into the Pacific Ocean in 48 hours, despite opposition from its neighbours.[178][179] Japan says the water is safe, many scientists agree, and the decision comes weeks after the UN's nuclear watchdog approved the plan; but critics say more studies need to be done and the release should be halted.[180][181] On 24 August, Japan begun the discharge of treated waste water into the Pacific Ocean, sparking protests in the region and retaliation from China, who said it would block all imports of seafood from Japan.[181][182]
Other radioactive substances created as a byproduct of the contaminated water purification process, as well as contaminated metal from the damaged plant, have drawn recent attention as the 3,373 waste storage containers for the radioactive slurry were found to be degrading faster than expected.[183]
Compensation and government expenses
Initial estimates of costs to Japanese taxpayers were in excess of 12 trillion yen ($100 billion).[184] In December 2016 the government estimated decontamination, compensation, decommissioning, and radioactive waste storage costs at 21.5 trillion yen ($187 billion), nearly double the 2013 estimate.[185] By 2021 12.1 trillion yen had already been spent, with 7 trillion yen on compensation, 3 trillion yen on decontamination, and 2 trillion yen on decommissioning and storage. Despite concerns, the government expected total costs to remain under budget.[186]
The amount of compensation to be paid by TEPCO is expected to reach 7 trillion yen.[187]
In March 2017, a Japanese court ruled that negligence by the Japanese government had led to the Fukushima accident by failing to use its regulatory powers to force TEPCO to take preventive measures. The Maebashi district court near Tokyo awarded ¥39 million (US$345,000) to 137 people who were forced to flee their homes following the accident.[188] On 30 September 2020, the Sendai High Court ruled that the Japanese government and TEPCO are responsible for the accident, ordering them to pay $9.5 million in damages to residents for their lost livelihoods.[189] In March 2022, Japan's Supreme Court rejected an appeal from TEPCO and upheld the order for it to pay damages 1.4 billion yen ($12 million) to about 3,700 people whose lives were harmed by the accident. Its decision covered three class-action lawsuits, among more than 30 filed against the utility.[190]
On 17 June 2022, the Supreme Court acquitted the government of any wrongdoing regarding potential compensation to over 3,700 people affected by the accident.[191]
On 13 July 2022, four former TEPCO executives were ordered to pay 13 trillion yen ($95 billion) in damages to the operator of power plant, in the civil case brought by Tepco shareholders.[192]
Equipment, facility, and operational changes
A number of nuclear reactor safety system lessons emerged from the incident. The most obvious was that in tsunami-prone areas, a power station's sea wall must be adequately tall and robust.[39] At the Onagawa Nuclear Power Plant, closer to the epicenter of 11 March earthquake and tsunami,[193] the sea wall was 14 meters (46 ft) tall and successfully withstood the tsunami, preventing serious damage and radioactivity releases.[194][195]
Nuclear power station operators around the world began to install passive autocatalytic recombiners ("PARs"), which do not require electricity to operate.[196][197][198] PARs work much like the catalytic converter on the exhaust of a car to turn potentially explosive gases such as hydrogen into water. Had such devices been positioned at the top of the reactor buildings, where hydrogen gas collected, the explosions would not have occurred and the releases of radioactive isotopes would arguably have been much less.[199]
Unpowered filtering systems on containment building vent lines, known as Filtered Containment Venting Systems (FCVS), can safely catch radioactive materials and thereby allow reactor core depressurization, with steam and hydrogen venting with minimal radioactivity emissions.[199][200] Filtration using an external water tank system is the most common established system in European countries, with the water tank positioned outside the containment building.[201] In October 2013, the owners of Kashiwazaki-Kariwa nuclear power station began installing wet filters and other safety systems, with completion anticipated in 2014.[202][203]
For generation II reactors located in flood or tsunami prone areas, a 3+ day supply of back-up batteries has become an informal industry standard.[204][205] Another change is to harden the location of back-up diesel generator rooms with water-tight, blast-resistant doors and heat sinks, similar to those used by nuclear submarines.[199] The oldest operating nuclear power station in the world, Beznau, which has been operating since 1969, has a 'Notstand' hardened building designed to support all of its systems independently for 72 hours in the event of an earthquake or severe flooding. This system was built prior to Fukushima Daiichi.[206][207]
Upon a station blackout, similar to the one that occurred after back-up battery supply was exhausted,[208] many constructed Generation III reactors adopt the principle of passive nuclear safety. They take advantage of convection (hot water tends to rise) and gravity (water tends to fall) to ensure an adequate supply of cooling water to handle the decay heat, without the use of pumps.[209][210]
As the crisis unfolded, the Japanese government sent a request for robots developed by the U.S. military. The robots went into the plants and took pictures to help assess the situation, but they couldn't perform the full range of tasks usually carried out by human workers.[211] The accident illustrated that robots lacked sufficient dexterity and robustness to perform critical tasks. In response to this shortcoming, a series of competitions were hosted by DARPA to accelerate the development of humanoid robots that could supplement relief efforts.[212][213] Eventually a wide variety of specially designed robots were employed (leading to a robotics boom in the region), but as of early 2016 three of them had promptly become non-functional due to the intensity of the radioactivity;[214] one was destroyed within a day.
Criticism
Prior safety concerns
On 5 July 2012, the NAIIC found that the causes of the accident had been foreseeable, and that the plant operator (TEPCO) had failed to meet basic safety requirements such as risk assessment, preparing for containing collateral damage, and developing evacuation plans. At a meeting in Vienna three months after the accident, the IAEA faulted lax oversight by the Japanese Ministry of Economy, Trade and Industry, saying the ministry faced an inherent conflict of interest as the government agency in charge of both regulating and promoting the nuclear power industry.[215] On 12 October 2012, TEPCO admitted that it had failed to take necessary measures for fear of inviting lawsuits or protests against its nuclear plants.[216][217][218]
Unit 1 EDG disabled by flooding in 1991
On 30 October 1991, one of unit 1's EDGs failed as a result of a condensate coolant leak in the turbine building, as reported by former employees in December 2011. A TEPCO report in 2011 detailed that the room was flooded through a door and some holes for cables, but the power supply was not cut off by the flooding. An engineer was quoted as saying that he informed his superiors of the possibility that a tsunami could damage the generators.
In response, TEPCO installed doors to prevent water from leaking into the generator rooms. The JNSC stated that it would revise its safety guidelines and would require the installation of additional power sources.[219]
Tsunami studies
In 1991, the U.S. Nuclear Regulatory Commission warned of a risk of losing emergency power in 1991 (NUREG-1150) and NISA referred to that report in 2004, but took no action to mitigate the risk.[220]
In 2000, an in-house TEPCO report recommended safety measures against seawater flooding, based on the potential of a 50 foot (15 m) tsunami. TEPCO did not act due to concerns about creating anxieties over the safety of the nuclear power plant.[221]
in 2002, the government earthquake research headquarters estimated that a tsunami up to 15.7 meters (52 ft) could hit the power station.[222]
In 2004, the cabinet office warned that tsunamis taller than the maximum of 5.6 meters (18 ft) forecast by TEPCO and government officials were possible.[223]
In 2008, another in-house study identified an immediate need to better protect the facility from flooding by seawater which cited the 15.7 meters (52 ft) estimate from the 2002 study.[222]
In 2009, the Active Fault and Earthquake Research Center urged TEPCO and NISA to revise their assumptions for possible tsunami heights upwards, based on his team's findings about the 869 Sanriku earthquake, but this was not seriously considered at the time.[221][224]
Communications
Many criticisms have been made which claim that the evacuation zone should have been further expanded, namely regarding the limited proliferation of data which governments of less affected areas may have acted upon. The national government only sent data from the SPEEDI network to the Fukushima prefectural government[225] and was later criticized for delaying the communication of data to the U.S. military.[226] Additionally, the U.S. military produced a detailed map using aircraft and provided it to the Ministry of Economy, Trade and Industry (METI) on 18 March and to the Ministry of Education, Culture, Sports, Science and Technology (MEXT) two days later, but no new evacuation plans were made a week after the accident.[227][228] The data was not sent to the prime minister or the Nuclear Safety Commission, for which the government was criticized, but was made accessible to the public on the 23rd.[229]
Record-keeping
The Japanese government did not keep records of key meetings during the crisis.[230] Emails from NISA to the Fukushima prefectural government, including evacuation and health advisories from 12 March 11:54 PM to 16 March 9 AM, went unread and were deleted.[225]
On 14 March 2011 TEPCO officials were instructed not to use the phrase "core meltdown" at press conferences.[231]
International reaction
The international reaction to the accident was diverse and widespread. Many inter-governmental agencies immediately offered help, often on an ad hoc basis. Responders included IAEA, World Meteorological Organization and the Preparatory Commission for the Comprehensive Nuclear Test Ban Treaty Organization.[234]
In May 2011, UK chief inspector of nuclear installations Mike Weightman traveled to Japan as the lead of an International Atomic Energy Agency (IAEA) expert mission. The main finding of this mission, as reported to the IAEA ministerial conference that month, was that risks associated with tsunamis in several sites in Japan had been underestimated.[235]
In September 2011, IAEA Director General Yukiya Amano said the Japanese nuclear disaster "caused deep public anxiety throughout the world and damaged confidence in nuclear power".[236] Following the accident, it was reported in The Economist that the IAEA halved its estimate of additional nuclear generating capacity to be built by 2035.[237]
Investigations
TEPCO released estimates of the state and location of the fuel in a November 2011 report.[46] The report concluded that the Unit 1 RPV was damaged during the accident and that "significant amounts" of molten fuel had fallen into the bottom of the PCV. The erosion of the concrete of the PCV by the molten fuel after the core meltdown was estimated to stop at approx. 0.7 m (2 ft 4 in) in depth, while the thickness of the containment floor is 7.6 m (25 ft). Gas sampling carried out before the report detected no signs of an ongoing reaction of the fuel with the concrete of the PCV and all the fuel in Unit 1 was estimated to be "well cooled down, including the fuel dropped on the bottom of the reactor". Fuel in Units 2 and 3 had melted, however less than in Unit 1. The report further suggested that "there is a range in the evaluation results" from "all fuel in the RPV (none fuel fallen to the PCV)" in Unit 2 and Unit 3, to "most fuel in the RPV (some fuel in PCV)". For Unit 2 and Unit 3 it was estimated that the "fuel is cooled sufficiently". According to the report, the greater damage in Unit 1 (when compared to the other two units) was due to the longer time that no cooling water was injected in Unit 1. This resulted in much more decay heat accumulating, as for about 1 day there was no water injection for Unit 1, while Unit 2 and Unit 3 had only a quarter of a day without water injection.[46]
Three investigations into the accident showed the man-made nature of the catastrophe and its roots in regulatory capture associated with a "network of corruption, collusion, and nepotism."[238][239] A New York Times report found that the Japanese nuclear regulatory system consistently sided with, and promoted, the nuclear industry based on the concept of amakudari ('descent from heaven'), in which senior regulators accepted high paying jobs at companies they once oversaw.[240]
In August 2011, several top energy officials were fired by the Japanese government; affected positions included the Vice-minister for Economy, Trade and Industry; the head of the Nuclear and Industrial Safety Agency, and the head of the Agency for Natural Resources and Energy.[241]
In 2016 three former TEPCO executives, chairman Tsunehisa Katsumata and two vice presidents, were indicted for negligence resulting in death and injury.[242][243] In June 2017 the first hearing took place, in which the three pleaded not guilty to professional negligence resulting in death and injury.[244] In September 2019 the court found all three men not guilty.[245]
NAIIC
The Fukushima Nuclear Accident Independent Investigation Commission (NAIIC) was the first independent investigation commission by the National Diet in the 66-year history of Japan's constitutional government.
The accident "cannot be regarded as a natural disaster," the NAIIC panel's chairman, Tokyo University professor emeritus Kiyoshi Kurokawa, wrote in the inquiry report. "It was a profoundly man-made accident – that could and should have been foreseen and prevented. And its effects could have been mitigated by a more effective human response."[246] "Governments, regulatory authorities and Tokyo Electric Power [TEPCO] lacked a sense of responsibility to protect people's lives and society," the Commission said. "They effectively betrayed the nation's right to be safe from nuclear accidents.[247] He stated that the accident was "made in Japan", since it was a manifestation of certain cultural traits, saying:
“Its fundamental causes are to be found in the ingrained conventions of Japanese culture: our reflexive obedience; our reluctance to question authority; our devotion to ‘sticking with the program’; our groupism; and our insularity.”[248]
The Commission recognized that the affected residents were still struggling and facing grave concerns, including the "health effects of radiation exposure, displacement, the dissolution of families, disruption of their lives and lifestyles and the contamination of vast areas of the environment".
Investigation committee
The purpose of the Investigation Committee on the Accident at the Fukushima Nuclear Power Stations (ICANPS) was to identify the accident's causes and propose policies designed to minimize the damage and prevent the recurrence of similar incidents.[249] The 10 member, government-appointed panel included scholars, journalists, lawyers, and engineers.[250][251] It was supported by public prosecutors and government experts[252] and released its final 448-page[253] investigation report on 23 July 2012.[254][255]
The panel's report faulted an inadequate legal system for nuclear crisis management, a crisis-command disarray caused by the government and TEPCO, and possible excess meddling on the part of the Prime Minister's office in the crisis' early stage.[256] The panel concluded that a culture of complacency about nuclear safety and poor crisis management led to the nuclear accident.[250]
See also
- Comparison of the Chernobyl and Fukushima nuclear accidents
- Environmental issues in Japan
- Fukushima disaster cleanup
- Fukushima Daiichi nuclear disaster casualties
- List of Japanese nuclear incidents
- List of civilian nuclear accidents
- Lists of nuclear disasters and radioactive incidents
- Nuclear power in Japan
- Nuclear power phase-out
- Martin Fackler (journalist)
References
- "High-resolution photos of Fukushima Daiichi" (Press release). Japan: Air Photo Service. 24 March 2011. Retrieved 14 January 2014.
- "Responses and Actions Taken by the Ministry of Health, Labour and Welfare of Japan on Radiation Protection at Works Relating to the Accident at TEPCO's Fukushima Daiichi Nuclear Power Plant 6th Edition (Fiscal Year of 2018)" (PDF). Ministry of Health, Labour and Welfare: 13. 31 January 2019. Archived from the original (PDF) on 20 January 2022.
- Robin.Harding (11 March 2018). "Fukushima nuclear disaster: did the evacuation raise the death toll?". Financial Times. Retrieved 2 February 2019.
- "Compensation claims from Fukushima plant work top 260 since 2011". The Japan Times. 31 October 2020. Retrieved 2 April 2021.
- Hasegawa, A.; Ohira, T.; Maeda, M.; Yasumura, S.; Tanigawa, K. (April 2016). "Emergency Responses and Health Consequences after the Fukushima Accident; Evacuation and Relocation". Clinical Oncology. 28 (4): 237–244. doi:10.1016/j.clon.2016.01.002. PMID 26876459.
- "Update on Japan Earthquake". IAEA. June 2011. Archived from the original on 14 March 2011. Retrieved 16 March 2011.
As reported earlier, a 400 millisieverts (mSv) per hour radiation dose observed at Fukushima Daiichi occurred between 1s 3 and 4. This is a high dose-level value, but it is a local value at a single location and at a certain point in time. The IAEA continues to confirm the evolution and value of this dose rate.
- McCurry, Justin (24 March 2011). "Japan nuclear plant workers in hospital after radiation exposure". The Guardian. Retrieved 16 December 2013.
- "Radiation-exposed workers to be treated at Chiba hospital". Kyodo News. 25 March 2011. Archived from the original on 17 February 2013. Retrieved 17 April 2011.
- The Fukushima Daiichi accident. STI/PUB. Vienna, Austria: International Atomic Energy Agency. 2015. ISBN 978-92-0-107015-9.
- Braun, Matthias (19 May 2011). "The Fukushima Daiichi Incident" (PDF). Areva. Archived from the original (PDF) on 26 February 2017 – via JS Miller design.
- "News Release" (PDF) (Press release). NISA. 12 April 2011. Archived from the original (PDF) on 1 May 2011. Retrieved 24 April 2011.
- "Fukushima Nuclear Accident Update Log". www.iaea.org. 12 April 2011. Retrieved 6 September 2023.
- Levels and effects of radiation exposure due to the accident at the Fukushima Daiichi Nuclear Power Station (PDF) (Report). United Nations Scientific Committee on the Effects of Atomic Radiation. 2021.
- Fujimori, Keiya; Nomura, Yasuhisa; Hata, Kenichi (2014). "Pregnant and Birth Survey after the Great East Japan Earthquake and Fukushima Daiichi Nuclear Power Plant Accident in the Fukushima Prefecture". Fukushima Journal of Medical Science. 60 (1): 106–107. doi:10.5387/fms.2014-12. ISSN 0016-2590.
- Waddington, I.; Thomas, P.J.; Taylor, R.H.; Vaughan, G.J. (November 2017). "J-value assessment of relocation measures following the nuclear power plant accidents at Chernobyl and Fukushima Daiichi". Process Safety and Environmental Protection. 112: 16–49. doi:10.1016/j.psep.2017.03.012.
- "Designating and rearranging the areas of evacuation" Japan Cabinet Office
- Government of Japan (2014). WG3 Question 2, Submission 6, Official Communication.
- Studying the Fukushima Aftermath: 'People Are Suffering from Radiophobia'. Spiegel (19 August 2011). Retrieved on 6 September 2013. Archived 16 January 2014 at the Wayback Machine
- Harada, Nahoko; Shigemura, Jun; Tanichi, Masaaki; Kawaida, Kyoko; Takahashi, Satomi; Yasukata, Fumiko (2 September 2015). "Mental health and psychological impacts from the 2011 Great East Japan Earthquake Disaster: a systematic literature review". Disaster Mil Med. 1 (17): 17. doi:10.1186/s40696-015-0008-x. ISSN 2054-314X. OCLC 1185993618. PMC 5330089. PMID 28265432.
- Hasegawa; et al. (2015). "From Hiroshima and Nagasaki to Fukushima 2. Health effects of radiation and other health problems in the aftermath of nuclear accidents, with an emphasis on Fukushima" (PDF). The Lancet. 386 (9992): 479–488. doi:10.1016/S0140-6736(15)61106-0. PMID 26251393. S2CID 19289052.
- "Protests continue against Japan's dumping of radioactive water | Green Left". www.greenleft.org.au. 5 September 2023. Retrieved 5 September 2023.
- "Japanese Earthquake Update (19 March 2011, 4:30 UTC) : IAEA Alert Log: Fukushima Daiichi Nuclear Accident". 7 June 2011. Archived from the original on 7 June 2011.
- B. Cox, Journal of Nuclear Materials, Pellet Clad Interaction (PCI) Failures of Zirconium Alloy Fuel Cladding – A Review, 1990, volume 172, pp. 249–92/
- Belle, Jack (1962). "Uranium dioxide:properties and nuclear applications". Nuclear Science and Engineering. 14 (3): 319. Bibcode:1962NSE....14..319E. doi:10.13182/NSE62-A26226.
- Hofmann, P. Chemical Interaction Between Uranium Oxide and Zircaloy-4 in the Temperature Range Between 900 and 1500°C.
- St. John Foreman, Mark Russell (2015). "An introduction to serious nuclear accident chemistry". Cogent Chemistry. 1. doi:10.1080/23312009.2015.1049111. S2CID 44589893.
- Omoto, Akira (December 2013). "The accident at TEPCO's Fukushima-Daiichi Nuclear Power Station: What went wrong and what lessons are universal?". Nuclear Instruments and Methods in Physics Research Section A: Accelerators, Spectrometers, Detectors and Associated Equipment. 731: 3–7. doi:10.1016/j.nima.2013.04.017.
- "Regulatory effectiveness of the station blackout rule" (PDF). Retrieved 7 April 2011.
- "The 2011 off the Pacific coast of Tohoku Pacific Earthquake and the seismic damage to the NPPs" (PDF). Archived from the original (PDF) on 22 May 2011. Retrieved 13 July 2011.
- Shirouzu, Norihiko (1 July 2011). "The Wall Street Journal: Design Flaw Fueled Nuclear Disaster". Online.wsj.com. Archived from the original on 4 July 2011. Retrieved 13 July 2011.
- Martin, Alex, "Lowdown on nuclear crisis and potential scenarios", Japan Times, 20 March 2011, p. 3.
- "Fukushima: Background on Fuel Ponds". Archived from the original (PDF) on 16 October 2013. Retrieved 23 November 2013.
- Yoshida, Reiji (20 March 2013). "No. 1 fuel pool power to be restored: Tepco". The Japan Times Online. Archived from the original on 7 January 2014. Retrieved 20 March 2013.
- "The 2011 off the Pacific coast of Tohoku Pacific Earthquake and the seismic damage to the NPPs" (PDF). NISA. p. 35. Archived from the original (PDF) on 1 May 2011. Retrieved 24 April 2011.
- "Fukushima to Restart Using MOX Fuel for First Time". Nuclear Street. 17 September 2010. Archived from the original on 29 April 2014. Retrieved 12 March 2011.
- Brady, A. Gerald (1980). Ellingwood, Bruce (ed.). An Investigation of the Miyagi-ken-oki, Japan, earthquake of June 12, 1978. NBS special publication. Vol. 592. United States Department of Commerce, National Bureau of Standards. p. 123.
- "Magnitude 9.0 – near the East coast of Honshu, Japan". Earthquake.usgs.gov. Archived from the original on 13 March 2011. Retrieved 17 March 2011.
- "Fukushima faced 14-metre tsunami". World Nuclear News. 24 March 2011. Archived from the original on 16 June 2011. Retrieved 24 March 2011.
- Lipscy, Phillip; Kushida, Kenji; Incerti, Trevor (2013). "The Fukushima Disaster and Japan's Nuclear Plant Vulnerability in Comparative Perspective" (PDF). Environmental Science & Technology. 47 (12): 6082–6088. Bibcode:2013EnST...47.6082L. doi:10.1021/es4004813. PMID 23679069. Archived from the original (PDF) on 22 November 2019.
- "Occurrence of a Specific Incident Stipulated in Article 15, Clause 1 of the Act on Special Measures Concerning Nuclear Emergency Preparedness". Tepco (Press release). 11 March 2011. Archived from the original on 19 March 2011.
- "Occurrence of a specific incident stipulated in Article 10, Clause 1 of the Act on "Special measures concerning nuclear emergency preparedness (Fukushima Daiichi)"". TEPCO (Press release). 11 March 2011. Archived from the original on 15 April 2011. Retrieved 13 March 2011.
- "TEPCO : Press Release | Employees of TEPCO Who Were Missing at Fukushima Daiichi Nuclear Power Station". www.tepco.co.jp. Retrieved 10 September 2023.
- "Japan Earthquake Update (2210 CET)" (Press release). International Atomic Energy Agency. 11 March 2011. Archived from the original on 14 March 2011. Retrieved 12 March 2011.
- "OECD Timeline for the Fukushima Daiichi nuclear power plant accident". Archived from the original on 29 October 2013.
- "Fukushima nuclear accident update log, updates". IAEA. 15 March 2011. Archived from the original on 24 March 2011. Retrieved 8 May 2011.
- The Evaluation Status of Reactor Core Damage at Fukushima Daiichi Nuclear Power Station Units 1 to 3 30 November 2011 Tokyo Electric Power Company
- Uncertainties abound in Fukushima decommissioning. Phys.org. 19 November 2013. Archived 14 March 2014 at the Wayback Machine
- Most of fuel NOT remaining in reactor1 core / Tepco "but molten fuel is stopped in the concrete base" Fukushima-Diary.com Archived 25 March 2014 at the Wayback Machine
- "TEPCO to start "scanning" inside of Reactor 1 in early February by using muon". Fukushima Diary. January 2015.
- "Muon Scans Begin At Fukushima Daiichi". SimplyInfo. Archived from the original on 7 February 2015. Retrieved 7 February 2015.
- "Muon Scan Finds No Fuel In Fukushima Unit 1 Reactor Vessel". SimplyInfo. Archived from the original on 21 March 2015. Retrieved 19 March 2015.
- "IRID saw no fuel or water remaining in reactor core of Reactor 1". Fukushima Diary. 19 March 2015.
- "High radiation readings at Fukushima's No. 2 reactor complicate robot-based probe". The Japan Times. 10 February 2017. Archived from the original on 15 February 2017. Retrieved 11 February 2017.
- 東電 2号機 格納容器の放射線量を大幅訂正 (in Japanese). NHK. 28 July 2017. Archived from the original on 27 July 2017. Retrieved 28 July 2017.
- Justin McCurry (3 February 2017). "Fukushima nuclear reactor radiation at highest level since 2011 meltdown". The Guardian. Archived from the original on 11 March 2017. Retrieved 3 February 2017.
- fukushima-is-still-news. "TEPCO footage shows fuel debris in No. 2 reactor". Archived from the original on 18 May 2018. Retrieved 17 May 2018.
- "Highest radiation reading since 3/11 detected at Fukushima No. 1 reactor". The Japan Times. 3 February 2017.
- Beser, Ari (22 February 2017). "After Alarmingly High Radiation Levels Detected, What Are the Facts in Fukushima?". National Geographic Society. Retrieved 9 April 2017.
- Su, S. (August 2006). TAD Source Term and Dose Rate Evaluation (PDF). Bechtel Saic. 000-30R-GGDE-00100-000-00A. Retrieved 20 May 2012.
- "Tepco surveys interior of unit 2 containment vessel". World Nuclear News. 19 January 2018. Retrieved 20 January 2018.
- Kawahara, Chikako (20 January 2018). "Melted nuclear fuel seen inside No. 2 reactor at Fukushima plant". The Asahi Shimbun. Archived from the original on 20 January 2018. Retrieved 20 January 2018.
- "TEPCO Admits Unit 3 Had Total Melt Through". SimplyInfo. 6 August 2014. Archived from the original on 18 August 2015. Retrieved 12 June 2015.
- "Fukushima Unit 3 Reactor Vessel Failure Preceded Explosion". SimplyInfo. 7 August 2014. Archived from the original on 18 August 2015. Retrieved 12 June 2015.
- "Report on the Investigation and Study of Unconfirmed/Unclear Matters in the Fukushima Nuclear Accident – Progress Report No. 2 – 6 August 2014 Tokyo Electric Power Company, Inc" (PDF).
- "Reactor 3 fuel is assumed to have melted concrete base up to 26cm to the wall of primary vessel". Fukushima Diary. 8 August 2014. Retrieved 12 June 2015.
- "Analysis of the TEPCO Fukushima Daiichi NPS Accident" (PDF). Nuclear Regulation Authority, Japan. October 2014. Retrieved 24 April 2020.
- "Seismic Damage Information (the 61st Release)" (PDF). Nuclear and Industrial Safety Agency. 29 March 2011. Archived from the original (PDF) on 1 May 2011. Retrieved 12 April 2011.
- "Report of Japanese Government to the IAEA Ministerial Conference on Nuclear Safety: The Accident at TEPCO's Fukushima Nuclear Power Stations" (PDF). Nuclear Emergency Response Headquarters. Government of Japan. 2011.
- "The official report of the Fukushima Nuclear Accident Independent Investigation Commission". National Diet of Japan. 2012.
- Japan Nuclear Energy Safety Organiation (2013), Initial Operations in the Local Nuclear Emergency Response Headquarters.
- "Interim Report". Investigation Committee on the Accident at the Fukushima Nuclear Power Stations of Tokyo Electric Power Company. 2011.
- Investigation Committee on the Accident at the Fukushima Nuclear Power Stations of Tokyo Electric Power Company (2012). Final Report.
- Tanigawa, Koichi; Hosoi, Yoshio; Hirohashi, Nobuyuki; Iwasaki, Yasumasa; Kamiya, Kenji (March 2012). "Loss of life after evacuation: lessons learned from the Fukushima accident". The Lancet. 379 (9819): 889–891. doi:10.1016/s0140-6736(12)60384-5. ISSN 0140-6736.
- Saegusa, Jun; Kikuta, Yasuaki; Akino, Hitoshi (July 2013). "Observation of gamma-rays from fallout collected at Ibaraki, Japan, during the Fukushima nuclear accident". Applied Radiation and Isotopes. 77: 56–60. doi:10.1016/j.apradiso.2013.02.018. ISSN 0969-8043.
- Stohl, A.; Seibert, P.; Wotawa, G.; Arnold, D.; Burkhart, J. F.; Eckhardt, S.; Tapia, C.; Vargas, A.; Yasunari, T. J. (1 March 2012). "Xenon-133 and caesium-137 releases into the atmosphere from the Fukushima Dai-ichi nuclear power plant: determination of the source term, atmospheric dispersion, and deposition". Atmospheric Chemistry and Physics. 12 (5): 2313–2343. doi:10.5194/acp-12-2313-2012. ISSN 1680-7324.
- KAWAMURA, Hideyuki; KOBAYASHI, Takuya; FURUNO, Akiko; IN, Teiji; ISHIKAWA, Yoichi; NAKAYAMA, Tomoharu; SHIMA, Shigeki; AWAJI, Toshiyuki (November 2011). "Preliminary Numerical Experiments on Oceanic Dispersion of131I and137Cs Discharged into the Ocean because of the Fukushima Daiichi Nuclear Power Plant Disaster". Journal of Nuclear Science and Technology. 48 (11): 1349–1356. doi:10.1080/18811248.2011.9711826. ISSN 0022-3131.
- IRSN (26 October 2011). "Synthèse actualisée des connaissances relatives à l'impact sur le milieu marin des rejets radioactifs du site nucléaire accidenté de Fukushima Dai-ichi" (PDF). Retrieved 3 January 2012.
- "Homes should not be abandoned after a big nuclear accident, study suggests". ScienceDaily.
- "Evacuees of Fukushima village report split families, growing frustration" (PDF). Mainichi Daily News. 30 January 2012. Archived from the original (PDF) on 22 September 2013.
- Katherine Harmon (2 March 2012). "Japan's Post-Fukushima Earthquake Health Woes Go Beyond Radiation Effects". Nature. Archived from the original on 13 October 2013.
- "UNSCEAR Report Volume 1: Levels and effects of radiation exposure due to the nuclear accident after the 2011 great east-Japan earthquake and tsunami" (PDF). October 2014. Retrieved 12 July 2022.
- Vetter, Kai (2020). "The Nuclear Legacy Today of Fukushima". Annual Review of Nuclear and Particle Science. 70: 257–292. Bibcode:2020ARNPS..70..257V. doi:10.1146/annurev-nucl-101918-023715.
- jlavarnway (22 June 2021). "Ten Years of Fukushima Disinformation | Skeptical Inquirer". Retrieved 6 July 2021.
- International Energy Agency (2016). Energy Balances of OECD Countries 2016.
- Agency for Natural Resources and Energy (2010). 3rd Strategic Energy Plan. Ministry of Economy, Trade, and Industry.
- Organization for Economic Cooperation and Development (2015). Economic Surveys: Japan 2015.
- Agency for Natural Resources and Energy (2014). 4th Strategic Energy Plan. Ministry of Economy, Trade, and Industry.
- International Energy Agency (2016). Energy Policies of IEA Countries: Japan 2016 Review.
- "Neon city goes dim as power shortage threatens traffic lights and telephones in Tokyo". news.com.au. 15 March 2011. Archived from the original on 17 March 2011.
- Yuri Kageyama, dealing with power shortage. Associated Press, 22 May 2011
- "Japan's Fuel Costs May Rise to 7.5 Trillion Yen, Meti Estimates". Archived from the original on 9 October 2013.
- "Abe dismisses Koizumi's call for zero nuclear power plants". The Asahi Shimbun. 25 October 2013. Archived from the original on 13 April 2014. Retrieved 30 December 2013.
- "Supporters of zero nuclear power "irresponsible": Abe". Archived from the original on 29 October 2013.
- "Most Japan cities hosting nuclear plants OK restart: survey". Bangkok Post. Archived from the original on 15 February 2013. Retrieved 30 December 2013.
- United Press International (2 June 2013). "60,000 protest Japan's plan to restart nuclear power plants". UPI Asia. Archived from the original on 29 October 2013.
- Hiroko Tabuchi (13 July 2011). "Japan Premier Wants Shift Away From Nuclear Power". The New York Times.
- Poch, Rafael (31 May 2011). "Merkel se despide de lo nuclear y anuncia una revolución en renovables" (in Spanish). lavanguardia.com. Retrieved 26 January 2014.
- Suman, Siddharth (April 2018). "Hybrid nuclear-renewable energy systems: A review". Journal of Cleaner Production. 181: 166–177. doi:10.1016/j.jclepro.2018.01.262.
- "Italy nuclear: Berlusconi accepts referendum blow". BBC News. 14 June 2011. Archived from the original on 12 June 2011. Retrieved 26 January 2014.
- Broomby, Rob (11 January 2014). "France struggles to cut down on nuclear power". BBC News. Retrieved 12 June 2015.
- Rob Broomby (11 January 2014). "France struggles to cut down on nuclear power". BBC News Magazine. Archived from the original on 7 February 2014. Retrieved 26 January 2014.
- "Nuclear Power in China". World Nuclear Association. Archived from the original on 2 February 2016. Retrieved 12 June 2015.
- "Insights" (PDF). KPMG. 20 September 2018.
- Tiezzi, Shannon. "Why China Will Go All-In on Nuclear Power". The Diplomat. Retrieved 12 June 2015.
- "Plans For New Reactors Worldwide". World Nuclear Association. Retrieved 23 January 2019.
- "Nuclear Power in South Korea". World nuclear Association. Archived from the original on 29 September 2015. Retrieved 12 June 2015.
- "Nuclear energy only option before country: Ansari". The Indian Express. 20 October 2012. Retrieved 12 June 2015.
- "Modi: India to build 10 more nuclear reactors with Russia". International Business Times. 12 December 2014.
- "S. Rept. 112-75 – Energy and Water Development Appropriations Bill, 2012". Library of Congress.
- "Accident Tolerant Fuel". NEI.
- "NRC: Accident Tolerant Fuel". United States Nuclear Regulatory Commission. Retrieved 2 December 2019.
- Menser, Paul (15 May 2018). "Accident Tolerant Fuels Effort Hits Important Milestone". Idaho National Laboratory. Retrieved 2 December 2019.
- "Fukushima Accident". World Nuclear Association. Retrieved 9 September 2018.
- Goldberg, Jeanne (September–October 2018). "From the Spectral to the Spectrum". Skeptical Inquirer. 42 (5).
- Brumfiel, Geoffrey (23 May 2012). "World Health Organization weighs in on Fukushima". Nature. Archived from the original on 6 October 2013. Retrieved 20 March 2013.
- Brumfiel, Geoff (January 2013). "Fukushima: Fallout of fear". Nature. 493 (7432): 290–293. Bibcode:2013Natur.493..290B. doi:10.1038/493290a. PMID 23325191. S2CID 4419435.
- Brumfiel, Geoff (May 2012). "Fukishima". Nature. 485 (7399): 423–424. Bibcode:2012Natur.485..423B. doi:10.1038/485423a. PMID 22622542. S2CID 205071768.
- Nebehay, Stephanie (28 February 2013). "Higher cancer risk after Fukushima nuclear disaster: WHO". Reuters. Archived from the original on 15 October 2013.
- Rojavin, Y; Seamon, MJ; Tripathi, RS; Papadimos, TJ; Galwankar, S; Kman, N; Cipolla, J; Grossman, MD; Marchigiani, R; Stawicki, SP (April 2011). "Civilian nuclear incidents: An overview of historical, medical, and scientific aspects". J Emerg Trauma Shock. 4 (2): 260–272. doi:10.4103/0974-2700.82219. PMC 3132367. PMID 21769214.
- WHO 2013, p. 92.
- "Global report on Fukushima nuclear accident details health risks". Archived from the original on 12 April 2014. Retrieved 28 April 2014.
- "Increase in Cancer Unlikely following Fukushima Exposure – says UN Report" (Press release). Vienna: United Nations Information Service.
- "UNSCEAR 2013 Report Volume I". United Nations: Scientific Committee on the Effects of Atomic Radiation.
- WHO 2013, p. 42.
- "British Columbia | Home". Fukushimainform.ca. Retrieved 2 November 2015.
- "Canadian researcher targeted by hate campaign over Fukushima findings". The Globe and Mail. Retrieved 2 November 2015.
- Welch, H. Gilbert; Woloshin, Steve; Schwartz, Lisa A. (2011). Overdiagnosed: Making People Sick in the Pursuit of Health. Beacon Press. pp. 61–34. ISBN 978-0-8070-2200-9.
- "Screening effect? Examining thyroid cancers found in Fukushima children". Fukushima Inform. 6 March 2016.
- Yamamoto, Hidehiko; Hayashi, Keiji; Scherb, Hagen (September 2019). "Association between the detection rate of thyroid cancer and the external radiation dose-rate after the nuclear power plant accidents in Fukushima, Japan". Medicine. 98 (37): e17165. doi:10.1097/MD.0000000000017165. PMC 6750239. PMID 31517868.
- WHO 2013, pp. 87–88.
- Ohira, Tetsuya; Takahashi, Hideto; Yasumura, Seiji; Ohtsuru, Akira; Midorikawa, Sanae; Suzuki, Satoru; Fukushima, Toshihiko; Shimura, Hiroki; Ishikawa, Tetsuo; Sakai, Akira; Yamashita, Shunichi; Tanigawa, Koichi; Ohto, Hitoshi; Abe, Masafumi; Suzuki, Shinichi; Fukushima Health Management Survey, Group. (August 2016). "Comparison of childhood thyroid cancer prevalence among 3 areas based on external radiation dose after the Fukushima Daiichi nuclear power plant accident: The Fukushima health management survey". Medicine. 95 (35): e4472. doi:10.1097/MD.0000000000004472. PMC 5008539. PMID 27583855.
- Yamashita, Shunichi; Suzuki, Shinichi; Suzuki, Satoru; Shimura, Hiroki; Saenko, Vladimir (January 2018). "Lessons from Fukushima: Latest Findings of Thyroid Cancer After the Fukushima Nuclear Power Plant Accident". Thyroid. 28 (1): 11–22. doi:10.1089/thy.2017.0283. PMC 5770131. PMID 28954584.
- Toki, H.; Wada, T.; Manabe, Y.; Hirota, S.; Higuchi, T.; Tanihata, I.; Satoh, K.; Bando, M. (December 2020). "Relationship between environmental radiation and radioactivity and childhood thyroid cancer found in Fukushima health management survey". Scientific Reports. 10 (1): 4074. Bibcode:2020NatSR..10.4074T. doi:10.1038/s41598-020-60999-z. PMC 7058088. PMID 32139763.
- cancer.org Thyroid Cancer By the American Cancer Society. In turn citing: AJCC Cancer Staging Manual (7th ed). Archived 18 October 2013 at the Wayback Machine
- Yamaguchi, Mari (26 January 2022). "6 cancer patients sue utility over Fukushima radiation". AP News.
- Yamaguchi, Mari (27 January 2022). "6 thyroid cancer patients sue TEPCO over Fukushima radiation". Japan Today. Associated Press.
- Walsh, Bryan. (1 March 2013) WHO Report Says That Fukushima Nuclear Accident Posed Minimal Risk to Health |Time.com. Science.time.com. Retrieved on 6 September 2013. Archived 4 November 2013 at the Wayback Machine
- WHO 2013, pp. 70, 79–80.
- Normile, Dennis (27 July 2012). "Is Nuclear Power Good for You?". Science. 337 (6093): 395–396. doi:10.1126/science.337.6093.395-b. Archived from the original on 1 March 2013.
- John E. Ten Hoeve; Mark Z. Jacobson (2012). "Worldwide health effects of the Fukushima Daiichi nuclear accident" (PDF). Energy & Environmental Science. 5 (9): 8743. CiteSeerX 10.1.1.360.7269. doi:10.1039/c2ee22019a. Retrieved 18 July 2012.
- Evangeliou, Nikolaos; Balkanski, Yves; Cozic, Anne; Pape Møller, Anders (2014). "Predictions on the contamination levels from various fission products released from the accident and updates on the risk assessment for solid and thyroid cancers". Science of the Total Environment. 500–501: 155–172. doi:10.1016/j.scitotenv.2014.08.102. PMID 25217754.
- Normile, D. (2011). "Fukushima Revives the Low-Dose Debate". Science. 332 (6032): 908–910. Bibcode:2011Sci...332..908N. doi:10.1126/science.332.6032.908. PMID 21596968.
- Aurengo, A.; et al. (2005). "Dose effect relationship and estimation of the carcinogenic effects of low doses of ionising radiation: The Joint Report of the Académie des Sciences (Paris) and of the Académie Nationale de Médecine". International Journal of Low Radiation. 2 (3/4): 135. doi:10.1504/IJLR.2006.009510. S2CID 26583588.
- Luckey, T.J. (27 September 2006). "Radiation Hormesis: The Good, the Bad, and the Ugly". Dose-Response. 4 (3): 189–190. doi:10.2203/dose-response.06-102.Luckey. PMC 2477686. PMID 18648595.
- "Japan acknowledges first radiation death from nuclear plant hit by tsunami". ABC News. 6 September 2018. Retrieved 30 April 2019.
- Hamada, Nobuyuki (2012). "Safety regulations of food and water implemented in the first year following the Fukushima nuclear accident". Journal of Radiation Research. 53 (5): 641–671. Bibcode:2012JRadR..53..641H. doi:10.1093/jrr/rrs032. PMC 3430419. PMID 22843368.
- Buesseler, Ken O.; Jayne, Steven R.; Fisher, Nicholas S.; Rypina, Irina I.; Baumann, Hannes; Baumann, Zofia; Breier, Crystaline F.; Douglass, Elizabeth M.; George, Jennifer; MacDonald, Alison M.; Miyamoto, Hiroomi; Nishikawa, Jun; Pike, Steven M.; Yoshida, Sashiko (2012). "Fukushima-derived radionuclides in the ocean and biota off Japan". Proceedings of the National Academy of Sciences. 109 (16): 5984–5988. Bibcode:2012PNAS..109.5984B. doi:10.1073/pnas.1120794109. PMC 3341070. PMID 22474387.
- Aoki, Mizuho, "Tohoku fears nuke crisis evacuees gone for good", Japan Times, 8 March 2012, p. 1. Archived 7 March 2012 at the Wayback Machine
- Daniel J. Madigan; Zofia Baumann; Nicholas S. Fisher (29 May 2012). "Pacific bluefin tuna transport Fukushima-derived radionuclides from Japan to California". Proceedings of the National Academy of Sciences of the United States of America. 109 (24): 9483–9486. Bibcode:2012PNAS..109.9483M. doi:10.1073/pnas.1204859109. PMC 3386103. PMID 22645346.
- "Radioactive Tuna Fish From Fukushima Reactor Spotted Off U.S. Shores". Fox Weekly. 30 April 2014. Archived from the original on 2 May 2014.
- Sebens, Shelby (29 April 2014). "Study finds Fukushima radioactivity in tuna off Oregon, Washington". Yahoo. Archived from the original on 3 May 2014.
- Teishima, Hirohiko; et al. (2017). "Concentration of radiocesium in Japanese whiting Sillago japonica living in Tokyo Bay after the Fukushima Daiichi Nuclear Power Station accident". Journal of Advanced Marine Science and Technology Society (in Japanese and English). 23 (1): 1–9. doi:10.14928/amstec.23.1_1.
- Tilman Ruff. Fukushima: The Misery Piles up, Pursuit magazine, University of Melbourne, 2016.
- Hiyama; et al. (2012). "The biological impacts of the Fukushima nuclear accident on the pale grass blue butterfly". Scientific Reports. 2: 570. Bibcode:2012NatSR...2E.570H. doi:10.1038/srep00570. PMC 3414864. PMID 22880161.
- Sutou; et al. (2015). "Commentary 2: abnormalities of butterflies captured around Fukushima areas might not be caused by non-genetic but toxic effects". Fukushima Nuclear Accident: Global Implications, Long-Term Health Effects and Ecological Consequences. New York: Nova Sciences Publishers Inc. pp. 225–230.
- "Thailand receives Fukushima's first fish export since 2011 nuclear disaster". The Straits Times. 6 March 2018. Retrieved 14 March 2018.
- "Activists oppose imports of fish from Fukushima". Bangkok Post. Retrieved 14 March 2018.
- Blair, Gavin (24 July 2023). "Fukushima fish with 180 times legal limit of radioactive cesium fuels water release fears". The Guardian. ISSN 0261-3077. Retrieved 5 September 2023.
- Hasegawa, Koichi (2012). "Facing Nuclear Risks: Lessons from the Fukushima Nuclear Disaster". International Journal of Japanese Sociology. 21 (1): 84–91. doi:10.1111/j.1475-6781.2012.01164.x.
- "Fukushima disaster area Tour – Feel the reality of the disaster in a life-changing tour". Fukushima.tohoku-tour.com. Archived from the original on 16 April 2019. Retrieved 31 May 2018.
- "Museum about 2011 quake and nuclear disaster opens in Fukushima". The Japan Times. 20 September 2020. Retrieved 22 September 2020.
- "Status of Fuel Removal from Spent Fuel Pools". TEPCO. Archived from the original on 11 August 2022. Retrieved 12 February 2023.
- 廃炉に向けたロードマップ (in Japanese). TEPCO. Archived from the original on 22 July 2022. Retrieved 12 February 2023.
- Justin Mccurry (10 March 2014). "Fukushima operator may have to dump contaminated water into Pacific". The Guardian. Archived from the original on 18 March 2014. Retrieved 10 March 2014.
- "Japan seeks outside help for contaminated water". World Nuclear News. 26 September 2013. Retrieved 18 September 2019.
- Martin, James (5 March 2019). "Fukushima's ice wall keeps radiation from spreading around the world". CNET.
- "Land-side Impermeable Wall (Frozen soil wall) | TEPCO". www7.tepco.co.jp. Archived from the original on 4 September 2019. Retrieved 20 September 2019.
- "Fukushima decommissioning moves forward". World Nuclear News. 17 September 2019. Retrieved 18 September 2019.
- "井戸から基準16万倍の放射性物質…公表せず" [Last year the radioactivity of a well is 160,000 times than discharge requirement, TEPC now discovered]. Yomiuri Shimbun. 7 February 2014. Archived from the original on 9 February 2014.
- "TEPCO to review erroneous radiation data". NHK World. NHK. 9 February 2014. Archived from the original on 9 February 2014. Retrieved 9 February 2014.
Tokyo Electric Power Company, or TEPCO, says it has detected a record high 5 million becquerels (0.13 millicuries) per liter of radioactive strontium in groundwater collected last July from one of the wells close to the ocean. ... Based on the result, levels of radioactive substances that emit beta particles are estimated to be 10 million becquerels (0.26 millicuries) per liter, which is more than 10 times the initial reading.
- Fernquest, John. "Japan floods: After typhoon, rivers overflow, nuclear water". Retrieved 10 September 2015.
- "Flooding swept away radiation cleanup bags in Fukushima". The Japan Times Online. 12 September 2015. Archived from the original on 17 September 2015. Retrieved 13 September 2015.
- "The subcommittee on handling of the ALPS treated water report" (PDF). Ministry of Economy, Trade and Industry. 10 February 2020. pp. 12, 16, 17, 33, 34. Retrieved 10 April 2020.
- "IAEA follow-up review of progress made on management of ALPS treated water and the report of the subcommittee on handling of ALPS treated water at TEPCO's Fukushima Daiichi nuclear power station" (PDF). International Atomic Energy Agency. 2 April 2020. p. 8. Retrieved 10 April 2020.
- "Regulator approves Fukushima water release". World Nuclear News. 22 July 2022. Retrieved 15 August 2022.
- Kuhn, Anthony (13 April 2021). "Japan To Dump Wastewater From Wrecked Fukushima Nuclear Plant Into Pacific Ocean". Retrieved 17 April 2023.
- Cabico, Gaea Katreena (13 April 2023). "Filipino fishers, anti-nuke activists oppose release of Fukushima water to ocean". Philippine Star. Retrieved 17 April 2023.
- "Japan to release radioactive water into sea despite warnings". The Independent. 22 August 2023. Retrieved 22 August 2023.
- Inagaki, Kana; Ho-him, Chan (22 August 2023). "Japan's release of radioactive water from Fukushima angers China". Financial Times. Retrieved 22 August 2023.
- "Fukushima Nuclear Disaster: Japan to release treated water in 48 hours". BBC News. 22 August 2023. Retrieved 22 August 2023.
- "Fukushima: China retaliates as Japan releases treated nuclear water". BBC News. 24 August 2023. Retrieved 24 August 2023.
- "Seafood/Fukushima: waste water release threatens export trade". Financial Times. 23 August 2023. Retrieved 24 August 2023.
- Staff. (2 January 2022). "TEPCO slow to respond to growing crisis at Fukushima plant". The Asahi Simbun website Retrieved 13 January 2022.
- Robin Harding (6 March 2016). "Japan taxpayers foot $100bn bill for Fukushima disaster". Financial Times. Retrieved 20 March 2016.
- Justin McCurry (30 January 2017). "Possible nuclear fuel find raises hopes of Fukushima plant breakthrough". The Guardian. Retrieved 3 February 2017.
- Yamamoto, Takaoki (7 November 2022). "12.1 trillion yen spent so far on Fukushima nuclear disaster". The Asahi Shimbun. Retrieved 2 December 2022.
- "Update: Fukushima operator's mounting legal woes to fuel nuclear opposition". Reuters. 17 August 2015. Retrieved 2 February 2016.
- McCurry, Justin (17 March 2017). "Japanese government liable for negligence in Fukushima disaster". The Guardian. London, United Kingdom. ISSN 0261-3077. Retrieved 17 March 2017.
- Yamaguchi, Mari (30 September 2020). "Japan court orders gov't, TEPCO to pay in Fukushima disaster". ABC News. Retrieved 1 October 2020.
- "Japan's top court orders damages for Fukushima victims in landmark decision -NHK". Reuters. 4 March 2022.
- "Japan's top court says government not responsible for Fukushima damage". Reuters. 17 June 2022. Retrieved 17 June 2022.
- "Tokyo court orders ex-Tepco execs to pay $95 bln damages over Fukushima disaster". Reuters. Reuters. 13 July 2022. Retrieved 13 July 2022.
- Maeda, Risa (20 October 2011). "Japanese nuclear plant survived tsunami, offers clues". Reuters. Archived from the original on 25 October 2011. Retrieved 27 October 2013.
- "IAEA Expert Team Concludes Mission to Onagawa NPP". www.iaea.org. 10 August 2012. Archived from the original on 29 October 2013.
- "Japanese nuclear plant 'remarkably undamaged' in earthquake". UN Atomic Agency News. 10 August 2012. Archived from the original on 29 October 2013.
- "Hydrogen fix for Japanese reactors". www.world-nuclear-news.org. Archived from the original on 14 February 2014.
- Jog, Sanjay (7 April 2011). "Hydrogen recombiners at all 20 NPC plants to avoid Fukushima". Business Standard. Archived from the original on 29 October 2013.
- "CFD analysis of passive autocatalytic recombiner interaction with atmosphere. Archive Kerntechnik – Issue 2011/02". Archived from the original on 29 October 2013.
- Strickland, Eliza (31 October 2011). "24 Hours at Fukushima". IEEE Spectrum. Archived from the original on 14 November 2013.
- Daly, Matthew (10 March 2013). "Nuclear chief: U.S. plants safer after Japan crisis. March 10, 2013". USA Today.
- "Vents and Filtering Strategies Come to Forefront in Fukushima Response Nuclear Energy Insight. Fall 2012".
- "TEPCO implements new safety measures in bid to restart Niigata reactors". Archived from the original on 13 April 2014.
- "Kashiwazaki-Kariwa plant shown to reporters". Archived from the original on 29 October 2013.
- "Nuclear power plant operator in China orders backup batteries for installation at plants". www.power-eng.com. 7 September 2012. Archived from the original on 29 October 2013.
- "China's Guangdong Nuclear Power Corp Announces Orders for BYD Battery Back-up for Nuclear Plants". www.businesswire.com. 6 September 2012. Archived from the original on 29 October 2013.
- Epstein, Woody (7 May 2012). "Not losing to the rain". Woody.com. Quantitative Risk Assessment. Archived from the original on 14 October 2013. Retrieved 26 February 2016.
The Notstand building, a bunkered facility which could support all of the plant systems for at least 72 hours given a severe flood or earthquake which could take out the normal power and cooling facilities. I asked Martin Richner, the head of risk assessment, why Beznau spent so much money on the Notstand building when there was no regulation or government directive to do so. Martin answered me, "Woody, we live here."
- "Special Panel Discussion I: Fukushima Accident, Issues and Lessons". Archived from the original on 22 September 2020. Retrieved 15 September 2023.
- Naitoh, Masanori; Suzuki, Hiroaki; Okada, Hidetoshi (2012). "Function of Isolation Condenser of Fukushima Unit-1 Nuclear Power Plant". 2012 20th International Conference on Nuclear Engineering and the ASME 2012 Power Conference. p. 819. doi:10.1115/ICONE20-POWER2012-55239. ISBN 978-0-7918-4499-1.
- "Gen III reactor design 04/06/2011 By Brian Wheeler Associate Editor". 6 April 2011. Archived from the original on 14 December 2013.
- "Nuclear Science and Techniques 24 (2013) 040601 Study on the long-term passive cooling extension of AP1000 reactor". Archived from the original on 14 December 2013.
- "Disaster response robots". Open Minds. Swiss re. Archived from the original on 22 February 2014.
- Seiji Iwata; Ryuichi Kanari (26 May 2011). "Japanese robots long gone before Fukushima accident". The Asahi Shimbun. Archived from the original on 3 September 2014. Retrieved 27 August 2014.
- "DARPA Robotics Challenge". DRC. DARPA. Archived from the original on 28 April 2016. Retrieved 27 April 2016.
- Gross, Rachel (10 March 2016). "Decontamination Bots Are Dying on Our Behalf in Fukushima". Slate.com.
- Fackler, Martin (21 June 2011). "Japan Plans to Unlink Nuclear Agency From Government". The New York Times. Retrieved 18 August 2019.
- Fackler, Martin (12 October 2012). "Japan Power Company Admits Failings on Plant Precautions". The New York Times. Archived from the original on 6 October 2014. Retrieved 13 October 2012.
- Sheldrick, Aaron (12 October 2012). "Fukushima operator must learn from mistakes, new adviser says". Reuters. Archived from the original on 9 March 2014. Retrieved 13 October 2012.
- Yamaguchi, Mari (12 October 2012). "Japan utility agrees nuclear crisis was avoidable". Boston. Associated Press. Archived from the original on 5 October 2013. Retrieved 13 October 2012.
- NHK-world (29 December 2011) Fukushima plant's backup generator failed in 1991.
JAIF (30 December 2011) Earthquake report 304:Fukushima plant's backup generator failed in 1991 Archived 3 January 2012 at the Wayback Machine.
The Mainichi Daily News (30 December 2011) TEPCO neglected anti-flood measures at Fukushima plant despite knowing risk. - "Fukushima Nuclear Accident – U.S. NRC warned a risk on emergency power 20 years ago". Bloomberg L.P. 16 March 2011. Archived from the original on 16 February 2014. Retrieved 14 September 2013.
- Clarke, Richard A.; Eddy, R.P. (2017). Warnings: Finding Cassandras to stop catastrophe. Harper Collins. p. 84.
- "Putting tsunami countermeasures on hold at Fukushima nuke plant". The Mainichi Shimbun. 20 October 2018.
- Fackler, Martin (9 March 2012). "Nuclear Disaster in Japan Was Avoidable, Critics Contend". The New York Times. Retrieved 24 September 2018.
- "AFERC urged to review assumption on Tsunami in 2009". Yomiuri News Paper. 11 March 2011. Archived from the original on 16 February 2014. Retrieved 14 September 2013.
- "Fukushima Pref. deleted 5 days of radiation dispersion data just after meltdowns". The Mainichi Shimbun. 22 March 2012. Archived from the original on 25 March 2012.
- "Earthquake report 447" (PDF). Japan Atomic Industrial Forum (JAIF). 19 June 2012.
- Kyodo News (20 June 2012). "Japan sat on U.S. radiation maps showing immediate fallout from nuke crisis". Japan Times. p. 1. Archived from the original on 1 November 2012.
- "Japan failed to use U.S. radiation data gathered after nuke crisis". The Mainichi Shimbun. 18 June 2012. Archived from the original on 16 July 2012.
- "U.S. forces given SPEEDI data early". The Japan Times. 17 January 2012.
- "Japan did not keep records of nuclear disaster meetings". BBC Online. 27 January 2012. Archived from the original on 20 February 2014.
- "Tepco concealed core meltdowns during Fukushima accident". Nuclear Engineering International. 24 June 2016. Retrieved 25 June 2016.
- "Areas to which evacuation orders have been issued" (PDF). 7 August 2013.
- "Designating and Rearranging the Areas of Evacuation" (PDF). JP: Meti. p. 7).
- "USS Ronald Reagan Exposed to Radiation". Navy Handbook. 14 March 2011. Archived from the original on 10 November 2013. Retrieved 18 March 2011.
- Grimes, Robin (16 June 2014). "The UK Response to Fukushima and Anglo-Japanese Relations". Science & Diplomacy. 3 (2).
- "IAEA sees slow nuclear growth post Japan". UPI. 23 September 2011. Archived from the original on 9 March 2014.
- "Gauging the pressure". The Economist. 28 April 2011. Archived from the original on 31 August 2012.
- Richard Tanter (October–December 2013). "After Fukushima: A Survey of Corruption in the Global Nuclear Power Industry". Asian Perspective. 37 (4). Retrieved 15 September 2023.
- Jeff Kingston (10 September 2012). "Japan's Nuclear Village". Japan Focus. Archived from the original on 29 March 2014.
- Culture of complicity tied to stricken nuclear plant, NYTimes, 27 April 2011
- "Japan to fire 3 top nuclear officials". Articles.cnn.com. 4 August 2011. Archived from the original on 19 August 2011. Retrieved 11 August 2011.
- "Fukushima disaster: Ex-Tepco executives charged with negligence". BBC News. 29 February 2016. Retrieved 13 March 2016.
- "3 former TEPCO executives face criminal trial over Fukushima crisis". The Asahi Shimbun. 31 July 2015. Archived from the original on 14 March 2016. Retrieved 13 March 2016.
- McCurry, Justin (30 June 2017). "Fukushima Nuclear Disaster: former Tepco executives go on trial". The Guardian. Retrieved 5 July 2017.
- "Court clears three former Tepco executives". World Nuclear News. 19 September 2019. Retrieved 20 September 2019.
- "Fukushima nuclear accident 'man-made', not natural disaster". Bloomberg L.P. The Sydney Morning Herald. Archived from the original on 3 November 2013. Retrieved 9 July 2012.
- "Japan says Fukushima disaster was 'man-made'". Al Jazeera and agencies. AL Jazeera English. 5 July 2012. Archived from the original on 30 January 2014. Retrieved 9 July 2012.
- McCurry, Justin (5 July 2012). "Japanese cultural traits 'at heart of Fukushima disaster". The Guardian. Retrieved 15 July 2021.
- "Official website of the Investigation Committee on the Accident at the Fukushima Nuclear Power Stations of Tokyo Electric Power Company". Archived from the original on 29 October 2011. Retrieved 29 July 2012.
This committee was established with the aim of conducting an investigation to determine the causes of the accident that occurred at Fukushima Daiichi and Daini Nuclear Power Stations of Tokyo Electric Power Company, and those of the damages generated by the accident, and thereby making policy proposals designed to prevent the expansion of the damages and the recurrence of similar accidents in the future.
- "Japan nuclear plants 'still not safe'". Al Jazeera Online. 23 July 2012. Archived from the original on 16 April 2014. Retrieved 29 July 2012.
- "Japan, TEPCO ignored atomic accident risks due to 'myth of nuclear safety': Report". Asian News International (ANI). News Track India. 23 July 2012. Archived from the original on 25 December 2013. Retrieved 29 July 2012.
- Mitsuru Obe; Eleanor Warnock (23 July 2012). "Japan Panel Says Plant Operator Falls Short on Nuclear Safety". The Wall Street Journal. Archived from the original on 27 September 2013. Retrieved 30 July 2012.
- Tsuyoshi Inajima; Yuji Okada (23 July 2012). "Fukushima Investigators Say More Study Needed on What Went Wrong". Bloomsberg Businessweek. Archived from the original on 28 September 2013. Retrieved 29 July 2012.
- "Update: Government panel blasts lack of 'safety culture' in nuclear accident". The Asahi Shimbun. 23 July 2012. Archived from the original on 13 April 2014. Retrieved 29 July 2012.
- Hancocks, Paula (23 July 2012). "New report criticizes TEPCO over Fukushima nuclear crisis". CNN. Archived from the original on 26 December 2013. Retrieved 29 July 2012.
- Kazuaki Nagata (24 July 2012). "Government, Tepco again hit for nuke crisis". The Japan Times. Archived from the original on 1 November 2012. Retrieved 29 July 2012.
Sources
Cited
- Health risk assessment from the nuclear accident after the 2011 Great East Japan Earthquake and Tsunami (PDF). WHO. 2013. ISBN 978-924150513-0. Retrieved 7 September 2016.
Others
- Caldicott, Helen [ed.]: Crisis Without End: The Medical and Ecological Consequences of the Fukushima Nuclear Catastrophe. [From the "Symposium at the New York Academy of Medicine, March 11–12, 2013"]. The New Press, 2014. ISBN 978-1-59558-970-5 (eBook)
- Nadesan, Majia (2013). Fukushima and the Privatization of Risk. London, Palgrave. ISBN 978-1-13734311-6
- Cleveland, Kyle; Knowles, Scott Gabriel; Shineha, Ryuma, eds. (2021). Legacies of Fukushima. University of Pennsylvania Press. ISBN 978-0-8122-9800-0.
External links
Investigation
Videos, films, drawings, and images
- "Inside Japan's Nuclear Meltdown", Season 2012, Episode 4, PBS Frontline
- Video of the Unit 1 explosion
- Video of the Unit 3 explosion
- Webcam Fukushima nuclear power plant I, Unit 1 through Unit 4
- Inside the slow and dangerous clean up of the Fukushima nuclear crisis
- TerraFly Timeline Aerial Imagery of Fukushima Nuclear Reactor after 2011 Tsunami and Earthquake
- In graphics: Fukushima nuclear alert, as provided by the BBC, 9 July 2012
- Analysis by IRSN of the Fukushima Daiichi accident
- Kumamoto, Murata & Nakate: "Fukushima Evacuees Face New Hardship Six Years On", provided by the Foreign Correspondents' Club of Japan, 9 March 2017
- Video from the Unit 2 containment below the reactor in February 2019
- The Days, docudrama, 2023, 8 one hour parts, based in part on Masao Yoshida's testimony in The Fukushima Nuclear Accident Report, 2012 - https://www.nirs.org/wp-content/uploads/fukushima/naiic_report.pdf This series "depicts the Fukushima Daiichi Nuclear Power Plant accident that occurred in 2011 over a period of 7 days." - https://www.imdb.com/title/tt22074484/]
- Ah humanity! – a film essay by Lucien Castaign-Taylor, Ernst Karel and Véréna Paravel
- "Statue of child clad in protective suit met with criticism in disaster-hit Fukushima". The Japan Times Online. 13 August 2018.
- Return to Fukushima , story taken from the collection Schegge di vita by the Italian writer Sabrina Gatti
Other
- "Inside Fukushima Daiichi~This is a virtual tour of the decommissioning site.~"(in English) by Tokyo Electric Power Company Holdings, Incorporate(in English)
- Fukushima Revitalization Station (Fukushima Prefectural Government) in English
- TEPCO News Releases, Tokyo Electric Power Company
- "Reassessment of Fukushima Nuclear Accident and Outline of Nuclear Safety Reform Plan(Interim Report)" by TEPCO Nuclear Reform Special Task Force.14 December 2012