Fuqing Nuclear Power Plant

The Fuqing Nuclear Power Plant (simplified Chinese: 福清核电站; traditional Chinese: 福清核電站; pinyin: Fúqīng Hédiànzhàn) is a nuclear power plant in Fuqing, Fujian Province, China. The plant is located on the coast of Xinghua Bay, near Qianxue Village, Sanshan Town.[1] The station has four 1,089 megawatt (MW) CPR-1000 pressurized water reactors (PWRs).[2] The CPR-1000 is an advanced PWR design developed by China from the Areva-designed PWRs at the Daya Bay Nuclear Power Plant.[3] The plant was jointly constructed and is operated by China National Nuclear Corporation (51%), China Huadian Corp. (39%) and the Fujian Investment & Development Co Ltd. (10%).

Fuqing Nuclear Power Plant
Official name福清核电站
CountryChina
LocationQianxue, Fuqing, Fujian
Coordinates25°26′45″N 119°26′50″E
StatusOperational
Construction beganNovember 21, 2008 (2008-11-21)
Commission date
  • Unit 1: August 20, 2014 (2014-08-20)
  • Unit 2: August 6, 2015 (2015-08-06)
  • Unit 3: September 7, 2016 (2016-09-07)
  • Unit 4: July 29, 2017 (2017-07-29)
  • Unit 5: November 27, 2020 (2020-11-27)
  • Unit 6: January 1, 2022 (2022-01-01)
Owner(s)Fujian Fuqing Nuclear Co.
Operator(s)China National Nuclear Corporation (CNNC)
Nuclear power station
Reactor typePWR
Thermal capacity
  • 4 × 2,905 MWt
  • 2 × 3,060 MWt
Power generation
Units operational
  • 4 × 1,000 MWe
  • 2 × 1,075 MWe
Make and model
Nameplate capacity6,656 MWe
(6,120 MWe net)
Annual net output2021: 39,394.32 GWh (141,819.6 TJ) (Units 1-5 only)
External links
Websitewww.cnnp.com.cn/cnnp/cydwzd62/fjfqhdyxgs/1101192/index.html

Construction of the first unit began on 21 November 2008[2] and was completed in 2014. First concrete for Unit 2 was poured on 17 June 2009[4] and the unit was started in October 2015. First concrete for Unit 3 was poured on 31 December 2010. Construction of Unit 4 was to begin in 2011, but was delayed until November 2012 by China's nuclear safety review following the Fukushima nuclear disaster.

In November 2014 it was announced that units 5 and 6 would be of the Hualong One (updated CPR-1000) design, with unit 5 scheduled to be in operation about 2019.[5] The first concrete was poured for Fuqing 5 on 7 May 2015.[6] Unit 5 achieved criticality in October 2020, the first Hualong One reactor to reach the milestone.[7] The unit was connected to the grid the following month.[8] It began commercial operation on 30 January 2021.[9] Unit 6 achieved criticality in December 2021, was connected to the grid in January 2022,[10] and began commercial operation on 25 March 2022.[11]

Reactor data

The Fuqing Nuclear Power Plant consist of 6 operational reactors.

UnitType / ModelNet powerGross powerThermal powerStart constructionFirst criticalityGrid connectionCommercial operationNotes
Phase I
Fuqing 1PWR / CNP-1000 1000MW1089MW2905MW 2008-11-212014-07-242014-08-202014-11-22 [3][12]
Fuqing 2PWR / CNP-1000 1000MW1089MW2905MW 2009-6-182015-07-222015-08-062015-10-16 [4][13]
Phase II
Fuqing 3PWR / CNP-1000 1000MW1089MW2905MW 2010-12-312016-07-032016-09-072016-10-24 [14][15][16]
Fuqing 4PWR / CNP-1000 1000MW1089MW2905MW 2012-11-172017-07-162017-07-292017-09-17 [2][17]
Fuqing 5PWR / HPR-1000 1060MW1150MW3060MW 2015-05-072020-10-212020-11-272021-01-30 [6][18]
Fuqing 6PWR / HPR-1000 1060MW1150MW3060MW 2015-12-222021-12-132022-01-012022-03-25 [19][20]

See also

References

  1. "Construction of Fuqing Nuclear Power Plant commences". People's Daily Online. 24 November 2008. Retrieved 2009-11-13.
  2. "Nuclear Power in China". Country Briefings. World Nuclear Association (WNA). October 2016. Retrieved 25 October 2016.
  3. "Construction gets under way at Chinese sites". World Nuclear News. WNA. 24 November 2008. Retrieved 2009-11-13.
  4. "Nuclear construction launch in China". World Nuclear News. WNA. 23 June 2009. Retrieved 2009-11-13.
  5. "Hualong One deployment at Fuqing 5". World Nuclear News. 4 November 2014. Retrieved 9 March 2015.
  6. "China starts building first Hualong One unit". World Nuclear News. 7 May 2015. Retrieved 7 May 2015.
  7. "China's Fuqing 5 achieves criticality - Nuclear Engineering International". www.neimagazine.com. Retrieved 15 December 2020.
  8. "World's first Hualong One unit connects to grid : New Nuclear - World Nuclear News". world-nuclear-news.org. Retrieved 15 December 2020.
  9. "China's first Hualong One begins commercial operation". Nuclear Engineering International. 1 February 2021. Retrieved 1 February 2021.
  10. "World's 3rd Nuclear Reactor with Hualong One Tech Connected to Grid_ News_ 福建省人民政府门户网站".
  11. "Second Fuqing Hualong One enters commercial operation". world-nuclear-news.org. 25 March 2022. Retrieved 25 March 2022.
  12. "Fuqing 1". PRIS. IAEA. 2021-04-25. Retrieved 2021-04-26.
  13. "Fuqing 2". PRIS. IAEA. 2021-04-25. Retrieved 2021-04-26.
  14. "Nuclear construction builds up". World Nuclear News. 4 January 2011. Retrieved 2011-01-11.
  15. "Fuqing 3". PRIS. IAEA. 2021-04-25. Retrieved 2021-04-26.
  16. "China's 37th reactor enters commercial operation". 2017-09-18. Retrieved 2017-09-25.
  17. "Fuqing 4". PRIS. IAEA. 2021-04-25. Retrieved 2021-04-26.
  18. "Fuqing 5". PRIS. IAEA. 2021-04-25. Retrieved 2021-04-26.
  19. "Fuqing 6". PRIS. IAEA. 2021-04-25. Retrieved 2021-04-26.
  20. "Third Hualong One unit connected to grid". World Nuclear News. World Nuclear Assn. 2022-01-04. Retrieved 2021-04-26.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.