Line 4 (Mumbai Metro)
Green Line 4 of the Mumbai Metro, currently under construction, is part of the metro system for the city of Mumbai, India and is being developed by MMRDA and a consortium of international companies.[3]
Mumbai Metro Green Line 4 | |
---|---|
Overview | |
Status |
|
Owner | MMRDA |
Line number | 4 |
Locale | Mumbai and Thane, Maharashtra, India |
Termini |
|
Stations | 32 + 2 extended 34 |
Website | Line 4 |
Service | |
Type | Rapid Transit |
System | Mumbai Metro |
Operator(s) | MMRDA |
Depot(s) | Mogharpada |
History | |
Planned opening | December 2025[2] |
Technical | |
Line length | 32.32 km (Line 4) 2.7 km (Line 4A) |
Number of tracks | 2 |
Character | Elevated |
Track gauge | 1,435 mm (4 ft 8+1⁄2 in) standard gauge |
Operating speed | 90 km/h (56 mph) |
Highest elevation | 3.90 m (12.8 ft) |
The 32.32 km (20.08 mi) line is planned to be fully elevated, and is expected to consist of 32 stations from Wadala (Mumbai) to Kasarvadavali (Ghodbunder road, Thane) via Chembur, Bhandup Mulund and Teen Hath Naka, a popular traffic crossing in Thane. It is estimated to cost ₹14,549 crore.[4] Its construction was expected to begin by June 2018.
It is expected to be completed in 2022 and is expected to provide interconnectivity among the existing Eastern Express Highway at Chembur, Central Railway, Mono Rail, the ongoing Metro Line 2B (D N Nagar to Mandale) at Chembur, and the proposed Metro Line 5 (Thane to Kalyan) at Kapurbawdi, Metro Line 6 (Swami Samarth Nagar to Vikhroli) in Kanjurmarg and Metro Line 11 (Wadala to CSMT) in Wadala. It will provide rail based access to the commercial, government bodies and geographical landmarks in Mumbai. Dedicated depots are planned in Owale land in up to an extent of 20 ha. and in Godrej Land in up to 15.50 ha. area. It will reduce the current travel time by between 50% and 75% depending on road conditions. Alstom awarded to provide rolling stock for this line, but the contract has been cancelled in March 2022 due to delays and uncertainties of the project.[5][6]
Planning
In June 2015, the Mumbai Metropolitan Region Development Authority (MMRDA) proposed building a 32 km Wadala-Thane-Kasarvadavali metro line as part of a plan to build 6 new metro lines at a total estimated cost of ₹64,000 crore (US$8.0 billion).[7] Chief Minister Devendra Fadnavis approved the proposal to build Line 4 on 3 June 2016,[8] and the Maharashtra Cabinet cleared the project on 27 September 2016. The project was estimated to cost ₹14,549 crore (US$1.8 billion).[9]
The foundation stone for Metro 4 was laid by Prime Minister Narendra Modi on 24 December 2016.[10] The Maharashtra Coastal Zone Management Authority granted Coastal Regulation Zone (CRZ) clearance to the project in February 2017. Over 1 km (0.62 mi) of the line passes over water bodies in Bhakti Park and Wadala, both areas classified as CRZ II, where regulations limit construction activities. A total of 48 piers are proposed to be built in the CRZ II zone. The MMRDA proposed building metro car depots for the line on a 30 hectare plot at Owala village in Thane district and another in Vikhroli.[11] The agency stated that the line would require two depots due to its length.[12]
The MMRDA utilized a drone to carry out survey work for Metro 4. The drones were fitted with 360 degrees camera that provide up to 3 millimetres (0.12 in) accuracy. The aerial survey takes less time than a regular survey, achieves greater accuracy and helps protect against false claims for compensation.[13] In February 2017, the MMRDA stated that it was studying the feasibility of extending the corridor from Kasarvadavali to Gaimukh.[14] In March 2017, the agency stated that it was conducting a pre-feasbility study on extending the line from Wadala to Mumbai General Post Office in South Mumbai, via the Mumbai Port Trust. The proposed 8 km (5.0 mi) extension is estimated to cost ₹300 crore per km.[15][16] The extension from Kasarvadavli to Gaimukh was approved by Fadnavis at the 144th meeting of the MMRDA on 12 January 2018. The 2.7 km extension is estimated to cost ₹949 crore (US$120 million).[17][18]
The MMRDA appointed Systra MVA Consulting India Pvt. Ltd. as the detail design consultants for Line 4 on 9 November 2017.[19] A consortium of DB Engineering, Louis Berger and Hill International was awarded a project management and construction management services contract for the Metro 4 project in April 2018.[20][21] In October 2018, the MMRDA announced that it would construct Metro 4 along with three flyovers to ensure smooth flow of traffic, with the metro running on the upper deck of the flyover. The three flyovers will be built at Bhayander Pada, Kasarvadavli and Anandnagar near Ghodbunder.[22][23]
In May 2019, MMRDA Metropolitan Commissioner R.A. Rajeev announced a modified plan to use Siddharth Colony as the interchange station with Line 2. The original plan had proposed to use the Eastern Express Highway station on Line 2B and Siddharth Colony on Line 4 as the interchange stations. However, the two stations are approximately 480 metres away from Siddharth Colony and the change was made to simplify passenger transfers.[24]
Construction
The MMRDA invited bids for civil work on the corridor on 4 January 2017.[26][27][28] The tenders for construction of viaducts and stations were divided into five packages - Wadala to Amar Mahal Junction, Garodia Nagar to Surya Nagar, Gandhi Nagar to Sonapur, Mulund Fire Station to Majiwada and Kapurbawdi to Kasarvadavali.[29][30] Metro 4 was tendered alongside Metro 2B. L&T, Afcons Infrastructure, Tata, NCC and JMC, Reliance Infrastructure-RdE, JKumar Group, ITD Cementation, CHEC-TPL bid for packages on both Metro 2B and Metro 4. A total of 10 firms and/or consortia submitted bids for the two lines, two of whom (Simplex Infrastructure and a consortium of GHEC-RCC-JV-China) bid exclusively for Metro 2B packages.[31][32]
The construction work was awarded through the engineering, procurement and construction (EPC) model in April 2018. A joint venture between Reliance Infrastructure and Italian firm Astaldi S.p.A. was awarded three packages between Kasarwadavali and Wadala worth ₹1,584 crore (US$200 million).[33] The contract for the remaining two packages, worth a combined ₹1,048 crore (US$130 million), was awarded to a joint venture between Tata Projects Limited and China Harbour Engineering Company.[34] The civil work was expected to be completed in 30 months.[35] Construction began in October 2018.[36] About 80% of soil-investigation works and 66% of utility works had been completed by 3 June 2019.[37]
In September 2019, the MMRDA awarded a ₹342 crore (US$43 million) contract to J Kumar Infraprojects to build the viaduct and two stations for the Metro 4A extension from Kasarvadavli to Gaimukh.[38][39] In August 2020, the Bombay High Court granted the MMRDA permission to carry out construction in a mangrove buffer zone.[40] Survey work on the land for a depot at Mogharpada began in January 2022.[41]
The MMRDA stated that 37% of total work on Lines 4 and 4A had been completed by June 2022. The agency stated that 43.44% of viaducts and 25.20% of work on stations on Line 4 had been completed. On Line 4A, 39.03% of viaducts and 19.82% of work on stations was completed.[42] By November 2022, 41% of civil works on Line 4 and 45% of work on Line 4A had been completed.[43][44]
Sl No. | Package | Contractor(s) |
---|---|---|
1 | Wadala to Amar Mahal
(6.2 km Viaduct & 6 Stations) |
Reliance-Astaldi JV |
2 | Garodia Nagar-Surya Nagar
(6.4 km Viaduct & 7 Stations) |
TPL-CHEC JV |
3 | Gandhi Nagar-Sonapur
(6.7 km Viaduct & 6 Stations) |
Reliance-Astaldi JV |
4 | Mulund Fire Station-Majiwada
(7.1 km Viaduct & 7 Stations) |
TPL-CHEC JV |
5 | Kapurbawdi-Kasarvadavali
(6.8 km Viaduct & 6 Stations) |
Reliance-Astaldi JV |
6 | Kasarvadavali to Gaimukh
(2.7 km Viaduct & 2 Stations) |
J Kumar Infraprojects Limited |
Current status
Status as of 21 May 2023 [45] | ||
---|---|---|
Sr. No. | Name of Work | Current Status |
1 | Pile | 89.2% |
2 | Pile Cap | 74.8% |
3 | Pier(Viaduct+Station up to CL) | 64.9% |
4 | Anti Crash Barrier | 56.3% |
5 | Road Restoration | 30.2% |
6 | Pier Cap Casting | 73.6% |
7 | Pier Cap Erection | 67.6% |
8 | Stitch Concrete | 66.7% |
9 | Stressing | 58.8% |
10 | Bearing Pedestal | 56.1% |
11 | U-Girder Casting for Viaduct | 73.1% |
12 | U-Girder Erection for Viaduct | 61.4% |
13 | I-Girder Casting for Viaduct | 27.1% |
14 | I-Girder Erection for Viaduct | 25.5% |
15 | Deck Slab Over I Girder | 25.9% |
16 | U Girder Casting For Station | 37.2% |
17 | U Girder Erection For Station | 31.3% |
18 | Cast in Situ Pier Head for Station (Concourse level) | 59.4% |
19 | Concourse Level Pier Arm Casting | 57.4% |
20 | Concourse Level Pier Arm Erection | 39.8% |
21 | Platform Level Pier Arm Casting | 57.5% |
22 | Platform Level Pier Arm Erection | 50.2% |
23 | Station L Girder Casting | 29.3% |
24 | Station L Girder Erection | 27.0% |
25 | Station T Girder Casting | 36.5% |
26 | Station T Girder Erection | 30.3% |
27 | Platform Level RCC Beam Casting | 29.2% |
Green Line 4
On 12 April 2023, MMRDA in press release stated that Green Line 4 project status is 49%.[46]
Green Line 4A
On 30 December 2022, MMRDA in press release stated that Green Line 4A project status is 45%.[47]
History of Previous Works and Status | ||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Sr. No. | Name of Work | Description | Status as of[45] | |||||||||||||
21 May 2019 | 4 July 2019 | 6 August 2019 | 21 October 2019 | 29 November 2019 | 29 January 2020 | 8 September 2020 | 1 January 2021 | 1 March 2021 | 31 May 2021 | 28 July 2021 | 18 April 2022 | 30 June 2022 | 1 September 2022 | |||
1 | Soil Investigation Works | Soil Investigation Work For Pier Foundation Completed | 78% | 81.0% | 82.0% | 83.0% | 85% | 87% | 90% | 93.20% | 90% | |||||
2 | Utility Works | Works Completed | 64% | 68.2% | 70% | 71.36% | 76% | 85% | 86% | |||||||
3 | Piling Works | Piling Work For
Foundations Completed |
17% | 22.7% | 25.25% | 33% | 37% | 42.56% | 55.15% | 62.40% | 65% | 66% | 67.78% | 65% | 69% | 69% |
4 | Pile Cap Works | Pile Cap Work Completed | 6.5% | 12.4% | 14.7% | 18.60% | 21% | 24.75% | 35.68% | 44.85% | 49% | 52% | 51.73% | 51.91% | 54% | 54% |
5 | Pier Works | Piers Cast | 3.5% | 8.0% | 10.2% | 15.70% | 18.3% | 29.23% | 29.29% | 38.16% | 42% | 45% | 45.92% | 46.80% | 49% | |
6 | Pier Cap Works | Pier Caps Cast | Nil | Casting of Pier Cap is started
at casting yard and 0.063% casting completed till June 2019 |
Casting of Pier Cap is started
at casting yard and 0.068% casting completed till July 2019 |
6% Casting completed. | 10% | 17.98% | 28.99% | 40.59% | 43% | 46% | 49.73% | 49.36% | 51% | 57.19% |
Pier Caps Erected | Nil | 0.80% Erection completed. | 2.4% | 23.34% | 23.81% | 31.33% | 36% | 39% | 42.65% | 45.06% | 46% | 46.92% | ||||
7 | Cast-in-situ Pier Cap | Nil | 89% | 89.19% | ||||||||||||
8 | U Girder Casting | Casting yard works are in progress | Nil | Casting of U Girder started
at casting yard and 0.21% casting completed till June 2019 |
Casting of U Girder started
at casting yard and 0.41% casting completed till July 2019 |
2.33% | 6% | 11.83% | 20.09% | 33.19% | 38% | 45% | 38.13% | 38.71% | 40% | 43.68% |
U Girder Erected | Nil | 0.9% | 15.69% | 29.97% | 24% | 31% | 26.27% | 27.86% | 32% | 36.63% | ||||||
9 | I Girder Casting | Nil | 8.83% | 19.09% | 21% | 24.98% | ||||||||||
10 | I Girder Erection | Nil | 17.21% | 19% | 22.42% | |||||||||||
11 | Desk Slab | Nil | 14.58% | 18% | 21.20% | |||||||||||
12 | Station work | Station work in progress | Pile Foundation works Started since last month | Works are in Progress | ||||||||||||
Station Pier Head | Nil | 37% | 40.96% | |||||||||||||
Stn Pier up to Platform level | Nil | 35% | 40.96% | |||||||||||||
13 | Concourse Pier Arm Casting | Nil | 40% | 43.86% | ||||||||||||
14 | Concourse Pier Arm Erection | Nil | 35% | 40.94% | ||||||||||||
15 | Platform Pier Arm Casting | Nil | 27% | 33.97% | ||||||||||||
16 | Platform Pier Arm Erection | Nil | 24% | 30.79% | ||||||||||||
17 | L Girder Casting | Nil | 11% | 15.03% | ||||||||||||
18 | L Girder Erection | Nil | 3% | 4.67% | ||||||||||||
19 | T Girder Casting | Nil | 15% | 20.67% | ||||||||||||
20 | T Girder Erection | Nil | 15% | 23.77% | ||||||||||||
21 | Platform Girder Casting | Nil | 8% | 13.31% |
Stations
32 stations are being planned on Line 4. Most of them were either in the stage of planning or under early stages of construction (as of November 2018) [48]
2 stations are being planned on Line 4A. Connected to word Gaimukh to Kasarvadavali also connect Metro 10.
Green Line 4 | |||||||||
---|---|---|---|---|---|---|---|---|---|
# | Station Name | Status | Connections | Layout | |||||
English | Marathi | ||||||||
1 | Gaimukh | गायमुख | Under Construction | Green Line 10 (Planned) | Elevated | ||||
2 | Gowniwada | गोवनीवाडा | Under Construction | None | Elevated | ||||
3 | Kasarvadavali | कासारवडवली | Under Construction | None | Elevated | ||||
4 | Vijay Gardens | विजय गार्डन | Under Construction | None | Elevated | ||||
5 | Hiranandani Estate | हीरानंदानी एस्टेट | Under Construction | None | Elevated | ||||
6 | Stretford Avenue | स्ट्रेटफर्ड ॲव्हेन्यू | Under Construction | None | Elevated | ||||
7 | Manpada (Thane) | मानपाडा | Under Construction | None | Elevated | ||||
8 | Kapurbawdi | कापूरबावडी | Under Construction | Orange Line 5 (Under Construction) | Elevated | ||||
9 | Majiwada | माजिवाडा | Under Construction | None | Elevated | ||||
10 | Cadbury Junction | कॅडबरी जंक्शन | Under Construction | None | Elevated | ||||
11 | Mahapalika Marg | महापालिका मार्ग | Under Construction | None | Elevated | ||||
12 | Thane RTO | आरटीओ ठाणे | Under Construction | None | Elevated | ||||
13 | Teen Haath Naka, Thane | तीन हात नाका (ठाणे) | Under Construction | None | Elevated | ||||
14 | Mulund Naka | मुलुंड नाका | Under Construction | None | Elevated | ||||
15 | Mulund Fire Station | मुलुंड अग्निशमन केंद्र | Under Construction | None | Elevated | ||||
16 | Sonapur | सोनापूर | Under Construction | None | Elevated | ||||
17 | Shangrila | शांग्रीला | Under Construction | None | Elevated | ||||
18 | Bhandup | भांडुप | Under Construction | None | Elevated | ||||
19 | Bhandup Mahapalika | भांडुप महापालिका | Under Construction | None | Elevated | ||||
20 | Naval Housing | नौदल गृहनिर्माण | Under Construction | None | Elevated | ||||
21 | Gandhi Nagar (Kanjurmarg) | गांधी नगर (कांजूरमार्ग) | Under Construction | Pink Line 6 (Under Construction) | Elevated | ||||
22 | Surya Nagar | सूर्य नगर | Under Construction | None | Elevated | ||||
23 | Vikhroli | विक्रोळी | Under Construction | None | Elevated | ||||
24 | Godrej Company | गोदरेज कंपनी | Under Construction | None | Elevated | ||||
25 | Shreyas Cinema | श्रेयस सिनेमा | Under Construction | None | Elevated | ||||
26 | Laxmi Nagar (Ghatkopar) | लक्ष्मी नगर (घाटकोपर) | Under Construction | None | Elevated | ||||
27 | Pant Nagar | पंत नगर | Under Construction | None | Elevated | ||||
28 | Garodia Nagar | गरोडिया नगर | Under Construction | None | Elevated | ||||
29 | Amar Mahal Junction | अमर महाल जंक्शन | Under Construction | None | Elevated | ||||
30 | Siddharth Colony | सिध्दार्थ कॉलनी | Under Construction | Yellow Line 2 (Under Construction) | Elevated | ||||
31 | Suman Nagar | सुमन नगर | Under Construction | None | Elevated | ||||
32 | Anik Nagar Bus Depot | अणिक नगर बस आगार | Under Construction | None | Elevated | ||||
33 | Wadala Truck Terminal | वडाळा ट्रक टर्मिनल | Under Construction | None | Elevated | ||||
34 | Bhakti Park (Wadala) | भक्ति पार्क (वडाळा) | Under Construction | Line 1 (Mumbai Monorail) Green Line 11 (Planned) | Elevated |
Cost
Line 4 is estimated to cost ₹14,549 crore (US$1.8 billion),[25] and Line 4A is estimated to cost ₹949 crore (US$120 million).[18] The Maharashtra Government signed an EUR545 million (₹4,000 crore) loan agreement with German development bank KfW to fund construction of Metro 4 and 4A in November 2020.[49]
Infrastructure
Rolling stock
The MMRDA awarded a ₹1,854 crore (US$230 million) contract to Alstom to supply 234 metro coaches for Line 4 and 4A in March 2021.[50] This was Alstom's first order after acquiring Bombardier Transportation in January 2021.[51][52] However, the company cancelled the order in March 2022 citing delays in completing the project.[53]
References
- "Mumbai Metro 4A". Archived from the original on 26 November 2018. Retrieved 26 November 2018.
- "Mumbai: Metro Lines 2A & 7 likely to be fully opened on August 15 | Mumbai News - Times of India".
- "Mumbai Metro line 4 - current status". www.mmrda.maharashtra.gov.in/. MMRDA official website. Archived from the original on 1 August 2018. Retrieved 15 November 2018.
- "Everything you need to know about Metro 2B and Metro 4 | Free Press Journal". Free Press Journal. Archived from the original on 12 February 2017. Retrieved 12 February 2017.
- "Alstom terminates Mumbai Line 4 fleet contract". 10 March 2022. Retrieved 6 April 2022.
- "Alstom cancels order bagged from MMRDA for supply of coaches for Mumbai Metro 4". 4 March 2022. Retrieved 6 April 2022.
- "Over 130 km of Metro lines to criss-cross city by 2020". The Indian Express. 16 June 2015. Retrieved 9 July 2023.
- "Maharashtra Cabinet Gives Go-Ahead For Two Metro Lines". NDTV.com. Archived from the original on 18 October 2016. Retrieved 14 October 2016.
- "Mumbai to get two more Metro Rails". Business Standard India. 27 September 2016. Archived from the original on 18 October 2016. Retrieved 14 October 2016.
- "MMRDA invites civil work bids for two Metro projects". The Times of India. Archived from the original on 12 February 2017. Retrieved 10 February 2017.
- "Wadala-Thane metro line clears CRZ hurdle - Mumbai Mirror -". Mumbai Mirror. Archived from the original on 28 February 2017. Retrieved 27 February 2017.
- "Mumbai: MMRDA to acquire private land in Thane for Metro 4 car shed". The Indian Express. 11 November 2018. Retrieved 10 July 2023.
- "MMRDA plans drone survey for other Metro lines". The Indian Express. 7 March 2017. Archived from the original on 7 March 2017. Retrieved 7 March 2017.
- "Mumbai Metro Phase 4 may cover entire Ghodbunder Road stretch in Thane". Hindustan Times. 2 February 2017. Retrieved 10 July 2023.
- "MMRDA plans to extend Metro-IV route from Wadala to GPO". The Times of India. Archived from the original on 16 March 2017. Retrieved 17 March 2017.
- "Mumbai Metro's Thane-Wadala line likely to be extended to CST/GPO | Latest News & Updates at Daily News & Analysis". dna. 16 March 2017. Archived from the original on 17 March 2017. Retrieved 17 March 2017.
- "Mumbai Metro 4 will now reach Thane's Ghodbunder Road". Hindustan Times. 12 January 2018. Retrieved 10 July 2023.
- "Kasarvadavali-Gaikmukh metro project in Thane approved". Mumbai Mirror. 27 December 2018. Retrieved 10 July 2023.
- "MMRDA's Executive Committee Meeting held today Contractors, consultants appointed for MTHL, Metro-4, Wadala Truck Terminal and flyover on NH-4". MMRDA. 9 November 2017. Retrieved 10 July 2023.
- Berger, Louis. "Louis Berger awarded Mumbai Metro Line 4 contract in India". GlobeNewswire News Room. Archived from the original on 9 October 2018. Retrieved 9 October 2018.
- "DB Engineering-Louis Berger bags contract for Mumbai Metro 4". dna. 10 April 2018. Archived from the original on 9 October 2018. Retrieved 9 October 2018.
- "Metro-4, 9 to be built along with flyovers". The Asian Age. 1 October 2018. Archived from the original on 9 October 2018. Retrieved 9 October 2018.
- "Mumbai: MMRDA to build Metro 4 & 9 corridors along with flyovers". Free Press Journal. 4 October 2018. Archived from the original on 9 October 2018. Retrieved 9 October 2018.
- Naik, Yogesh (21 May 2019). "MMRDA redrafts plans for better connectivity between Mumbai Metro corridors". Mumbai Mirror. Archived from the original on 6 June 2019. Retrieved 6 June 2019.
- "Non-confirmation of depot land: Fate of 3 new Mumbai Metro lines hangs in balance". The Indian Express. 8 February 2023. Retrieved 10 July 2023.
- "MMRDA invites bids for 2 metro projects". dna. 5 January 2017. Archived from the original on 8 January 2017. Retrieved 10 February 2017.
- "MMRDA invites tenders for design, construction of stations, viaducts for new Metro routes". The Indian Express. 5 January 2017. Archived from the original on 11 February 2017. Retrieved 10 February 2017.
- "Racing against 2021 deadline, Maharashtra opens bids for two more Metro lines". Hindustan Times. 5 January 2017. Archived from the original on 11 February 2017. Retrieved 10 February 2017.
- Correspondent, Special. "MMRDA invites tenders for Metro-2B and 4". The Hindu. Archived from the original on 6 January 2017. Retrieved 12 February 2017.
- "Mumbai commute to get faster, firms queue up to build two more Metro lines". Hindustan Times. 13 May 2017. Archived from the original on 14 May 2017. Retrieved 13 May 2017.
- "MMRDA receives interest from domestic, foreign firms for metro". India Today. Archived from the original on 14 June 2017. Retrieved 13 May 2017.
- "R Infra, 10 others bid for Metro-2B, Metro-4 corridors". Asian Age. 13 May 2017. Archived from the original on 24 May 2017. Retrieved 13 May 2017.
- "Reliance Infra bags three packages of Mumbai Metro Line 4". The Economic Times. 13 April 2018. Archived from the original on 9 October 2018. Retrieved 9 October 2018.
- "Tata Projects bag Rs 1,048 crore Mumbai Metro packages". The Economic Times. 13 April 2018. Archived from the original on 9 October 2018. Retrieved 9 October 2018.
- Pillay, Amritha (14 April 2018). "Reliance Infrastructure, Tata Projects win bids for Mumbai Metro project". Business Standard India. Archived from the original on 9 August 2018. Retrieved 9 August 2018.
- "Metro Lines 4, 5 connecting Thane to different cities to be completed only by 2025, says MMRDA official". Hindustan Times. 3 June 2022. Retrieved 10 July 2023.
- "Metro lines 4 and 5 to be linked at station in Thane". Hindustan Times. 17 June 2019. Retrieved 10 July 2023.
- "Contractor for Metro 4A named". The Times of India. 10 September 2019. ISSN 0971-8257. Retrieved 10 July 2023.
- "Mumbai Metro 4A bags civil contracts". Archived from the original on 13 October 2019. Retrieved 30 November 2020.
- "High Court gives nod for Metro Line 4 in Mumbai's mangrove buffer zone". Business Standard. Retrieved 10 July 2023.
- "Hurdles for Wadala to Thane Metro Line 4 cleared; survey of car shed land begins". Hindustan Times. 28 January 2022. Retrieved 10 July 2023.
- "Four years on, Mumbai-Thane Metro Line 4 still only 37% complete". Free Press Journal. Retrieved 10 July 2023.
- "Mumbai: Here is latest update of more than dozen Metro projects in the city". Free Press Journal. Retrieved 10 July 2023.
- "State of the Mumbai Metro: 14 lines in the works, two nearing completion". The Indian Express. 4 November 2022. Retrieved 10 July 2023.
- "Mumbai Metropolitan Region Development Authority - Metro Line - 4". Mmrda.maharashtra.gov.in. 28 July 2021. Archived from the original on 5 October 2017. Retrieved 3 June 2023.
- "Metro line 4 achieves 49% Physical Work Completion". 12 April 2023. Retrieved 14 May 2023.
- "MMRDA Press Release 30th December 2022" (in Marathi). 30 December 2022. Retrieved 20 April 2023.
- "Mumbai Metro 4 – Wadala–Ghatkopar-Mulund–Teen Hath Naka–Kasarvadavali Station". Archived from the original on 5 October 2017. Retrieved 7 June 2017.
- "German bank extends credit line for 2 lines of Mumbai Metro". The Indian Express. 7 November 2020. Retrieved 10 July 2023.
- "Alstom to make 39 rakes for Metro 4, 4A for Rs 2k cr in Mumbai". The Times of India. 31 March 2021. ISSN 0971-8257. Retrieved 10 July 2023.
- "Alstom wins €220-million contract to manufacture 234 metro cars for Mumbai Metro Lines 4, 4A". www.thehindubusinessline.com. 30 March 2021. Retrieved 10 July 2023.