National Highway 275 (India)

National Highway 275 (NH-275), also commonly referred to as Bengaluru–Mysuru access-controlled Expressway, part of the Bengaluru–Mangaluru Economic Corridor (EC-34),[1] is a national highway that starts from Bengaluru and goes through Mysuru as a 10-lane expressway of 119 km (74 mi), and again as 4-lane till Bilikere (towards Madikeri), and ends at Bantwal.[2] This highway connects the coastal city of Mangaluru to Bengaluru. It is also a bypass route for the National Highway 75 (NH-75). The Bengaluru to Mysuru section of this highway was upgraded from 4 to 10 lanes, out of which the 6-lane section is the main elevated access-controlled carriageway and the other 2-lane section on both ends of the carriageway are service roads. It claims to reduce the travel time between Bengaluru and Mysuru from 3 hours to 75 minutes.[3]

Highway NumberSourceDestinationViaLength (km)
275BantwalBengaluruMysuru367

National Highway 275 shield}}
National Highway 275
Map of the National Highway in red
Vehicles_plying_on_Bengaluru_Mysuru_Expressway.jpg
Route information
Length367 km (228 mi)
Major junctions
East endBengaluru
Major intersections
List
West endBantwal, Karnataka
Location
CountryIndia
StatesKarnataka
Major citiesBengaluru, Kengeri, Bidadi, Ramanagara, Channapatna, Maddur, Mandya, Srirangapattana, Mysuru, Hunsur, Periyapatna, Bylakuppe, Kushalanagar, Madikeri, Sullia, Puttur and Bantwal
Highway system
NH 48 NH 73

Bengaluru-Mysuru section

The highway section between Bengaluru and Mysuru

The Bengaluru–Mysuru access-controlled Expressway is a 119 km (74 mi) long, 10-lane, elevated access-controlled expressway. It has been built at a cost of ₹ 8,000 crore and was developed in two phases. Phase-1 of 56 km (35 mi) length connecting Bengaluru and Nidaghatta, and Phase-2 of 61 km (38 mi) connecting Nidaghatta and Mysuru. The foundation stone for the project was laid in March 2018.[4]

Status updates

  • Mar 2018: Foundation stone laid for the project.
  • Apr 2018: Contract awarded for Phase-1 to Bhopal-based Dilip Buildcon Limited.
  • Mar 2019: Civil work which got stuck due to land acquisition issues to start by April 2019.[5]
  • Jul 2020: Work on Phase-1 started in May 2019 and work on Phase-2 started in Dec 2019. Both phase are seeing delay due to COVID-19 related problems, which caused labour shortages and several delays in work. It may see the deadline of January 2022; to get further delayed.[6]
  • Dec 2021: Work on Phase-1 completed up to 83% and Phase II completed up to 73%. The expressway is expected to become operational by October 2022.[7]
  • Feb 2023: The highway is at its final stages of construction work, and will be inaugurated by Prime Minister Narendra Modi on 11 March 2023.[8][9]
  • March 2023: The expressway section was inaugurated by Prime Minister Narendra Modi on 12 March 2023.[10]

See also

References

This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.