Nordjylland Power Station (Danish: Nordjyllandsværket) is a coal-fired combined heat and power plant in Vodskov, 17 kilometres (11 mi) north-east of Aalborg, Denmark. It is operated by the municipality Aalborg Kommune. The first unit at the site became operational in 1967, under the association "I/S Nordjyllands Elektricitetsforsyning".[2][3] Its original name from the opening was "Vendsysselværket", and build to burn oil from the start, but prepared for reconstruction to also burn coal.[3]
Nordjylland Power Station | |
---|---|
Official name | Nordjyllandsværket |
Country | Denmark |
Location | Vodskov |
Coordinates | 57°04′29.9″N 10°02′21.8″E |
Status | Operational |
Commission date | 1967 |
Owner(s) | Aalborg Kommune |
Operator(s) | Aalborg Forsyning |
Thermal power station | |
Primary fuel | Coal |
Turbine technology | Steam turbine |
Cooling source | Salt sea water from the fjord |
Cogeneration? | Yes |
Power generation | |
Units operational | 1 × 25 MW Unit 3: 411 MW |
Units decommissioned | 2 |
Nameplate capacity | 411 MW |
Annual net output | 1,418,294 MWh electric and 4,144 TJ district heating (2018)[1] |
External links | |
Website | |
Commons | Related media on Commons |
The power plant have had 3 coal fired boilers and a gas turbine. The gas turbine has an output of 25 MW and entered service in 1977, while unit 2, which went also in 1977 has a maximum production capacity of electricity of 305 MW and heat of 42 MJ/s. Unit 3, which entered service in 1998, has a maximum production capacity of 411 MW and a maximum heat production capacity of 490 MJ/s. It uses a 170.1 metres (558 ft) tall flue gas stack, while Units 1 and 2 and the gas turbine use 112.17 metres (368.0 ft) tall stacks. Unit 3 was the first power plant in Denmark with a SNOX-system for exhaust cleaning.
The produced heat is used for district heating of Aalborg.
An electric boiler for district heating was inaugurated in January 2018.[4][5] It can convert 35 MW from electricity to heated water, and can act as an back-up heating source for the district heating system. This electric boiler was envisioned in 2017 to replace some of the use of methane gas and oil for the district heatings backup needs, and sell regulations services for the electricity market.[6]
Power lines
While two power lines leave the station eastward to the famous Vester Hassing Static Inverter Plant, where HVDC Konti-Skan starts, two other 380-kV lines cross Limfjord just east of the power plant in two spans. The towers of the westernmost of these spans are 101.2 metres (332 ft) tall and cross Limfjord in a 723 metres (2,372 ft) long span, while that of the easternmost span are 141.7 metres (465 ft) tall and cross Limfjord in a 797 metres (2,615 ft) long span. Latter towers are the tallest electricity pylons in Denmark. Their considerable height results from the fact that they are equipped with a further crossbar for a 110-kV circuit.
See also
References
- Nordjyllandsværket A/S (2019-04-11). "Annual report/Årsrapport 2018" (PDF) (in Danish). p. 12.
- "History". Aalborg Forsyning. Retrieved 14 November 2019.
- "Newspaper article published 1967-04-28: "Vendsyssel selvforsynende med elektricitet"". Republished by 'Teknologiens Mediehus'. Originally published by 'Ingeniør- og Bygningsvæsen'. 1967-04-28. Retrieved 14 November 2019.
- "Aalborg Energikoncern indvier 35 MW elkedel". Energy Supply DK. 2018-01-22. Retrieved 2019-11-14.
- "Newspaper article titled "Kæmpe el-kedel klar til brug"". www.nordjyske.dk (in Danish). 2018-01-19. Retrieved 2019-11-14.
- "Press release titled "Aalborg Energikoncern får elkedel"" (PDF). Aalborg Forsyning. 2017-08-16. Retrieved 2019-11-14.