London and Continental Railways

London and Continental Railways (LCR) is a property development company owned by the Government of the United Kingdom for developing former railway land. The company was originally established in 1994 as a private consortium to own European Passenger Services and build the Channel Tunnel Rail Link (CTRL) under a contract agreed with the government.

London & Continental Railways Limited
TypeLimited liability company
IndustryProperty development
Founded1994 (1994)
Headquarters,
England, UK
OwnersDepartment for Transport
Websitelcrproperty.co.uk

After the full length of the CTRL was opened and rebranded as High Speed 1 (HS1) in late 2007, the company subsequently ran into financial difficulties and was nationalised in June 2009.

History

Creation

LCR was established in 1994 during the privatisation of British Rail. LCR bid for and won the contract from the UK government in 1996 to build and operate the Channel Tunnel Rail Link between London and the Channel Tunnel, under the terms of the Channel Tunnel Rail Link Act 1996.[1][2] As part of this deal European Passenger Services (EPS) and Union Railways, companies owned by British Rail, were transferred to LCR ownership, as well as key pieces of railway infrastructure including St Pancras railway station and the King's Cross Central lands nearby.

EPS was the British arm of the joint Eurostar operation, along with SNCF in France and SNCB in Belgium. LCR renamed EPS as Eurostar (UK) Ltd (EUKL). Union Railways had been developing plans for the CTRL since before the opening of the Channel Tunnel and became the construction company of the CTRL under the ownership of LCR. To aid the construction process, Union Railways was empowered by the British government to make use of compulsory purchase orders as a reserve measure for land acquisition.[3]

The original shareholders of LCR were Bechtel (19%), Warburg (19%), Virgin Group (18%), National Express (17.5%), SNCF (8.5%), London Electricity (8.5%), Arup (3.5%), Halcrow (3%) and Systra (3%).[4] As part of the 1996 contract, LCR was to finance and construct the CTRL itself, funding the project from income received from the Eurostar operation. LCR also planned to raise additional capital from a partial stock market flotation once the project was underway.[5][6]

Financial problems

In January 1998, LCR ran into major financial difficulties after finding that income from its share of the Eurostar operation was not at the level it expected.[7][8] It blamed the lower level of passenger growth on disruption caused by a November 1996 fire in the Channel Tunnel and the growth of competing low-cost airlines. LCR's planned flotation, which had already been delayed, was aborted. With the entire CTRL project in doubt, LCR appealed to the British government for help.[9][10]

Government support

To enable the project to continue, LCR was allowed to issue £3.7bn of private bonds, which the government pledged to guarantee.[11] In return the government gained a percentage of future profits from the operation of the CTRL once completed, as well as a golden share in LCR. As part of the deal LCR was forced to appoint a management contract for EUKL. This was won by Inter-Capital and Regional Rail (ICRR), a consortium of National Express (40%), SNCF (35%), SNCB (15%) and British Airways (10%). The contract was to run from 1998 until 2010.[12][13]

Following the access to finance, LCR was able to begin the CTRL project. Rail Link Engineering (RLE) was appointed to design and engineer the CTRL. RLE was a group made up of the four engineering companies involved in LCR; Bechtel (50%), Arup (19%), Halcrow (17%) and Systra (14%).[14] In addition, Railtrack was brought into the project by the government and agreed to purchase the CTRL from LCR once completed.[15]

To reduce the risks surrounding the project, the construction was split into two phases. Section 1, from the Channel Tunnel to Fawkham Junction in Kent, was to be managed by Union Railways (South) under the control of Railtrack, who committed to purchase Section 1 from LCR once complete for the cost of its construction. The more complex part, Section 2 running from Fawkham Junction to London St Pancras was to be managed by Union Railways (North). Railtrack also purchased an option, to be exercised by 2003, to control Union Railways (North) during construction and acquire Section 2 once complete. It was intended that with the completed full-length CTRL then in Railtrack's future ownership, EUKL would then pay track access charges to use the line.[16]

Railtrack crisis

Following a series of rail accidents and a subsequent share price collapse, Railtrack announced in April 2001 that it would not take up its option to project manage and then purchase Section 2. Instead, Section 2 would be owned on completion by LCR, with Railtrack owning Section 1 as well as being responsible for operating both sections.[17][18][19]

In October 2001, Railtrack was placed into "railway administration" with debts of £7.1bn and in October 2002 Railtrack's assets were transferred to a newly created "not for dividend" company called Network Rail, whose debts would be guaranteed by the government.[20][21] LCR re-purchased Railtrack's interest in Section 1 for £295m, meaning that both sections would once again be in LCR's ownership upon subsequent competition. Network Rail agreed to pay LCR £80m for the right to operate and maintain HS1 on LCR's behalf once complete.[22]

CTRL completion

Section 1 of the Channel Tunnel Rail Link was completed in September 2003 and handed over by Union Railways (South) to LCR.[23][24] Upon its completion, Eurostar services started running on Section 1, leading to international journey reductions of approximately 20 minutes. Furthermore, freight trains operated by EWS started running over Section 1 during April 2004.[25]

During early 2006, the Office for National Statistics reclassified LCR as a public corporation due to LCR's reliance on government funding and the resulting high levels of influence the government enjoyed over the company.[26] Over the next few years, rumours repeatedly circled that numerous parties, including the businessman Adrian Montague, intended to acquire LCR from its current shareholders.[27][28] By late 2007, reports were emerging that the British government were contemplating breaking up LCR into three separate companies and their sale to private owners.[29]

The Channel Tunnel Railway Link was finally finished when Section 2 was completed and handed over by Union Railways (North) to LCR. In November 2007, the full length of the line was opened to the public, rebranded as High Speed 1 (HS1).[27] It permitted Eurostar trains to operate international train services from St Pancras railway station, and a further 20-minute journey time reduction. Furthermore, a high-speed domestic service, operated by Southeastern to London St Pancras via Ebbsfleet International and Stratford International, began in June 2009.[30][31]

Nationalisation

By May 2009, LCR had become insolvent, and the government received an agreement to use state aid to purchase the line and to open it up to competition to allow other services to use it apart from Eurostar.[32]

Following the Channel Tunnel Rail Link (Supplementary Provisions) Act 2008, the Department for Transport took direct ownership of LCR in June 2009 for a nominal price. This was possible due to the company's dependence on £5.1bn of government-guaranteed debt, and the government's special share in LCR giving it a wide range of control over the business.[33][34] The government stated it planned to sell off LCR's assets, such as EUKL and HS1, as individual companies to recoup some of the large amounts of government money paid to LCR since 1998.[35]

Eurostar restructuring

On 31 December 2009, EUKL was renamed Eurostar International Limited (EIL). On 1 September 2010, the three national Eurostar operators merged into a single company with a single management structure. Following this change, the ICRR management contract for the UK business was terminated.[36] All Eurostar assets were transferred to EIL, with LCR's holding in the new company becoming 40%. The remaining shares were held by SNCF (55%) and SNCB (5%).[37]

High Speed 1 concession

In November 2010, a 30-year concession to own and operate HS1 was sold to a Canadian consortium of Borealis Infrastructure and Ontario Teachers' Pension Plan for £2.1bn.[38][39] The sale was somewhat controversial, largely as the highest bid made was passed over on in favour of a lower sum.[40]

During 2017, the sale of the 30 year HS1 concession was announced to funds advised and managed by InfraRed Capital Partners and Equitix Investment Management; participants include HICL Infrastructure (35%), Equitix (35%) and South Korea's National Pension Service (30%), in exchange for £3 billion.[41][42]

BRB (Residuary) assets

Following the abolition of BRB (Residuary) Limited (BRBR) on 30 September 2013, LCR took ownership of a number of former British Rail offices in Croydon, Derby, Manchester and Birmingham, as well as sites in Oxford and Leeds. It also took over the management of the closed Waterloo International railway station and North Pole depot, on behalf of the Secretary of State for Transport. The remaining BRBR assets and responsibilities were split between the Highways Agency, Network Rail and the Rail Safety and Standards Board.[43][44]

Eurostar divestment

On 4 December 2013, the government announced that it intended to sell LCR's 40% stake in EIL.[45] In June 2014, the shareholding was transferred from LCR to HM Treasury[46][47] and the sale process was subsequently launched on 13 October 2014.[48] The sale was completed in March 2015, raising a grand total of £760 million.[49]

Current operations

As of 2015, LCR is a state-owned railway property development company. It is involved in a number of regeneration projects on former railway land, including King's Cross Central, Stratford City and Manchester Mayfield. It also managed Waterloo International railway station and currently manages North Pole depot , as well as providing property advice to HS2 Limited.

In 2021, LCR plans to bring forward property developments on several railway sites in North West England.[50]

See also

References

  1. "London & Continental wins Eurostar and Channel Tunnel Rail Link". The Railway Magazine. No. 1, 141. May 1996. p. 9.
  2. "Virgin consortium calls pitch for 5m Eurostar". marketingweek.com. 8 March 1996.
  3. "Offer to homes on CTRL route". constructionnews.co.uk. 30 September 1999.
  4. "Stakeholders London and Continental Railways". OMEGA Centre. Archived from the original on 23 December 2012. Retrieved 6 May 2012.
  5. Harrison, Michael (3 January 1998). "LCR set to award contracts for rail link tunnels". The Independent.
  6. Ramesh, Randeep; Brown, Colin (3 June 1998). "BA wins race for high-speed tunnel rail link". The Independent.
  7. Sorkin, Andrew Ross (30 January 1998). "INTERNATIONAL BUSINESS; Consortium May Abandon Rail Contract". New York Times.
  8. Pollalis, Spiro N.; Georgoulias, Andreas (May 2013). "Channel Tunnel Rail Link: Risk Transfer and Innovation in Project Delivery" (PDF). Harvard.
  9. "Shooting Star". Marketing Week. 5 March 1998. (subscription required)
  10. "London & Continental 'gets rail link deadline extension'". constructionnews.co.uk. 26 February 1998.
  11. Stokdyk, John (14 October 1998). "Business - Bonds save LCR #400m in interest costs". accountancyage.com.
  12. "Memorandum by Inter-Capital and Regional Rail Ltd (RES 4)" (Press release). Parliament.uk. 20 November 1998.
  13. "Eurostar restructure sees UK expand rail stake". Archived from the original on 23 October 2013.
  14. "United Kingdom High Speed 1" (PDF). Systra.
  15. "Railtrack poised to take control of CTRL". New Civil Engineer. 21 May 1998.
  16. "Railtrack and Bechtel set to build CTRL in stages". constructionnews.co.uk. 12 March 1998.
  17. Harper, Keith (30 May 2000). "Railtrack funding of Channel rail link in doubt again". The Guardian. London. Archived from the original on 8 May 2014. Retrieved 1 August 2009.
  18. Harrison, Michael (16 January 2001). "Railtrack could ditch new Channel rail link". The Independent. London. Archived from the original on 1 December 2009. Retrieved 1 August 2009.
  19. Brown, Colin (1 April 2001). "Railtrack to lose its new-line monopoly". The Independent. London. Retrieved 1 August 2009.
  20. "Network Rail closer to Railtrack takeover". BBC News. 18 September 2002. Archived from the original on 17 September 2009. Retrieved 20 May 2010.
  21. Bowman, Andrew (March 2015). "An illusion of success: The consequences of British rail privatisation". Accounting Forum. 39 (1): 51–63. doi:10.1016/j.accfor.2014.10.001. S2CID 154910139.
  22. Tran, Mark (27 June 2002). "Railtrack". The Guardian.
  23. "Britain finally joins the high-speed club: the first section of CTRL opens on 28 September". International Railway Journal. August 2003.
  24. "Network Rail takes control of CTRL phase 1 high speed rail link". Network Rail. 29 September 2003.
  25. "Channel Tunnel Rail Link opens for freight services" (Press release). English, Welsh & Scottish Railway. 2 April 2004. Archived from the original on 1 October 2006. Retrieved 18 August 2011.
  26. "Debt-laden Channel tunnel rail link is 'nationalised'". The Guardian. 21 February 2006.
  27. "High Speed 1 opens amid rumours of bids for LCR". New Civil Engineer. 7 November 2007.
  28. Mathiason, Nick (19 February 2006). "Channel link investors will sell to Montague". The Guardian.
  29. Boyd, Olivia (2 November 2007). "Government considers LCR sell-off". building.co.uk.
  30. "Fast and surreal: Ashford to London on the high speed train". Kent Online. 18 June 2009. Retrieved 10 September 2018.
  31. "Javelin train on 140mph test-run". BBC News. 18 June 2009. Retrieved 28 October 2019.
  32. Owen, Ed (8 June 2009). "Government takes control of London and Continental". New Civil Engineer. London. Archived from the original on 27 April 2012. Retrieved 16 February 2010.
  33. "Government acquires LCR". Railway Gazette International. July 2009. p. 9.
  34. "Department for Transport Resource Accounts 2009-2010" (PDF). The Stationery Office. 22 July 2010.
  35. "London and Continental Railways Limited (Oral statement)" (Press release). Department for Transport. 8 June 2009. Archived from the original on 8 April 2010.
  36. "Eurostar restructure sees UK expand rail stake". AllRailJobs.co.uk. 27 June 2009. Archived from the original on 23 October 2013.
  37. "Eurostar Ownership & Structure". Eurostar. Archived from the original on 8 May 2009. Retrieved 6 May 2012.
  38. "£2.1bn HS1 sale lifts privatisation prospects". The Financial Times. 5 November 2010.
  39. "High Speed 1 concession awarded to Canadian pension consortium". Railway Gazette International. London. 5 November 2010. Archived from the original on 8 November 2010. Retrieved 5 November 2010.
  40. Milmo, Dan (28 January 2011). "Highest bidder asks why it lost Channel tunnel rail link sale". The Guardian. London. Archived from the original on 13 January 2015. Retrieved 2 February 2011.
  41. "HS1 concession sold on". Railway Gazette International. 17 July 2017. Archived from the original on 24 July 2017. Retrieved 26 July 2017.
  42. "HS1 railway line sold for EV of £3bn, below initial expectations". Financial Times. 15 July 2017. Retrieved 9 April 2023.
  43. "LCR takes on BRBR properties". LCR. 30 September 2013.
  44. "BRB (Residuary) Ltd has been abolished – News stories". www.gov.uk. Retrieved 4 August 2015.
  45. "UK government revives infrastructure drive". The Financial Times. 4 December 2013.
  46. "House of Commons Hansard Ministerial Statements for 19 June 2014 (pt 0001)". UK Parliament. House of Commons. Retrieved 3 October 2014.
  47. "Proposed sale of the UK Government's stake in Eurostar" (PDF). gov.uk. 13 October 2014.
  48. "Eurostar rail stake touted for sale by UK government". BBC News. 13 October 2014.
  49. "The sale of Eurostar". National Audit Office. 6 November 2015.
  50. "Place North West | LCR to start search for railway site developers". Place North West. 28 January 2021.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.