Kolkata Metro Line 2

Kolkata Metro Line 2, also known as the East-West Metro and Green Line, is a rapid transit line of the Kolkata Metro in the Indian state of West Bengal. It currently consists of an operational section between Salt Lake and Sealdah, and will eventually connect Howrah by going underneath the Hooghly River, with an eastern extension also planned for Teghoria.[1] It would consist of 17 stations from Teghoria (Haldiram) in the east to Howrah Maidan in the west, of which 11 would be elevated and 6 would be underground, with a total distance of 22 km (14 mi). It is expected to derive a very high ridership since it will connect India's two largest commuter railway and long-distance railway terminals (Howrah and (Sealdah) along with two of its largest business districts (BBD Bagh and Salt Lake Sector V). It will also be connecting the industrial hub of Kolkata i.e. Howrah and the IT hub of Kolkata i.e. Sector 5.[7] Line 2 has India's biggest underwater metro tunnel along with the deepest metro shaft.[8][9] In the deepest metro shaft, Howrah metro station will be the deepest metro station in India, which will be 33 meters deep.[10]The first phase between Salt Lake Sector V and Salt Lake Stadium was inaugurated by Union Railway Minister Piyush Goyal on 13 February 2020 and commercial services started from 14 February 2020.[11][12]

Kolkata Metro Line 2
Kestopur - Howrah Maidan
BEML Kolkata metro rake in a platform
Overview
Status
  • Phase 1 – Operational
  • Phase 2 – Under Construction
  • Phase 3 – Proposed
OwnerKolkata Metro Rail Corporation Green line
LocaleKolkata Metropolitan Area, India
Termini
Connecting linesBlue Line Purple Line Orange Line
Stations8 (operational)
WebsiteKMRC
Service
TypeRapid transit
SystemKolkata Metro
Operator(s)Metro Railway, Kolkata[2]
Depot(s)Central Park depot
Rolling stockBEML Limited
Daily ridership100,000[3][4] (1 million by 2035, when fully operational)[5]
History
Opened13 February 2020 (2020-02-13)
Last extension11 July 2022 (2022-07-11)
Technical
Line length32.11 km (19.95 mi)
9.1 km (5.7 mi) (operational)
7.31 km (4.54 mi) (under construction)
15.7 km (9.8 mi) (proposed)(Underground: 11.04 km (6.86 mi)
Elevated: 21 km (13 mi))
Number of tracks2
Character
  • Underground – 6
  • Elevated – 11
Track gauge1,435 mm (4 ft 8+12 in) standard gauge
Electrification750 V DC third rail[6]
Operating speed80 km/h (50 mph) (design)
SignallingCommunications-based train control
Route Map

Teghoria
(Haldiram) Orange Line
Raghunathpur
Baguiati
Dum Dum Park
Kestopur
Salt Lake Sector-V
Karunamoyee
Central Park
City Center
Bengal Chemical
Salt Lake Stadium
Phoolbagan
Sir Gurudas
Banerjee Halt
Circular Canal
Sealdah crossover
Sealdah
Esplanade
Mahakaran
Howrah ferry/water interchange
Howrah Maidan

History

The master plan had already identified the corridor way back in 1971. But the success of the Delhi Metro contributed to the sanction of the East – West Metro corridor, which will connect Howrah Railway Station with the Satellite city of Salt Lake. In January 2004, the Pacific Consultant International Group conducted a feasibility study for the line. The report proposed the route and tubular structures be under the Hooghly River.

A new organisation called the Kolkata Metro Rail Corporation Limited (KMRC) was formed, which will be executing the operations of this Line, commencing construction in 2009.[13] Of KMRC's eight directors, four each were from the state and central governments. The cost was being shared between the state government (30 per cent), the Union Urban Development Ministry (25 per cent), and the Japan Bank for International Cooperation (JBIC) (45 per cent).[14] But as of 2011, after state government dis-invested from the project, most of the share of this project went to Indian Railways and with Japan Bank for International Cooperation (JBIC). The project is estimated at a cost of 50 billion (US$630 million).[15] While by 2019, the cost escalated to 80 billion (equivalent to 99 billion or US$1.2 billion in 2023).

But due to major setbacks, such as land acquisition, slum relocation, and route alignment problems, the project got delayed. The East-West Corridor was originally slated to be operational by 2012, but was later pushed back to 2015. The project will now be implemented in four phases. The first phase, from Salt Lake Sector V to Salt Lake Stadium, became operational on 13 February 2020. The second phase, to Phoolbagan opened on 4 October 2020, operational from 5 October 2020. The third phase to Sealdah is operational from 14 July 2022 and the final phase which includes the journey through the tubular tunnels under the Ganges will be operational by 2023.

Current status

As of July 2022

  • Elevated Corridor: The elevated section for Phase 1 is complete, including last trials. Commercial operations started on 14 February 2020.[12]
  • Tunnel for Phase 2: The construction of the 5490 metre tunnel has been completed. This section was constructed by ITD-ITD Cementation JV.
  • Underground Stations for Phase 2: The works at Phoolbagan station is complete and it is operational from 04 October 2020.
  • Underground Stations for Phase 3: The Sealdah station is now complete and has inaugurated by Union Minister Smriti Irani and is available for commercial usage from 14 July 2022. [16]
  • Tunnel for Phase 3: Tunneling work for phase 3 is complete. However, work at the shaft at Durga Pithuri Lane is ongoing.
  • Underground Stations for Phase 4: Howrah Maidan, Howrah, Mahakaran and the new Esplanade are structurally complete.[17][18]
  • Tunnel work for phase 4: Both tunnels for phase 4 is complete. Tunneling between Esplanade and Sealdah was completed on 9 October 2020 and between Sealdah and Bowbazar shaft completed on 15 May 2021.[16][19] Retrieval of the TBMs and covering of the shaft is on-going.
  • Train Depot: Construction, electrical and mechanical work have been completed and it is presently operational.

Timeline

  • 2009: Contract for building the overground stations and viaduct awarded to Gammon and Simplex Infrastructure.
  • 2009: Contract for building the underground section from Subhash Sarabor to Central Station awarded to ITD-ITD Cementation JV.
  • 2009-February: Physical Construction of EW corridor starts.
  • 2010: Contract for building the underground section from Central to Howrah Maidan awarded to Afcons.
  • 2012: KMRC awards rolling stock contract to Spain's Construcciones y Auxiliar de Ferrocarriles (CAF).
  • 2012: Realignment proposed to avoid shifting of 80 families from Bowbazar and hawkers from Brabourne Road.
  • 2014: CAF withdraws from the KMRC rolling stock contract due to cost escalation.
  • 2015: Realignment approved by Railways and JICA in between Sealdah to Howrah station.
  • 2015: Subodh Mullick Square station, a key stop in the revised blueprint, done away with to avoid eviction of hawkers.
  • 2015: Complete elevated tracks other than 365 metres (1,198 ft) at Duttabad ready.
  • 2016-February: Rolling stock contract for 14 rakes having 6 coaches awarded to BEML.
  • 2017-January: Structural and Roofing work of all elevated stations completed.
  • 2017-March: Work starts at 365 metres (1,198 ft) of elevated section at Duttabad after resettlement of affected household. Elevated section is to be made of steel girders.
  • 2017-March: Afcons nicknames the tunnel boring machine as Prerna and Rachna inspired from the names of daughter of their employee.
  • 2017-May 23: First TBM completes tunneling the East bound tunnel under the Hoogly river.
  • 2017-June 21: Second TBM completes tunneling the West bound tunnel under the river Hoogly.
  • 2017-June: Permission received from Archaeological Survey of India for construction of tunnel within 100 metres (328 ft) of three heritage buildings.
  • 2017-July: Tram depot at Esplanade shifted to facilitate construction of Metro Station.
  • 2017-July: People from 11 buildings in Brebourne Road evacuated in phased manner when the TBM's passes below these old buildings.
  • 2017-August: Mini-bus stand at Mahakaran shifted to facilitate the construction of underground station.
  • 2017-September: Panasonic Manufacturing and Zhuzhou CRRC Times Electric have been awarded contract of platform screen door on all 12 stations.
  • 2017-October: 365 m of elevated section at Duttabad completed using steel girders.
  • 2017-December: Tunnelling between Mahakaran station and Esplanade station ongoing.
  • 2017-December: KMRC declares first phase to be in between Sector V and IFA Salt Lake Stadium instead of Phoolbagan to be inaugurated in June 2018.
  • 2018-January: Demo coach arrives at IFA Salt Lake Metro Depot. People question its use.
  • 2018-February 12: Metro general manager Mr. Ajay Vijayvargiya again postpones opening of first phase from June to September 2018.[20]
  • 2018-February: Constantly KMRC and Railways have postponed the opening of Phase 1 (the new deadline was before October 2018) and truncated the route for Phase 1 from Sealdah to Phoolbagan and now only till Salt lake Sec V.
  • 2018-March 23: First TBM named Prerna reaches Esplanade station completing the section from Howrah Maidan to Esplanade. This tunnel will be used by Howrah bound tunnel.
  • 2018-March 31: BEML delivers first metro train set to KMRC. The train sets to arrive in 20 days. Second train set will be delivered in the end of April.
  • 2018-April 5: Second TBM completes boring of second tunnel between Howrah Maidan and Esplanade station.
  • 2018-April 20: First metro rake arrives at IFA Salt Lake Depot.[21]
  • 2018-May 1: The second metro rake from BEML arrives.
  • 2018-June 20: First test ride inside depot starts.[22]
  • 2018-June 27: Work at Esplanade Sealdah tunnel drilling stalled due to existing steel structure in North South Line.
  • 2018-July 4: First trial run between Central Park and Sector V.[23]
  • 2018-July: October deadline of inauguration announced
  • 2018-August: Tunneling from Esplanade to Sealdah suspend due to detection of underground steel beams of Line 1.
  • 2018-August: Due to fund crunch & other issues, initial run postponed to March 2019.
  • 2018-August 30: Installation of Platform Screen Doors started in Karunamoyee and Central Park stations.
  • 2018-October: Trial Runs conducted between Sector V and IFA Salt Lake Stadium stations.
  • 2018-November: Trial Runs conducted by RDSO between Sector V and IFA Salt Lake Stadium stations.
  • 2018-November: Speed limit of trains plying in Line 1 decreased for removing steel beams.
  • 2018-November: Small tunnels being made using NATM method at Esplanade to remove steel beams left during North-South Metro construction in 1980s.[24][25]
  • 2018-December: Issues in software detected.
  • 2019-January-25: Tunneling on Esplanade Sealdah section begins. TBM named Chandi starts its initial push from Esplanade station. It will take 12–15 months to complete the tunnelling.
  • 2019-February-19: Second boring machine named Urvi starts tunnelling from Esplanade station.
  • 2019-February: Fare chart released.
  • 2019-April: Glitches detected during software integration while negotiating curves in line (First phase of the project till Salt Lake Stadium). Glitches have been fixed, and the signalling and communication firm Ansaldo STS has recommended 1000 hours of trial run before commencement of service.[26]
  • 2019-April: Inauguration delayed again. Misses April end deadline. New deadline June
  • 2019-May: Tunnel boring machine Urvi and Chandi after initial slow start progressing steadily towards Sealdah.
  • 2019-May-18: Gets RDSO clearance, and railway board nod.[27]
  • 2019-May-31: Electrification of third rail and trail run in underground section from IFA Salt Lake Stadium & Phoolbagan stations. It was the first time after 1995 that a metro trial was held underground.[28]
  • 2019-June-14: Inspection by fire department. Says, inadequate emergency exits in Bengal Chemical & IFA Saltlake Stadium stations.
  • 2019-June-15: Gets international safety nod from French certifier.
  • 2019-July-3: TBMs Rachna & Prerna successfully taken out from Curzon Park
  • 2019-July-7: Fire dept. assures temporary permission to the 2 stations, Bengal Chemical & IFA Saltlake Stadium stations. NOC to be valid for a year.[29]
  • 2019-July-18: Operations handed over to Metro Railway, Kolkata from Kolkata Metro Rail Corporation[30]
  • 2019-July-23: CRS inspection and safety audit for initial run. But, Fire department delayed the NOC.
  • 2019-July-30: Opening rescheduled on September. Smart Card released. Employees of Metro Railway, Kolkata being trained by Kolkata Metro Rail Corporation.[31]
  • 2019-August-02: CRS nod given, with 3 month validity of the clearance.[32]
  • 2019-August-12: India's deepest metro station, Howrah (30 m (98 ft)) finishes structural construction. It took 17 months.[33]
  • 2019-August-21: Trial till Sealdah crossover and 7-day mock trial started.[34]
  • 2019-September-01: Tunnel boring machine Chandi hits an aquifer causing massive soil settlement. Multiple buildings damaged, hundreds had to be moved to hotels[35][36]
  • 2019-October: By the mid of the month, the land was stabled by grouting and no more subsidence recorded. High Court ordered to stop tunneling, till further notice.
  • 2019-October-30: First round of service trials started.[32]
  • 2019 October: The first phase of this line was scheduled to start its first commercial run on 24 October, the same day when the first metro in India Kolkata Metro Line 1 was inaugurated in 1984
  • 2019-October-24: But the date was postponed to 7 November for some technical reasons.
  • 2019-October-30: Second round of service trials started.[32]
  • 2019 November-8: The Metro Authority was also unable to start its inaugural run on 7 November also. Failure drill started and performed till 18 November.[37][32]
  • 2019-November-26: Initial CRS deadline expired. 3 months grace period given. Valid till 29 February 2020.[38]
  • 2019-December: New opening date planned, i.e. December end. But, it is missed again.
  • 2020-January-07: High Court asks Railways to file report on resuming East- West Metro tunneling work, that was stopped after Bowbazar mishap.[39]
  • 2020-January-28: 2022 is the revised deadline of the entire corridor.[40]
  • 2020-February-03: Last group of 2 families moved to new flats from hotel after the Bowbazar mishap.[41] Final inauguration date announced. Rail Minister to flag off services on 13 February.[12]
  • 2020-February-11: Last trails, known as 'time-table trials' conducted.[42] High Court gives nod to resume construction in Bowbazar area.[43]
  • 2020-February-13: First phase from Salt Lake Sector V to IFA Salt Lake Stadium inaugurated.
  • 2020-February-14: Commercial services start.[42]
  • 2020-February-28: Tunneling resumed in Bowbazar area, and cracks redevelop in buildings.[44]
  • 2020-March: All operations and constructions stopped due to country-wide coronavirus lockdown.
  • 2020-June-18: IFA Salt Lake Stadium to Phoolbagan section gets CRS nod.[45]
  • 2020-August-10: India's deepest evacuation shaft on Strand Road gets completed.[46]
  • 2020-October-2: the Vidyapati Setu (Sealdah Flyover) has been closed by Kolkata Police due to the work of making tunnel by TBM under this dilapidated bridge has started.[47]
  • 2020-October-4: Services extended up to Phoolbagan.[48]
  • 2020-October-8: Indian Football Association, West Bengal has announced that the name of Salt Lake Stadium Metro Station has renamed as IFA Salt Lake Stadium.[49]
  • 2020-October-9: Work on the eastbound tunnel (towards Salt Lake Sector V) has been completed, TBM Urvi entered the under Construction Sealdah metro station on around 5 PM.[50] Earlier, on 4 October 2020 the Vidyapati Setu (Sealdah Flyover) reopened by Kolkata Police for vehicular traffic as the tunneling work has completed 13 hours before.[51]
  • 2021-January-4: TBM Urvi starts bridging the last 800 m (2,600 ft) gap of E-W Metro tunnel from Sealdah to Esplanade.[52]
  • 2021-May-15: TBM Urvi reaches Bowbazar shaft. Last tunneling section of the entire project completed.[19]
  • 2022-July-12: Services extended up to Sealdah.[53]
  • 2023-April-21:Kolkata Metro runs first underwater passenger trial run between Howrah Maidan and Esplanade.[54]

Tunneling and Bowbazar issue (Phase 2)

The section between Sealdah and Mahakaran station was realigned due to the objection of Government of West Bengal. Work at Howrah Maidan has started in March 2016. The section between Howrah Maidan and Esplanade station has been built by the Afcons – Transtonnelstroy JV team, two tunnel boring machines from Herrenknecht are being used to dig the tunnel. This section passes through the river Hooghly for a distance of 520 metres (1,710 ft). The section under the river is at a depth of 30 metres (98 ft) (roof to ground distance) whereas the average roof to ground distance is 17 metres (56 ft). The Howrah station on the west side of the river will be at a depth of 30 metres (98 ft). Tunnelling started from Howrah Maidan side, by Afcons. On 23 May 2017 one of the TBM named Rachna completed the tunneling under the Hoogly river in 36 days. The other TBM named Prerna also completed the tunnelling work under the river on 21 June 2017. There were some concerns during tunneling under Brabourne road as the tunnel would pass within 100 metres (330 ft) of heritage structures and there were also many old and dilapidated buildings in this section. KMRC received permission from Archaeological Survey of India in June 2017. Residents and shops in the old building were temporarily shifted and the buildings were reinforced before construction of tunnel. Construction of tunnel to Mahakaran station was completed in November 2017. For the Mahakaran-Esplanade section, tunneling has been completed on 23 March 2018. The other tunnel has also been completed by April. In these sections, above ground retail buildings have been shifted in a phased manner prior to tunnelling. The Esplanade – Sealdah section will be executed by ITD Cementation JV and started in May 2018. The Esplanade - Sealdah section has been delayed due to the detection of steel beams that were left during the construction of the first line of Kolkata Metro. The NATM tunneling method is being used to cut the steel beams. This work was concluded in February 2019 and then the main tunneling commenced. In September 2019, when TBM Chandi reached Bowbazar, it hit a massive aquafier, less than a kilometer from its destination, Sealdah. It led to soil subsidence and many buildings collapsed. The residents were shifted to hotels and apartments. Later the land was stabilized by grouting and the unsafe buildings were pulled down. High Court ordered to stop further tunneling immediately. Due to the incident the tunneling was delayed, thus delaying the overall deadline for one year. It was planned that the affected TBM would be taken out from the incident site, and the second one will complete the tunneling till Sealdah. Then it will be reversed again to complete the remaining portion of the tunnel of first TBM.[55] In mid-February 2020, High Court asked to resume the work in the affected area.

Working cautiously, coupled with some more subsidences, all tunnelling works, retrieval of the two TBMs and closure of all shafts were completed in April 2023. The Metro authorities deemed the Esplanade-Sealdah section (particularly the incomplete, caved-in west-bound tunnel that took long to complete), to be challenging and impossible to finish by 2023.[56] So, they planned to run trains (brought via completed east-bound tunnel) over a truncated Esplanade-Howrah Maidan section that is almost complete. For this, the authorities brought two racks from Central Park depot to Esplanade metro station on 9 April 2023.[57] They were brought via a battery-powered, hybrid locomotive as Esplanade-Sealdah section is not electrified. From there, the wheels of railways rolled for the first time below the Hoogly river when, both trains arrived at Howrah Maidan station on 13 April 2023. Currently, trial runs are ongoing over this truncated section, after which the authorities expect this section to be opened for commercial operations in December 2023, while they plan to complete the remaining construction work in Esplanade-Sealdah stretch by the same month.[58][59]

List of stations (East to West)

Line 2 (Green Line)
No. Station Name Location Phase Status Opening Date Connections Layout Platform Type Depot Notes
EnglishBengali
1Teghoria / Haldiramতেঘরিয়া / হলদিরামTeghoria 3Planned Orange Line (Under construction)

Haldiram's Bus Stop

Teghoria Minibus Stand

Kaikhali Bus Terminus

Elevated Side -
2RaghunathpurরঘুনাথপুরBaguiati Bramhachari Ashram Bus Stop
3Baguiatiবাগুইআটি Baguiati Jora Mandir Bus stop

Baguiati Bus Stand

4 Dum Dum Park দমদম পার্ক Dum Dum Park Dum Dum Park Bus Stand
5 Kestopur কেষ্টপুর Kestopur Keshtopur Bus Stop

Nayapatty Bus Stop

6Salt Lake Sector Vসল্টলেক সেক্টর V Salt Lake1AOperational 14 February 2020 Orange Line (Under Construction)

Wipro Bus Stop

Salt Lake Bus Depot

Elevated Side Central Park Depot Located near IT Hub of Kolkata
7Karunamoyee করুণাময়ী

Korunamoyee Bus Terminus (WBTC,CTC,SBSTC,NBSTC)

International bus terminus. First station in Kolkata to have PSDs
8Central Park সেন্ট্রাল পার্ক Bikash Bhawan Bus Stand
Sech Bhawan Bus Stop
Serving Central Park
9City Center সিটি সেন্টার City Center City Centre Bus StopLocated near Bidhannagar College
10Bengal Chemical বেঙ্গল কেমিক্যাল

Bengal Chemical Bus Stop

Mani Square Bus Stop

11Salt Lake Stadium সল্টলেক স্টেডিয়াম Salt Lake Stadium Apollo Hospital Bus Stop

Kadapara Bus Stop

Swabhumi Bus Stop

Serving Vivekananda Yuba Bharati Krirangan
12PhoolbaganফুলবাগানPhoolbagan 1B 4 October 2020 Phoolbagan Minibus Stand

Phoolbagan Bus Stop

Gurudas College

Underground IslandFirst underground station of the line. Also after 25 years.
13Sealdah শিয়ালদহSealdah 2A 11 July 2022 Sealdah Station

Sealdah Bus Stop

NRS Bus Stop

Both side & island Interchange with local suburban and national rail services
14Esplanadeএসপ্ল্যানেডEsplanade 2BUnder construction Blue Line (operational)

Purple Line (Under Construction)

Esplanade Bus Station(WBTC,SBSTC,NBSTC)

Esplanade Tram Depot

Underground Both side & island - International Bus Terminus. Also known as Dharmatala / Chowringhee
15MahakaranমহাকরণBBD Bagh

B.B.D. Bagh Tram Depot

B.B.D. Bagh Bus Stop

Island
16Howrah হাওড়া Howrah

Howrah Station

Howrah Station Bus Terminus

ferry/water interchangeHowrah Station Jetty

Both side & islandDeepest station in India.[60] Interchange with local suburban and national rail services
17Howrah Maidan হাওড়া ময়দান Howrah Maidan

Howrah Maidan Bus Stand

Sarat Sadan Bus Stop

IslandServing Howrah Municipal Corporation Stadium

Inauguration

1st phase

On 3 February 2020, the final inauguration date was revealed. After 11 years, since the construction started, the first phase of the line was inaugurated on 13 February by Union Minister of Railways Piyush Goyal, with commercial services to start the very next day. The service will start from 8 am and ends at 8 pm, with 37 pairs of services a day. 5 rakes would run at a frequency of 20 minutes. Dipak Kumar drove the first train.[42][61][39][62][63]

In October 2021, services up to Phoolbagan were extended as a part of Phase 1A.

2nd Phase

On 14 July 2022, the first commercial run from Sealdah metro station was made, as a part of Phase 2.[64]

Infrastructure

Stations

All the stations in this line will be equipped with Platform Screen Doors to keep people away from the tracks.[65] Mott MacDonald is the detailed design consultant for all the elevated stations, whereas Lee Harris Pomeroy Architects have designed all the underground stations. Out of the 6 underground stations, 3 will be built by ITD Cementation, a part of Italian-Thai Development Public Company and the other 3 will be built by Afcons including the 520 meters underwater stretch. All the elevated stations will be built by Kolkata based Simplex Infrastructure ltd.[66][67]

Escalators and elevators

Ninety escalators and forty elevators are to be installed at different levels in the line to facilitate smooth mobility of passengers including physically challenged & aged persons. LOA for installation of forty-one escalators and twenty-six elevators for 8 nos. stations of Phase-I has been awarded.[68]

Tunnel Ventilation System (TVS)

TVS shall provide a means to control smoke flow and ensure safe evacuation of passengers in case of fire as well as maintain an acceptable environment in the tunnel and station track way. Tender for the TVS was invited and the bids of eligible tenderers are being evaluated.

Platform Screen Doors at the Salt Lake Stadium metro station

Platform Screen Doors (PSDs)

PSDs are a system of full height/half height motorized sliding doors that provide controlled access to the trains and protect the platform edge. PSD work for 6 elevated and 2 underground stations have been completed.

Electrification, Signaling & Automatic Fare Collection

The line will have two types of signaling equipment supplied by ANSALDO STS . One will feature cab signaling and continuous automatic train control with automatic train protection. The other signaling equipment will include an integrated system featuring fiber optic cable, SCADA, radios and a PA system. The line will also have a train information system, control telephones and a centralized clock system. Contract for AFC works has been awarded to M/s. Indra Sistemas SA (Spain).[68]

Operations

Unlike the north–south corridor, the east–west metro will run from 8 am to 8 pm at a frequency of 1.5 minutes during peak hours and 5 minutes during non-peak hours.[69] But in phase 1 operations, the frequency will be 20 minutes, and each will stop for 20 seconds in each station.[70]

Rolling stock

The interior of the East West Metro rake

CAF in collaboration with Melco was to supply 14 trains for this line.[71] The 14 rakes were acquired at a cost of approximately €110m[6] 6 billion (US$75 million). Each rake will compose of 6 coaches having a capacity of 2068 people per train.[71] The maximum speed of the train will be 90 km/h (56 mph). The first lot of trains was to be manufactured in Spain and imported to Kolkata in November 2014. The next lot was to be manufactured in India. However, the tender was cancelled by KMRC due to technical reasons[72] and excessive delay in project. And a re-tender was issued in July 2015. BEML emerged as the only bidder in the fourth round of bidding for providing rolling stock.[73] Thus, the contract for providing the rakes was awarded to BEML.[74] BEML have earlier provided rakes for Delhi Metro, Bengaluru Metro & Jaipur Metro. Fourteen rakes, each with six coaches, were ordered. Out of Fourteen, eleven rakes have already been received by KMRC.

Proposed Extensions

The West Bengal government have proposed an extension to the East–West Metro line. In this proposal the East-West Metro will be connected again to the Dum Dum Airport-New Garia Metro in Teghoria (Haldiram). According to this proposal the East-West Metro will have 3 terminating stations at Howrah Maidan, Sector V and the proposed Teghoria station. In Teghoria, it will be connected to the NSCBI Airport-New Garia metro route (VIP Road Station) and interconnection facilities will be present. It was previously planned that the extension and the present route would converge at the Central Park Station.[75] But now the plan is changed and it is decided to extend the line directly from Salt Lake Sector V Station.[76] The proposed extension is under study and it will need several clearances before being implemented. 10 km East-West Metro extension project from Howrah Maidan to Santragachi bus terminus had been proposed. RITES, the implementing agency for this project planned to start work on the corridor early in 2017.[77]

See also

References

  1. "New System Map of Kolkata Metro". Archived from the original on 5 September 2019. Retrieved 20 July 2019.
  2. "East-West load on struggling Metro". Archived from the original on 23 July 2019. Retrieved 23 July 2019.
  3. Chakraborty, Ajanta (15 February 2020). "On Valentine's Day, Kolkata falls in love with East-West Metro as trains start rolling out". The Times of India. Archived from the original on 18 February 2020. Retrieved 28 February 2020.
  4. Chakraborty, Ajanta (29 February 2020). "'World-class' East-West Metro still wows Kolkata but crowd thins in 14 day". The Times of India. Archived from the original on 29 February 2020. Retrieved 29 February 2020.
  5. "Kolkata East West Metro will ferry 1 million people a day by 2035: Railway official". Archived from the original on 25 July 2019. Retrieved 25 July 2019.
  6. "CAF to supply Kolkata metro trains". Archived from the original on 16 August 2014. Retrieved 11 October 2013.
  7. "Kolkata Metro Rail Corporation Ltd".
  8. "Kolkata Metro's TBM S639 Crosses Halfway Mark Under Hooghly". The Metro Rail Guy. 5 May 2017. Retrieved 14 February 2023.
  9. Howrah—Sealdah Metro Link Update || Kolkata East-West Metro || MetroRail Blog, archived from the original on 6 October 2019, retrieved 12 September 2019
  10. "India's first underwater train to be operational by 2023 in Kolkata - Kolkata Metro Rail Corporation train".
  11. "Kolkata Metro gets its second corridor after 36 years. See photos". 13 February 2020. Archived from the original on 14 February 2020. Retrieved 14 February 2020.
  12. "১৩ ফেব্রুয়ারি চালু হচ্ছে ইস্ট-ওয়েস্ট মেট্রো, জেনে নিন ভাড়া তালিকা..." bengali.news18.com (in Bengali). 3 February 2020. Archived from the original on 3 February 2020. Retrieved 3 February 2020.
  13. "East-West Metro gets new boss". The Telegraph. Archived from the original on 2 November 2012. Retrieved 1 July 2011.
  14. "East-West Metro's route likely to change". Business Standard.
  15. Pramanik, Abhishek Law, Ayan (17 July 2012). "Kolkata Metro inks purchase pact for coaches for East-West corridor". Archived from the original on 27 September 2013. Retrieved 5 August 2012.{{cite web}}: CS1 maint: multiple names: authors list (link)
  16. "Kolkata: New Sealdah metro station is all set to be inaugurated today, commercial operations to start on July 15". 11 July 2022.
  17. Hossain, Shaheryar (1 December 2020). "Outer structure of Esplanade Metro Station completed". www.millenniumpost.in. Retrieved 20 May 2021.
  18. Ajanta Chakraborty (24 February 2020). "Kolkata: After work for 29 months, station structure ready at Mahakaran | Kolkata News - Times of India". The Times of India. Retrieved 20 May 2021.
  19. Ajanta Chakraborty (16 May 2021). "12 years and several stumbling blocks later, E-W Metro tunnelling work is complete | Kolkata News - Times of India". The Times of India. Retrieved 20 May 2021.
  20. "Metro to connect Sector V to Salt Lake Stadium soon". Millennium Post. Archived from the original on 28 February 2018. Retrieved 28 February 2018.
  21. "First look at East-West Metro rake". The Telegraph. Archived from the original on 8 May 2018. Retrieved 8 May 2018.
  22. "East West Metro's six-car rake takes first test run at depot". Times of India. Archived from the original on 16 July 2018. Retrieved 21 June 2018.
  23. "E-W Metro ready for trial run between Central Park & Sec V". Times of India. Archived from the original on 27 July 2018. Retrieved 4 July 2018.
  24. "Calcutta Metro's slow-mo stretch". The Telegraph. Archived from the original on 20 December 2018. Retrieved 20 December 2018.
  25. "Another eight joists to be removed before TBMs restart". Times of India. Archived from the original on 20 December 2018. Retrieved 20 December 2018.
  26. "Firm insists on 1000 hours of trial for glitch-free Metro". The Telegraph. Archived from the original on 31 May 2019. Retrieved 31 May 2019.
  27. Chakraborty, Ajanta (18 May 2019). "Kolkata: East-West Metro gets rail board nod". The Times of India. Archived from the original on 29 September 2019. Retrieved 3 September 2019.
  28. "Kolkata: Underground trials at Phoolbagan on Friday". The Times of India.
  29. Chakraborty, Ajanta (7 July 2019). "Two East-West Kolkata Metro stations get fire nod for a year". The Times of India. Archived from the original on 18 July 2019. Retrieved 7 July 2019.
  30. "East-West load on struggling Metro". www.telegraphindia.com. Archived from the original on 23 July 2019. Retrieved 24 July 2019.
  31. Chakraborty, Ajanta (30 July 2019). "Post fire nod, East-West eyes pre-Puja start to services". The Times of India. Archived from the original on 15 August 2019. Retrieved 30 July 2019.
  32. Chakraborty, Ajanta (17 November 2019). "East-West Metro races against time to meet November 30 deadline". The Times of India. Retrieved 3 February 2020.
  33. Chakraborty, Ajanta (13 August 2019). "India's deepest Metro station comes up 30m below Howrah railway station | Kolkata News - Times of India". The Times of India. Archived from the original on 2 September 2019. Retrieved 13 August 2019.
  34. Chakraborty, Ajanta (21 August 2019). "Kolkata East-West Metro starts its underground trial runs till Sealdah station". The Times of India. Archived from the original on 29 September 2019. Retrieved 3 September 2019.
  35. "Kolkata: Homes emptied after cracks in Calcutta's Bowbazar". The Telegraph. Archived from the original on 3 September 2019. Retrieved 17 September 2019.
  36. "18 buildings damaged as Kolkata Metro tunnel-borer 'hits aquifer'". Times of India. 2 September 2019. Archived from the original on 5 September 2019. Retrieved 17 September 2019.
  37. "Railways Mulling to Flag-off Kolkata Metro East-West Corridor on 24 October". News18.com. 24 October 2019. Archived from the original on 22 October 2019. Retrieved 12 November 2019.
  38. Chakraborty, Ajanta (26 November 2019). "Kolkata Metro asks for extension of Eest-West's November 30 deadline". The Times of India. Archived from the original on 29 November 2019. Retrieved 3 February 2020.
  39. Singh, Neha (5 February 2020). "Kolkata East-West Metro is all set to begin Operations on 13th February". Metro Rail News. Archived from the original on 5 February 2020. Retrieved 5 February 2020.
  40. "India's first underwater metro expected to be complete by March 2022". www.businesstoday.in. 29 January 2020. Archived from the original on 30 January 2020. Retrieved 3 February 2020.
  41. Chakraborty, Ajanta (3 February 2020). "East-West tunnelling disaster: Last group of seven moves to new flats from hotel". The Times of India. Archived from the original on 4 February 2020. Retrieved 3 February 2020.
  42. Chakraborty, Ajanta; Gupta, Jayanta (5 February 2020). "8am on Valentine's Day; Your date with East-West Metro". The Times of India. Archived from the original on 5 February 2020. Retrieved 5 February 2020.
  43. "Kolkata Metro: High Court gives nod for resumption of East-West corridor work". Livemint. 11 February 2020. Archived from the original on 12 February 2020. Retrieved 11 February 2020.
  44. "Cracks in houses on East-West Metro tunnel route". www.telegraphindia.com. Archived from the original on 28 February 2020. Retrieved 28 February 2020.
  45. Chakraborty, Ajanta (18 June 2020). "West Bengal: East-West Metro's Phoolbagan extension gets CRS nod". The Times of India. Retrieved 8 July 2020.
  46. Chakraborty, Ajanta (10 August 2020). "Good news in lockdown times: Metro completes India's deepest air shaft". The Times of India. Retrieved 10 August 2020.
  47. Mondal, Suvodip (1 October 2020). "Agencies seek Friday-Sunday Sealdah flyover closure for East-West Metro tunnelling". The Times of India.
  48. "Phoolbagan Metro station starts Monday". www.telegraphindia.com. Retrieved 4 October 2020.
  49. "The Metro Station of Salt Lake Stadium will be known as IFA Salt Lake Stadium". Facebook.
  50. "Tunnel boring machine reached Sealdah metro station" (in Bengali).
  51. "Sealdah flyover opened to traffic 13 hours early". The Times of India.
  52. Mondal, Biswadeep (5 January 2021). "Urvi starts bridging last 800m gap of E-W Metro tunnel". Times of India.
  53. Nag, Jayatri. "Sealdah station of Kolkata metro inaugurated". The Economic Times. Retrieved 14 July 2022.
  54. TODAY "Kolkata Metro runs first underwater passenger trial run between Howrah Maidan and Esplanade". {{cite news}}: Check |url= value (help)
  55. "East West Metro: Latest News, Videos and Photos of East West Metro | Times of India". The Times of India. Archived from the original on 21 February 2020. Retrieved 3 February 2020.
  56. "Cave-in zone: Survey focus on strengthening Kolkata's East-West Metro tunnels". The Times of India. 12 February 2023. ISSN 0971-8257. Retrieved 14 April 2023.
  57. "Kolkata Metro runs through tunnel below Hooghly, first in India to complete under-river journey". The Indian Express. 13 April 2023. Retrieved 14 April 2023.
  58. "East-West Metro's under-river trial starts on Howrah-Esplanade stretch". The Times of India. 14 April 2023. ISSN 0971-8257. Retrieved 14 April 2023.
  59. Service, Statesman News (17 April 2023). "Two tunnels in remaining stretch of East-West Metro expected to be ready by December". The Statesman. Retrieved 17 April 2023.
  60. "Howrah metro station is India's deepest subway". Constro Facilitator. 20 August 2019. Archived from the original on 20 February 2020. Retrieved 20 February 2020.
  61. "Kolkata Metro: East-West Metro railway set to roll out on 13 February". Livemint. 4 February 2020. Archived from the original on 5 February 2020. Retrieved 5 February 2020.
  62. "আজ উদ্বোধন ইস্ট-ওয়েস্ট মেট্রোর". Anandabazar Patrika (in Bengali). 13 February 2020. Archived from the original on 13 February 2020. Retrieved 13 February 2020.
  63. Chakraborty, Ajanta (12 February 2020). "West Bengal: This is how your journey through Salt Lake will be from Valentine's Day". The Times of India. Archived from the original on 14 February 2020. Retrieved 20 February 2020.
  64. "Kolkata takes a first look at Sealdah Metro station after inauguration". www.telegraphindia.com. Retrieved 14 July 2022.
  65. "KMRC=2013-07-22". Archived from the original on 4 June 2013. Retrieved 22 July 2013.
  66. "Mott MacDonald is detailed design consultant on Salt Lake City Stations". Archived from the original on 26 July 2010. Retrieved 22 July 2013.
  67. "Railway Technology". Archived from the original on 4 August 2013. Retrieved 22 July 2013.
  68. "REVIEW OF ANNUAL REPORT AND AUDITED ACCOUNTS OF KOLKATA METRO RAIL CORPORATION LIMITED (KMRCL) FOR THE YEAR 2016-17" (PDF). Archived (PDF) from the original on 9 December 2019.
  69. "Kolkata East West Metro". The Times of India. Retrieved 22 July 2013.
  70. Chakraborty, Ajanta (11 June 2019). "Kolkata East-West Metro trains to ply every 20 mins, stop for 20 secs at each station". The Times of India. Archived from the original on 26 December 2019. Retrieved 28 June 2019.
  71. "CAF-Construcciones y Auxiliar de Ferrocarriles, your railway solutions". Archived from the original on 19 October 2014. Retrieved 11 October 2013.
  72. "Kolkata loses Spanish Rides". The Telegraph. Archived from the original on 30 January 2016. Retrieved 2 January 2016.
  73. "Bid saves Metro blushes". The Telegraph (Calcutta). Archived from the original on 31 January 2016. Retrieved 25 January 2016.
  74. "Central PSU wins Rs 900-crore Metro rake order". The Times of India. Archived from the original on 22 January 2016. Retrieved 25 January 2016.
  75. "East-West eyes easy route to airport". The Telegraph (Calcutta). Archived from the original on 19 February 2016. Retrieved 18 February 2016.
  76. "Kolkata Metro Official Map". Archived from the original on 5 September 2019. Retrieved 20 July 2019.
  77. "2017 start for Howrah EW Metro". The Times of India. Archived from the original on 4 December 2016. Retrieved 3 December 2016.
[1]
  1. 73 "Howrah metro station is India's deepest subway". nipani industries. 20 August 2019. Archived from the original on 20 February 2020. Retrieved 20 February 2020.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.