Kolkata Metro Line 3

Kolkata Metro Line 3 or the Purple Line is a line of the Kolkata Metro. The 6.5 kilometres (4.0 mi) stretch from Joka to Taratala of the 15.08 kilometres (9.37 mi) line was inaugurated on 30 December 2022.[3][4] The route spans 15.08 kilometres (9.37 mi) from Joka in the south, to Esplanade in the north with an extension of 3.39 kilometres (2.11 mi) to Diamond Park from Joka.[5] It will connect Kolkata Metro Line 1 at Park Street in central Kolkata and run in parallel up to Esplanade in central Kolkata where it will connect Kolkata Metro Line 2 also. Line 3 is being built by Rail Vikas Nigam Limited.

Kolkata Metro Line 3

Diamond Park - Esplanade Metro
Kolkata Metro Line 3 viaduct along the Diamond Harbour Road
Overview
StatusPhase 1 - Operational

Phase 2 - Under Construction

Phase 3 - Planned
OwnerMetro Railway, Kolkata
Line number3
LocaleIndia Kolkata, India
Termini
Connecting linesBlue Line Green Line
Stations6 (operational)
WebsiteIndian Railways
Service
TypeRapid transit
SystemKolkata Metro
Operator(s)Metro Railway, Kolkata
History
Opened30 December 2022 (2022-12-30)
Technical
Line length18.47 kilometres (11.48 mi) Operational: 6.5 kilometres (4.0 mi)
Under Construction: 8.58 kilometres (5.33 mi)
Planned: 3.39 kilometres (2.11 mi)[1]
Number of tracks2
CharacterElevated and Underground
Track gauge5 ft 6 in (1,676 mm) broad gauge
Electrification750 V DC using third rail[2]
Operating speed80 km/h (50 mph) (designed)
Route map

Esplanade
Park Street
Victoria
Tolly Canal
Khidirpur
Mominpur
Majerhat
Taratala
Behala Bazar
Behala Chowrasta
Sakher Bazar
Thakurpukur
Joka
IIM Calcutta
Diamond Park

Development

Prime Minister Narendra Modi inaugurates the Joka-Taratala stretch of Purple Line of Kolkata Metro on December 30, 2022.

It is partially elevated and partially underground: around 8.5 kilometres (5.3 mi) of the project will be elevated and the rest 6.32 kilometres (3.93 mi) of the metro line will be underground.[4] The project is getting delayed due to nonavailability of land for the construction of train depot at Joka. In 2019, RVNL was given the land required for building the depot and the construction for its boundary wall and land development started in February 2019.[6] Tenders for its construction and plant & machinery were invited in April 2020.[7]

Construction was further delayed in September 2018 due to the Majerhat Bridge collapse, the metro was being built right next to the bridge.

Tender for Majherhat to Esplanade underground section has been floated in 1st week of December 2019.

By 15 September 2022, the stretch from Joka to Taratala has been fully constructed and electrification has been done. Testing trials are underway from Joka to Taratala using the old decommissioned Metro Rakes. Eventually in service there will be new air conditioned metro rakes. The stretch from Majerhat to Esplanade is under construction.

Prime Minister Narendra Modi inaugurated the Joka-Taratala stretch, including Joka metro station of Kolkata Metro's Purple Line on 30 December 2022 in the presence of West Bengal Chief Minister Mamata Banerjee and Indian Railway Minister Ashwini Vaishnaw. Some students from schools especially St Thomas Boys School, whose premises are utilised for planned Khidirpur metro station in this stretch, were granted the rare opportunity to be the first ones to ride in this Joka-Taratala stretch after the inauguration.[8][9][10]

List of stations

The work has been sanctioned in 2010-11 for the new Metro line from Joka to B.B.D. Bagh for a length of 16.72 km (10.39 mi) at an anticipated cost of Rs. 2619.02 Crores. But, later the route was shortened and planned to terminate at Esplanade. A separate Depot is under construction in Joka. It is being built by RVNL and the tender has gone to Simplex Infrastructures. The extension of this line to IIM and Diamond Park for 2 km (1.2 mi) has been sanctioned in the Budget of 2012–13 at a cost of Rs. 294.49 Cr. The execution of this work has been entrusted to RVNL.

There are 3 phases in this line-

  • Joka to Taratala (Operational)
  • Taratala to Esplanade (Under construction)
  • Diamond Park to Joka (Planned)
Line 3 (Purple Line)
No. Station Name Location Phase Opening Connections Layout Coordinates Notes
English Bengali
1 Diamond Park ডায়মন্ড পার্ক Joka 3 Planned Vivekananda Mission School Bus Stop Elevated
2 IIM আইআইএম
3Joka জোকা 1AOperational Joka bus Depot

Diamond Park Bus Stop

Also known as Diamond Park
4Thakurpukur ঠাকুরপুকুর Thakurpukur

Thakurpukur Police Station Bus Stop

Thakurpukur Bazar Bus Stand

5Sakherbazar সখেরবাজার Behala

Thakurpukur Bus Depot

Silpara Bus Stop

Behala Sakherbazar Minibus Stand

Kadamtala Bus Stand

Also known as Silpara
6Behala Chowrasta বেহালা চৌরাস্তা

Behala Chowrasta Bus Stand

7Behala Bazar বেহালা বাজার

Behala Bazar Bus Stop

8Taratala তারাতলা Taratala

Ajanta Cinema Bus Stop

Taratala Bus Stand

Also known as Pathakpara
9Majerhat মাঝেরহাট Majerhat 1B Under Construction Majerhat Station

DH Road Mint Bus Stop

Majherhat Gurudwara Bus Stop

10Mominpur মোমিনপুর Mominpur Mominpore Bus Stop
11Kidderpore খিদিরপুর Kidderpore 2 Khidirpur Station

Khidderpore Crossing Tram Stop Khidderpore Bus Stop

Underground
12Victoria ভিক্টোরিয়া Maidan Hastings Tram Stop

Victoria Memorial Bus Stop

PG Hospital Bus Stop

Birla Planetarium Bus Stop

Also known as Hastings
13Park Street পার্ক স্ট্রিট Park Street Park Street Bus Stop

Blue Line

14Esplanade এসপ্ল্যানেড EsplanadeBlue Line

Green Line (Under Construction)

Esplanade Bus Station(WBTC,SBSTC,NBSTC)

Esplanade Tram Depot

International Bus Terminus. Also known as Dharmatala / Chowringhee

See also

References

  1. "Kolkata Metro Map".
  2. "CAF to supply Kolkata metro trains". Railway Gazette. 9 September 2012. Retrieved 6 September 2018.
  3. "Kolkata Metro: First glimpse of Joka-Taratala route in pics". mint. 30 December 2022. Retrieved 30 December 2022.
  4. Bandyopadhyay, Krishnendu; Chakraborty, Ajanta (10 June 2019). "Kolkata: Work on fast track as East-West Metro eyes new links in next two years | Kolkata News - Times of India". The Times of India. Retrieved 28 June 2019.
  5. "Kolkata Metro Line 3".
  6. Bandyopadhyay, Krishnendu (1 March 2019). "Work begins at Joka Metro depot, wall built | Kolkata News - Times of India". The Times of India. Retrieved 28 June 2019.
  7. "RVNL Invites Bids for Kolkata Metro Line-3's Joka Depot". The Metro Rail Guy. 28 April 2020. Retrieved 29 April 2020.
  8. "Kolkata Metro: First glimpse of Joka-Taratala route in pics". www.livemint.com. 30 December 2022. Retrieved 30 December 2022.
  9. "In-pics: Inaugration of Vande Bharat Express, Joka-Taratala Metro & more news from Kolkata". www.telegraphindia.com. Retrieved 31 December 2022.
  10. "Another school demands Metro route tweak". The Times of India. 18 December 2020. ISSN 0971-8257. Retrieved 2 May 2023.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.