Pink Line (Namma Metro)

The Pink Line of Namma Metro is under construction and will form part of the metro rail network for the city of Bangalore, Karnataka, India. The 21.25 km (13.20 mi) line connects Kalena Agrahara station (previously named Gottigere) on Bannerghatta road in the south with Nagawara station on Outer Ring road in the north. The Pink Line is mostly underground (13.92 km (8.65 mi)) but also has a 6.98 km (4.34 mi) elevated section and a 0.48 km (0.30 mi) at-grade (surface) section. There are 18 stations on the line of which 12 are underground and 6 are elevated.[2] Pink Line will have an interchange with the Purple Line at MG Road station. It will also have interchanges with the Yellow line at Jayadeva Hospital station and with the Blue Line at Nagawara. Both these lines are under construction.[3] The entire line is planned to open at the end of March 2025.[1]

Pink Line
Overview
Other name(s)Namma Metro
Native nameNamma Metro
OwnerBangalore Metro Rail Corporation Limited (BMRCL)
LocaleBangalore, Karnataka, India
Termini
  • Kalena Agrahara
  • Nagawara
Stations18
Websitebmrc.co.in
Service
TypeMetro
SystemNamma Metro
Depot(s)Kothanur
History
Planned openingMarch 2025 (2025-03)[1]
Technical
Line length21.25 km (13.20 mi)
Number of tracks2
CharacterElevated, At Grade and Underground
Track gauge1,435 mm (4 ft 8+12 in) standard gauge
Electrification750 V DC third rail
Pink Line Map (TBC)

Kalena Agrahara
Hulimavu
IIMB
JP Nagar 4th Phase
Jayadeva Hospital
Yellow Line
Under Construction
Tavarakere
Dairy Circle
Lakkasandra
Langford Town
National Military School
Mahatma Gandhi Road
Shivaji Nagar
Cantonment Bangalore Cantonment railway station
Pottery Town
Tannery Road
Venkateshpura
Kadugundanahalli
Nagawara
Blue Line
Under Construction

History

In 2007, as follow up to the Metro Phase that was about to begin construction then, RITES had recommended several mono-rail routes totaling 60 km (37 mi). These recommendations were made as Government of Karnataka requested a survey of feeder routes for Phase l of metro that was to begin construction. One of the routes was entirely on Bannerghatta Road from Bannerghatta National Park up to its northern end at Hosur Road (near Adugodi).[4] At that stage, Bannerghatta Road was not expected to have high growth and dense population, hence the recommendation for Monorail. However, by 2010 itself, it became apparent that Bannerghatta Road would need a higher capacity system than a monorail. Also, Karnataka government did not favor a monorail system and preferred expansion of the Metro system. Accordingly, for its Phase ll, BMRC had requested DMRC for a DPR for the route between[5] Bannerghatta to Yelahanka via:

  • Jayadeva Underpass, Hosur Road, Brigade Road, MG Road,
  • Kamaraj Road, Tannery Road, Nagavara Junction (along Outer Ring Road), Sahakara Nagar, Vidyaranyapura to Yelahanka.
  • Jayamahal Extension, RT Nagar, Nagavara Junction (along Outer Ring Road), Sahakara Nagar to Yelahanka.

The DPR had noted that the Metro Alignment may have to go underground after Jayadeva flyover (along Bannerghatta Road) up to Nagawara junction (along Outer Ring Road). The remaining portion could be elevated.

Planning

Since there were plans for a line along Outer Ring Road and also the possibility that a link to Airport may have to be routed along Airport Road (passing Yelahanka), BMRC opted to terminate the Pink Line in Phase ll at Nagawara.

Land requirement was estimated at 50 hectares (120 acres) and Karnataka Industrial Area Development Board (KIADB) was tasked with acquiring land on behalf of BMRC. A total of 690 trees were to be cut to build the line (438 trees for the elevated section and 252 trees for the underground stretch).[6]

On 14 July 2017, BMRC unveiled the alignment of the 13.92 km (8.65 mi) underground section of the line. The alignment included a modification from the original plan - Cantonment metro station had been proposed to be constructed on Indian Railways land next to Cantonment railway station. Due to technicalities (steep gradient between Shivajinagar and Cantonment, sharp curve past the old location of Cantonment Station, construction below built-up structures, difficulty acquiring land and very high costs of demolishing several properties in the area), BMRC opted to shift Cantonment Metro Station.[7] Cantonment Metro Station would instead be built under a playground belonging to Bruhat Bengaluru Mahanagara Palike (BBMP), near Bamboo Bazaar.[3][8][9]

This was resented by sections of the public as the new location would be further away from the entrance of Cantonment station. SWR is however planning new suburban platforms on railways land that is towards the Metro station. A skywalk or pedestrian subway is being planned to connect the Metro station to Cantonment Railway Station.[10]

The MG Road station on the Pink Line is to be located under Kamaraj Road and will serve as an interchange station with the Purple Line.[3]

Tendering

Due to long underground section with tunneling in difficult geology, the cost of the Pink Line was expected to be high. Total cost estimates for the line were 11,014 crore (US$1.4 billion) in March 2017 (most expensive line in Phase ll).[11][12] BMRC initially floated tenders for the construction of the 13.9 km (8.6 mi) underground section in four packages during June 2017. However, all bids received were too high (nearly 70% higher).[13][14]

Initial

Tendering

Estimated

by BMRC

Bids Received (₹ /crores)
L&T ITD-Cem Afcons Gülermak
Package-1 1268.90 2337.93 2223.40^ 2311.34
Package-2 1325.97 2333.71 2349.70 2311.11 2219.86^
Package-3 1334.83 2237.58^ 2373.35 2361.32 2341.32
Package-4 1117.86 1872.47^ 2010.95 1994.41
Total 5047.56 4571.29* 8933.45 8906.78 8866.93
*L&T bid for only two packages; ^Lowest Bid.

Since bids were too high, all tenders for the underground section had been canceled by BMRC on 26 March 2018. There was speculation of collusion as bids were similar and each bidder had quoted lowest for one package, thus all four might get to be awarded one package each.

The second round of tendering resulted in bids that were closer to estimates by BMRC and were awarded to three firms during February–November period, 2019. One of the firms (L&T) won two bids.[15] The total awarded tunneling tenders for the underground sections was ₹5,925.95 crores (appx US$812 million).

2nd Tendering Section Length Successful Bid /Cost Contractor Award
Reach 6 UG Pkg-1 South Ramp /Dairy Circle - Langford Town 3.65 km ₹1,526.33 crore (US$218 million) Afcons 06 Nov 2019
Reach 6 UG Pkg-2 Rashtriya Military School - Shivajinagar 2.76 km 1,329.14 crore (US$170 million) L&T 28 Feb 2019
Reach 6 UG Pkg-3 Shivajinagar - Tannery Road 2.88 km 1,299.23 crore (US$160 million) L&T 28 Feb 2019
Reach 6 UG Pkg-4 Tannery Road - Nagawara North Ramp 4.59 km ₹1,771.25 crore (US$253 million) ITD-Cem 06 Nov 2019
Total South Ramp /Dairy Circle - Nagawara /North Ramp 13.9 km ₹5,925.95 crore (US$841 million)

Construction

Elevated Section

In March 2017, BMRC had floated tender for construction of the 7.5 km (4.7 mi) elevated section between Kalena Agrahara (previously Gottigere) and Tavarekere (previously Swagat Cross) stations for construction of the elevated section of Pink Line with viaduct, five stations and depot entry line to Kothanur depot.[16][17] The tender was awarded to Simplex Constructions for 578.70 crores on 8 September 2017.[18]

Due to very slow progress by Simplex, their tender was canceled and a fresh tender was called for the remaining works in February 2021. GR Infra was the lowest bidder and the tender was awarded to them in July, 2021.

Underground Section

Pre-tunneling construction work and piling for stations began in May 2019 by L&T. Tunnel boring using TBMs began in August–September 2020 by L&T with two TBMs. L&T uses four TBMs named Urja, Avni, Vindhya and Lavi. Two TBMs (Avni and Lavi) are used for tunnel boring southwards from Shivajinagar towards Rashtriya Military School. The other two TBMs (Urja and Vindhya) are used for boring southwards from Cantonment to Shivajinagar after which they will be shifted back to Cantonment to bore tunnels northwards towards Tannery road.

Tunnel boring work by Afcons with three TBMs (Varada, Rudra and Vamika) on the section between Rashtriya Military School and Dairy Circle began during March–June 2021 period.

ITD-Cem began tunnel works during June–August 2021 period on the Venkateshpura-Nagawara section.

Funding

In May 2017, BMRC received in-principle approval from the European Investment Bank (EIB) to fund construction of the Kalena Agrahara-Nagawara line through a 3,700 crore (US$460 million) loan.[19] The BMRC secured an agreement with the Asian Infrastructure Investment Bank (AIIB) on 4 June 2019 to receive a soft loan of 2,255.14 crore (US$280 million) to be repaid over a period of 25 years.[20] The line will also be funded by the Central and State Governments.[21]

Stations

The Pink Line will have 18 stations, of which 12 are underground and 6 are elevated.

Pink Line
# Station Name Connections Layout
EnglishKannada
1 Kalena Agrahara ಕಾಳೇನ ಅಗ್ರಹಾರ Elevated
2 Hulimavu ಹುಳಿಮಾವು Elevated
3 Indian Institute of Management Bengaluru ಭಾರತೀಯ ನಿರ್ವಹಣಾ ಸಂಸ್ಥೆ ಬೆಂಗಳೂರು Elevated
4 Jayaprakash Nagara 4th Phase ಜಯಪ್ರಕಾಶ ನಗರ 4ನೇ ಹಂತ  Orange  (Proposed) Elevated
5 Jayadeva Hospital ಜಯದೇವ ಆಸ್ಪತ್ರೆ  Yellow  (Under Construction) Elevated
6 Tavarekere ತಾವರೆಕೆರೆ Elevated
7 Dairy Circle ಹೈನುಗಾರಿಕೆ ವೃತ್ತ Underground
8 Lakkasandra ಲಕ್ಕಸಂದ್ರ Underground
9 Langford Town ಲಾಂಗ್ಫೋರ್ಡ್ ಪಟ್ಟಣ Underground
10 National Military School ರಾಷ್ಟ್ರೀಯ ಸ್ಯೆನಿಕ ಶಾಲೆ Underground
11 Mahatma Gandhi Road ಮಹಾತ್ಮಾ ಗಾಂಧಿ ರಸ್ತೆ  Purple  Underground
12 Shivajinagara ಶಿವಾಜಿನಗರ Underground
13 Cantonment Railway Station ದಂಡು ರೈಲ್ವೇ ನಿಲ್ದಾಣ Mainline rail interchange Bengaluru Cantonment Underground
14 Pottery Town ಪಾಟರಿ ಪಟ್ಟಣ Underground
15 Tannery Road ಟ್ಯಾನರಿ ರಸ್ತೆ Underground
16 Venkateshpura ವೆಂಕಟೇಶಪುರ Underground
17 Kadugundanahalli ಕಾಡುಗುಂಡನಹಳ್ಳಿ Underground
18 Nagawara ನಾಗವಾರ  Blue  (Under Construction) Underground

See also

References

  1. Mathew Philip, Christin (16 February 2023). "72% Namma Metro tunnelling work over in Bengaluru; Pink Line to be commissioned in March 2025". Times of India.
  2. bmrc.co.in/pdf/phase2/phase2forweb.pdf
  3. "Know the location of new Pink Line metro stations". The Hindu. Retrieved 22 July 2017.
  4. "Bangalore Monorail | Bangalore High Speed Rail". Karnataka.com. 29 October 2010. Retrieved 8 September 2020.
  5. "DPR Phase-2" (PDF).
  6. Menezes, Naveen (6 July 2017). "Civic work to start in a year: Metro Phase II boasts of most expensive underground line". The Economic Times. Retrieved 22 July 2017.
  7. "BMRCL justifies not constructing metro station near Cantonment railway station, face public ire". Asianet News Network Pvt Ltd. Retrieved 9 September 2020.
  8. "Metro: New alignment for longest underground stretch". The New Indian Express. Retrieved 22 July 2017.
  9. "Location of proposed Cantt Metro station moved by 300 metres". Deccan Herald. Retrieved 22 July 2017.
  10. "Bengaluru Cantonment to be suburban rail terminal". Deccan Herald. 11 May 2019. Retrieved 9 September 2020.
  11. "Gottigere-Nagawara Metro line estimated to cost Rs 11,014 crore". The Economic Times. Retrieved 16 March 2017.
  12. "BMRCL to construct a 11,014 Cr metro line in Bengaluru". Dalal Street Investment Journal. Retrieved 16 March 2017.
  13. "Bangalore Metro bids for Phase II". www.tunneltalk.com. Retrieved 8 September 2020.
  14. Menezes, Naveen. "High cost forces BMRCL to cancel underground tenders". The Economic Times. Retrieved 8 September 2020.
  15. "Bangalore Metro Phase II moves ahead". www.tunneltalk.com. Retrieved 8 September 2020.
  16. "Tenders called for Metro phase 2 stations". Deccan Herald. Retrieved 7 March 2017.
  17. "Dairy Circle to Nagawara metro link announced, but it won't be quick – Bangalore Mirror -". Bangalore Mirror. Retrieved 7 March 2017.
  18. "Simplex Infrastructures emerge L1 Bidder in tender for Metro Rail stretch on Bannerghatta Road – RailNews Media India Ltd". Retrieved 8 September 2020.
  19. "Rs 3,700-cr loan likely for Nagawara-Gottigere line". Deccan Herald. Retrieved 11 May 2017.
  20. "Rs 2K cr boost for Phase-II BMRCL underground network". The New Indian Express. Retrieved 6 June 2019.
  21. Briginshaw, David. "India seeks EIB loan for Bangalore metro Line 4". International Rail Journal. Retrieved 2 March 2017.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.